Year 0:-18100
Year 1:5490
Year 2:5220
Year 3:5050
Year 4:7280
Cumulative net cash flows:
Year 0:-18100
Year 1:5490-18100=-12610
Year 2:5220-12610=-7390
Year 3:5050-7390=-2340
Year 4:7280-2340=4940
Payback period=3+2340/7280=3.32142857 or 3.32 years (Rounded to two decimal places)
Question 2 (1 point) Find the Payback period for the following project: Project Y Initial Outlay...
Find the Payback period for the following project: Project Y Initial Outlay $18,100 Year 1 $5,460 Year 2 $5,520 Year 3 $5,740 Year 4 $6,150 The answer should be calculated to two decimal places.
Find the payback period for the following project initial outlay $18,800 year 1 $5,050 year 2 $5,890 year 3 $5,120 year 4 $6,660 the answer should be calculated to two decimal places
Find the Payback period for the following project: Project Y Initial Outlay $18,900 Year 1 $5,610 Year 2 $5,620 Year 3 $5,860 Year 4 $6,970 The answer should be calculated to two decimal places.
Thanks all! Find the Payback period for the following project: Project Y Initial Outlay $18,800 Year 1 $5,890 Year 2 $5,390 Year 3 $5,670 Year 4 $6,580 The answer should be calculated to two decimal places.
Find the payback period for the following project: Initial Outlay $18,500 Year 1 $5,390 Year 2 $5,140 Year 3 $5,810 Year 4 $7,190 The answer should be calculated to two decimal places.
Find the Payback period for the following project: Project X Initial Outlay $8,920 Year 1 $3,260 Year 2 $3,940 Year 3 $3,990 Year 4 $6,470 The answer should be calculated to two decimal places.
Find the Payback period for the following project: Project X $8,870 Initial Outlay $3,620 Year 1 $3,430 Year 2 Year 3 $3,660 $7,010 Year 4 The answer should be calculated to two decimal places.
Find the Payback period for the following project: Project X Initial Outlay $8,550 Year 1 $3,180 Year 2 $3,590 Year 3 $3,500 Year 4 $5,270 The answer should be calculated to two decimal places.
Find the Payback period for the following project: Project X Initial Outlay $8,210 Year 1 $3,640 Year 2 $3,350 Year 3 $3.770 Year 4 $5,030 The answer should be calculated to two decimal places.
Question 4 (1 point) Find the Discounted Payback period for the following project. The discount rate is 9% Project X Initial Outlay $17,174 Year 1 $5,861 Year 2 $5,397 Year 3 $5,918 Year 4 $8,969 Round the answer to two decimal places.