Question

Required information [The following information applies to the questions displayed below.] Saddleback Company makes camping lanterns...

Required information

[The following information applies to the questions displayed below.]

Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows:

Units Costs
Beginning work in process (30% complete) 127,800
Direct materials $ 182,000
Conversion cost 334,000
Total cost of beginning work in process $ 516,000
Number of units started 233,000
Number of units completed and transferred to finished goods 333,800
Ending work in process (65% complete) ?
Current period costs
Direct materials $ 497,400
Conversion cost 638,000
Total current period costs $ 1,135,400

Required:

1. Using the weighted-average method of process costing, complete each of the following steps:

a. Reconcile the number of physical units worked on during the period.

Physical Units Physical Units
Beginning Units Units Completed
Units Started Ending Units
Total Units 0 Total Units 0

b. Calculate the number of equivalent units.

Equivalent Units
Physical Units Direct Materials Conversion
Units Completed
Ending Inventory
Total 0 0 0

c. Calculate the cost per equivalent unit.

Direct Materials Conversion
Cost per Equivalent Unit

d. Reconcile the total cost of work in process.

Direct Materials Conversion Total Cost
Units Completed
Ending Inventory
Total Cost Accounted for $0 $0 $0
0 0
Add a comment Improve this question Transcribed image text
Answer #1
1a
Physical Units Physical Units
Beginning Units 127800 Units Completed 333800
Units Started 233000 Ending Units 27000
Total Units 360800 Total Units 360800
1b
Equivalent Units
Physical Units Direct Materials Conversion
Units Completed 333800 333800 333800
Ending Inventory 27000 27000 17550
Total 360800 360800 351350
c
Direct Materials Conversion
Beginning work in process costs 182000 334000
Current period costs 497400 638000
Total costs 679400 972000
Divide by Equivalent units 360800 351350
Cost per Equivalent Unit 1.88304 2.76647
d
Direct Materials Conversion Total cost
Units Completed 628559 923448 1552007
Ending Inventory 50842 48552 99394
Total Cost Accounted for 679401 972000 1651401
Workings for d:
Direct Materials Conversion
Units Completed =333800*1.88304 =333800*2.76647
Ending Inventory =27000*1.88304 =17550*2.76647
Add a comment
Know the answer?
Add Answer to:
Required information [The following information applies to the questions displayed below.] Saddleback Company makes camping lanterns...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.) Saddleback Company makes camping lanterns...

    Required information [The following information applies to the questions displayed below.) Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Costs Units 127,800 $ 182,000 334,000 $ 516,000 Beginning work in process (30% complete) Direct materials Conversion cost Total cost of beginning work in process Number of units started Number of units completed and transferred to finished goods Ending work...

  • [The following information applies to the questions displayed below.] Saddleback Company makes camping lanterns using a...

    [The following information applies to the questions displayed below.] Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Units Costs Beginning work in process (30% complete) 121,300 Direct materials $ 199,000 Conversion cost 351,000 Total cost of beginning work in process $ 550,000 Number of units started 250,000 Number of units completed and transferred to finished goods 335,500 Ending work...

  • Saddleback Company makes camping lanterns using a single production process. All direct materials are added at...

    Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Units Costs Beginning work in process (30% complete) 126,800 Direct materials 184,000 Conversion cost 336,000 Total cost of beginning work in process 520,000 Number of units started 235,000 Number of units completed and transferred to finished goods Ending work in process (65% complete) Current period costs 334,000 Direct materials 499,400 640,000...

  • Saddleback Company makes camping lanterns using a single production process. All direct materials are added at...

    Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Costs $ 184,000 336,000 520,000 $ Units Beginning work in process (30% complete) 126,800 Direct materials Conversion cost Total cost of beginning work in process Number of units started 235,000 Number of units completed and transferred to 221 00 finished goods Ending work in process (65% complete) Current period costs Direct...

  • -ok Saddleback Company makes camping lanterns using a single production process. All direct materials are added...

    -ok Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: nt ences Units 117,800 Costs $ 192,000 344,000 $ 536,000 Beginning work in process (30% complete) Direct materials Conversion cost Total cost of beginning work in process Number of units started Number of units completed and transferred to finished goods Ending work in process (65% complete) Current period costs Direct...

  • Saddleback Company makes camping lanterns using a single production process. All direct materials are added at...

    Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Units Costs Beginning work in process (30% complete) 121,300 Direct materials $ 199,000 Conversion cost 351,000 Total cost of beginning work in process $ 550,000 Number of units started 250,000 Number of units completed and transferred to finished goods 335,500 Ending work in process (65% complete) ? Current period costs Direct...

  • Saddleback Company makes camping lanterns using a single production process. All direct materials are added at...

    Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Units 122,800 Costs $ 202,000 354,000 $ 556,000 Beginning work in process (30% complete) Direct materials Conversion cost Total cost of beginning work in process Number of units started Number of units completed and transferred to finished goods Ending work in process (65% complete) Current period costs Direct materials Conversion cost...

  • Required information [The following information applies to the questions displayed below.] Stem Games manufactures playing cards....

    Required information [The following information applies to the questions displayed below.] Stem Games manufactures playing cards. It has three departments: Printing, Cutting & Collating, and Wrapping. Transferred-in costs are considered materials costs. The following information is available for the Wrapping department for the month of October: Physical Units 283,000 Beginning work in process (100% complete for materials, 80% complete for conversion) Decks transferred in Decks completed and transferred to Finished Goods Inventory Ending Work in Process (100% complete for materials,...

  • e-Built Problems Required information (The following information applies to the questions displayed below) Mirada Company manufactures...

    e-Built Problems Required information (The following information applies to the questions displayed below) Mirada Company manufactures handheld calculators and has the following information available for the month of July. Work in process, July 1 (100% complete for materials, 25% for conversion) Direct materials Conversion cost 124,000 units $ 238,000 $ 392,000 Number of units started 218,000 units July costs Direct materials Conversion cost $ 424,000 $ 482,000 Work in process, July 31 (100% complete for materials, 10% for conversion) 142,000...

  • ! Required information (The following information applies to the questions displayed below.] The following partially completed...

    ! Required information (The following information applies to the questions displayed below.] The following partially completed process cost summary describes the July production activities of the Molding department at Ashad Company. Its production output is sent to the next department. All direct materials are added to products when processing begins. Beginning work in process inventory is 20% complete with respect to conversion. Conversion Equivalent Units of Production Units transferred out Units of ending work in process Equivalent units of production...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT