Required information
[The following information applies to the questions displayed below.]
Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows:
Units | Costs | |||||
Beginning work in process (30% complete) | 127,800 | |||||
Direct materials | $ | 182,000 | ||||
Conversion cost | 334,000 | |||||
Total cost of beginning work in process | $ | 516,000 | ||||
Number of units started | 233,000 | |||||
Number of units completed and transferred to finished goods | 333,800 | |||||
Ending work in process (65% complete) | ? | |||||
Current period costs | ||||||
Direct materials | $ | 497,400 | ||||
Conversion cost | 638,000 | |||||
Total current period costs | $ | 1,135,400 | ||||
Required:
1. Using the weighted-average method of process costing, complete each of the following steps:
a. Reconcile the number of physical units worked on during the period.
|
b. Calculate the number of equivalent units.
|
c. Calculate the cost per equivalent unit.
|
d. Reconcile the total cost of work in process.
|
1a | |||
Physical Units | Physical Units | ||
Beginning Units | 127800 | Units Completed | 333800 |
Units Started | 233000 | Ending Units | 27000 |
Total Units | 360800 | Total Units | 360800 |
1b | |||
Equivalent Units | |||
Physical Units | Direct Materials | Conversion | |
Units Completed | 333800 | 333800 | 333800 |
Ending Inventory | 27000 | 27000 | 17550 |
Total | 360800 | 360800 | 351350 |
c | |||
Direct Materials | Conversion | ||
Beginning work in process costs | 182000 | 334000 | |
Current period costs | 497400 | 638000 | |
Total costs | 679400 | 972000 | |
Divide by Equivalent units | 360800 | 351350 | |
Cost per Equivalent Unit | 1.88304 | 2.76647 | |
d | |||
Direct Materials | Conversion | Total cost | |
Units Completed | 628559 | 923448 | 1552007 |
Ending Inventory | 50842 | 48552 | 99394 |
Total Cost Accounted for | 679401 | 972000 | 1651401 |
Workings for d: | |||
Direct Materials | Conversion | ||
Units Completed | =333800*1.88304 | =333800*2.76647 | |
Ending Inventory | =27000*1.88304 | =17550*2.76647 |
Required information [The following information applies to the questions displayed below.] Saddleback Company makes camping lanterns...
Required information [The following information applies to the questions displayed below.) Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Costs Units 127,800 $ 182,000 334,000 $ 516,000 Beginning work in process (30% complete) Direct materials Conversion cost Total cost of beginning work in process Number of units started Number of units completed and transferred to finished goods Ending work...
[The following information applies to the questions displayed below.] Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Units Costs Beginning work in process (30% complete) 121,300 Direct materials $ 199,000 Conversion cost 351,000 Total cost of beginning work in process $ 550,000 Number of units started 250,000 Number of units completed and transferred to finished goods 335,500 Ending work...
Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Units Costs Beginning work in process (30% complete) 126,800 Direct materials 184,000 Conversion cost 336,000 Total cost of beginning work in process 520,000 Number of units started 235,000 Number of units completed and transferred to finished goods Ending work in process (65% complete) Current period costs 334,000 Direct materials 499,400 640,000...
Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Costs $ 184,000 336,000 520,000 $ Units Beginning work in process (30% complete) 126,800 Direct materials Conversion cost Total cost of beginning work in process Number of units started 235,000 Number of units completed and transferred to 221 00 finished goods Ending work in process (65% complete) Current period costs Direct...
-ok Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: nt ences Units 117,800 Costs $ 192,000 344,000 $ 536,000 Beginning work in process (30% complete) Direct materials Conversion cost Total cost of beginning work in process Number of units started Number of units completed and transferred to finished goods Ending work in process (65% complete) Current period costs Direct...
Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Units Costs Beginning work in process (30% complete) 121,300 Direct materials $ 199,000 Conversion cost 351,000 Total cost of beginning work in process $ 550,000 Number of units started 250,000 Number of units completed and transferred to finished goods 335,500 Ending work in process (65% complete) ? Current period costs Direct...
Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Units 122,800 Costs $ 202,000 354,000 $ 556,000 Beginning work in process (30% complete) Direct materials Conversion cost Total cost of beginning work in process Number of units started Number of units completed and transferred to finished goods Ending work in process (65% complete) Current period costs Direct materials Conversion cost...
Required information [The following information applies to the questions displayed below.] Stem Games manufactures playing cards. It has three departments: Printing, Cutting & Collating, and Wrapping. Transferred-in costs are considered materials costs. The following information is available for the Wrapping department for the month of October: Physical Units 283,000 Beginning work in process (100% complete for materials, 80% complete for conversion) Decks transferred in Decks completed and transferred to Finished Goods Inventory Ending Work in Process (100% complete for materials,...
e-Built Problems Required information (The following information applies to the questions displayed below) Mirada Company manufactures handheld calculators and has the following information available for the month of July. Work in process, July 1 (100% complete for materials, 25% for conversion) Direct materials Conversion cost 124,000 units $ 238,000 $ 392,000 Number of units started 218,000 units July costs Direct materials Conversion cost $ 424,000 $ 482,000 Work in process, July 31 (100% complete for materials, 10% for conversion) 142,000...
! Required information (The following information applies to the questions displayed below.] The following partially completed process cost summary describes the July production activities of the Molding department at Ashad Company. Its production output is sent to the next department. All direct materials are added to products when processing begins. Beginning work in process inventory is 20% complete with respect to conversion. Conversion Equivalent Units of Production Units transferred out Units of ending work in process Equivalent units of production...