Direct Labor Rate Variance= (Actual Hours * Actual Rate ) - ( Actual Hours * Standard Rate)
= ( 22400* $ 15.40)- (22400* $ 15.00)
=22,400 hours * ( $ 15.40- $15.00)
= $ 8,960 Unfavorable
Since the Actual rate is higher than the standard rate, the variance is Unfavorable.
Hence the correct answer is $ 8,960 Unfavorable
-----------
Direct Labor Efficiency Variance= (Actual Hours * Standard Rate ) - ( Standard Hours * Standard Rate)
= ( 22400* $ 15.00)- (7600 units * 3 Hours * $ 15.00)
= $ 336,000- $ 342,000
= $ 6,000 Favorable
Since the Actual hours is less than the standard hours, the variance is favorable.
Hence the correct answer is $ 6,000 Favorable
Required information [The following information applies to the questions displayed below.] A manufactured product has the...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 7 lbs. @ $8 per lb. 3 hrs. @ $15 per hr. 3 hrs. @ $11 per hr. Actual 53,600 lbs. @ $8.10 per lb. 22,400 hrs. @ $15.40 per hr. $257,700 7,600 1) Compute the standard cost per unit. 2) Compute the total cost variance for June. Complete this question by...
[The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 7 lbs. @ $8 per lb. 3 hrs. @ $15 per hr. 3 hrs. @ $11 per hr. Actual 53,600 lbs. @ $8.10 per lb. 22,400 hrs. @ $15.40 per hr. $ 257,700 7,600 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance by selecting...
The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 6 lbs. @ $8 per lb. 2 hrs. @ $16 per hr. 2 hrs. @ $12 per hr. Actual 48,500 lbs. @ $8.10 per lb. 15,700 hrs. @ $16.50 per hr. $198,000 8,000 Compute the direct labor rate variance and the direct labor efficiency variance. (Indicate the effect of each variance by selecting for...
Required information The following information applies to the questions displayed below) A manufactured product has the following information for June Direct materials Direct labor Overhead Units manufactured Standard Actual 7 lbs. @ $8 per lb. 51,lbs. @ $8.1e per lb. 3 hrs. @ $15 per hr. 21,400 h 4 hrs. @ $15.40 per hr. 3 hrs. @ $13 per hr. $286,400 7,200 Compute the direct labor rate variance and the direct labor efficiency variance. (Indicate the effect of each variance...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (7 lbs. @ $8 per lb.) (2 hrs. @ $15 per hr.) (2 hrs. @ $11 per hr.) Actual 55,900 lbs. @ $8.10 per lb. 15,500 hrs. @ $15.40 per hr. $179, 700 7,900 Compute the direct materials price variance and the direct materials quantity variance. Indicate whether each variance is favorable...
Required information [The
following information applies to the questions displayed below.] A
manufactured product has the following information for June.
Standard Actual Direct materials 5 lbs. @ $9 per lb. 40,400 lbs. @
$9.20 per lb. Direct labor 3 hrs. @ $15 per hr. 23,700 hrs. @
$15.60 per hr. Overhead 3 hrs. @ $12 per hr. $ 294,800 Units
manufactured 8,000 Compute the direct labor rate variance and the
direct labor efficiency variance. (Indicate the effect of each
variance...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials (5 lbs. @ $8 per lb.) 42,000 lbs. @ $8.10 per lb. Direct labor (3 hrs. @ $16 per hr.) 24,700 hrs. @ $16.40 per hr. Overhead (3 hrs. @ $12 per hr.) $ 305,300 Units manufactured 8,300 Compute the direct labor rate variance and the direct labor efficiency variance. Indicate whether each variance is favorable...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $8 per lb.) (3 hrs. @ $16 per hr.) (3 hrs. @ $12 per hr.) Actual 49,000 lbs. @ $8.10 per lb. 24,000 hrs. @ $16.40 per hr. $297,200 8,100 Compute the direct labor rate variance and the direct labor efficiency variance. Indicate whether each variance is favorable or...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $8 per lb.) (2 hrs. @ $16 per hr.) (2 hrs. $12 per hr.) Actual 49,700 lbs. @ $8.10 per lb. 16,000 hrs. @ $16.60 per hr. $202,300 8,200 Compute the direct labor rate variance and the direct labor efficiency variance. Indicate whether each variance is favorable or unfavorable....
Required information The following information applies to the questions displayed below) A manufactured product has the following information for June Standard Direct materials (6 lbs. 58 per lb.) (2 hrs. @ 516 per Direct labor hr.) Overhead (2 hrs. $12 per hr.) Units manufactured Actual lbs. 48, see $8.10 per Ib. 15.20 hrs. $16.50 per 15,700 $198,000 8,000 Compute the direct labor rate variance and the direct labor efficiency variance Indicate whether each variance is favorable or unfavorable AH -...