Solutions:
A.
Make CISCO | Buy CISCO | Net Income Increase / Decrease | |
Direct Material | 43497 | 0 | 43497 |
direct labour | 32805 | 0 | 32805 |
Indirect labour | 3321 | 0 | 3321 |
Utilities | 2997 | 0 | 2997 |
Depreciation | 2930 | 0 | 2930 |
Property taxes | 900 | 0 | 900 |
Insurance | 1490 | 0 | 1490 |
Purchase price | 0 | 83295 | -83295 |
Freight and inspection | 0 | 2835 | -2835 |
Receiving costs | 0 | 1270 | -1270 |
Total Annual Cost | 87940 | 87400 | 540 |
B. The company Should Purchase Because it can save $540.
C. The decision would be different if the company can produce a net income of $3000 with the facilities currently being used to produce CISCO because now it is savings only $540. $3000 net income is higher than $540.
CALCULATOR PRINTER VERSION RACK NI Problem 20-2A The management of Shatner Manufacturing Company is trying to...
Problem 21-2A The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company's finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017. 1. 8,100 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit...
Problem 20-2A The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017. 1. 8,000 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit...
Problem 20-02A a-c The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company's finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1. 7,900 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CIsco, is a component of the company's finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017 1. 8,100 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were: direct...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a co The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1.7,900 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were: direct materials $5.11, direct labor $4.54, indirect...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company's finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1.7.900 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were: direct materials...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1. 8,100 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were: direct...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1. 8,100 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were: direct...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1. 7,900 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were: direct...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017. 1. 8,000 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were: direct...