Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work and should bear higher customer charges. The estimator sums up his position in this way: “My job is to measure the area to be cleared of asbestos. As directed by top management, I simply multiply the square footage by $3.20 to determine the bid price. Since our average cost is only $2.805 per square foot, that leaves enough cushion to take care of the additional costs of nonroutine work that shows up. Besides, it is difficult to know what is routine or not routine until you actually start tearing things apart.” To shed light on this controversy, the company initiated an activity-based costing study of all of its costs. Data from the activity-based costing system follow:

Activity Cost Pool Activity Measure Total Activity
Removing asbestos Thousands of square feet 850 thousand square feet
Estimating and job setup Number of jobs 400 jobs
Working on nonroutine jobs Number of nonroutine jobs 100 nonroutine jobs
Other (organization-sustaining costs and idle capacity costs) None

Note: The 100 nonroutine jobs are included in the total of 400 jobs. Both nonroutine jobs and routine jobs require estimating and setup.

Disposal fees 824,000
Equipment depreciation 108,000
On-site supplies 64,000
Office expenses 340,000
Licensing and insurance 540,000
Total cost $

2,316,000

Wages and salaries Disposal fees Equipment depreciatiorn On-site supplies office expenses Licensing and insurance Total cost $ 440 000 824,000 108,000 64,000 340,000 540,000 $ 2,316,000 Distribution of Resource Consumption Across Activities Estimating Working on Removing and Job Nonroutine Asbestos 50% 70% 40% 608 15% 30% Setup 108 08 58 30% 35% 08 Jobs 308 30% 20% 10% 20% 608 Other Total 1008 1008 1008 1008 1008 100% 108 0% 35% Wages and salaries Disposal fees Equipment depreciation On-site supplies Office expenses Licensing and insurance 30% 108 Required: 1. Perform the first-stage allocation of costs to the activity cost pools. 2. Compute the activity rates for the activity cost pools. 3. Using the activity rates you have computed. determine the total cost and the average cost per tho following jobs according to the activity-based costing system. a. A routine 1.000-square-foot asbestos removal job. b. A routine 2,000-square-foot asbestos removal job. c. A nonroutine 2.000-square-foot asbestos removal job. & Answer is complete but not entirely correct.

Required:

1. Perform the first-stage allocation of costs to the activity cost pools.

2. Compute the activity rates for the activity cost pools.

3. Using the activity rates you have computed, determine the total cost and the average cost per thousand square feet of each of the following jobs according to the activity-based costing system.

a. A routine 1,000-square-foot asbestos removal job.

b. A routine 2,000-square-foot asbestos removal job.

c. A nonroutine 2,000-square-foot asbestos removal job.

Answer is complete but not entirely correct. Complete this question by entering your answers in the tabs below. Req 2Req 3A to 3C Rea 1 Perform the first-stage allocation of costs to the activity cost pools. Removing asbestos Estimating Working on Nonroutine and Job Other Total Wages and salaries Disposal fees Equipment depreciation On-site supplies Office expenses Licensing and insurance Total cost $ 220,000 44,000 132000 44,000440,000 824,000 432005,400 2160037,800108.000 64,000 51,000119,00068,00102000 340,000 0 4000540,00 $ 1.091,400 5 187.600 5 799 200 237 800 218000 247.200 576,800 38,4009.2006.400 162,000 324,000 Req 2 > K Prev 6 of 6 Next>

following jobs according to the activity-based costing system. a. A routine 1,000-square-foot asbestos removal job. b. A routine 2,000-square-foot asbestos removal job. c. A nonroutine 2,000-square-foot asbestos removal job. Answer is complete but not entirely correct. Complete this question by entering your answers in the tabs below. Req 1 Req 2 Req 3A to 3C | Compute the activity rates for the activity cost pools. Activity Cost Pool Removing asbestos Estimating and job Working on nonroutine jobs Activity Rate 1.284 per thousand square $ 469 per job 7,992 e per nonroutine job |$ Req 1 Req 3A to 3C > K Prev 6 of 6 Next >3. Using the activity rates you have computed, determine the total cost and the average cost per thousand square feet of eac following jobs according to the activity-based costing system. a. A routine 1,000-square-foot asbestos removal job. b. A routine 2,000-square-foot asbestos removal job. c. A nonroutine 2,000-square-foot asbestos removal job. Answer is complete but not entirely correct. Complete this question by entering your answers in the tabs below. Req 1 Req 2Req 3A to c Using the activity rates you have computed, determine the total cost and the average cost per thousand square feet of each of the following jobs according to the activity-based costing system. (Round the Average Cost per thousand square f decimal places.) a. A routine 1,000-square-foot asbestos removal job. b. A routine 2,000-square-foot asbestos removal job. c. A nonroutine 2,000-square-foot asbestos removal job. Req 3A to 3C eet to 2 Show less & Routine Nonroutine Routine 1,000 sq. ft. job $ 2,000 sq. ft. job 2,000 sq. ft job 1,753 O s 3.037 O s 10.560 Total cost of the job 2.568.00 * Average Cost per thousand square feet |s 1,284 00 C)s 2.568.00 C)s Req2 Req 3A to 3C くPrev 6016 ::: Next

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

1

First stage allocation of cost to activity cost pools

Particulars

Removing Asbestos

Estimating
and Job Setup

Working on non routine job

Others

Total Cost

Amount

Amount

Amount

Amount

Wages & Salaries

220000

44000

132000

44000

440000

Disposal Fees

576800

0

247200

0

824000

Equipment depreciation

43200

5400

21600

37800

108000

On Site Supplies

38400

19200

6400

0

64000

Office Expenses

51000

119000

68000

102000

340000

Licensing and Insurance

162000

0

324000

54000

540000

Total

1091400

187600

799200

237800

2316000

2

Determination of activity rate for each activity

Activity

Estimated Overhead Cost

Activity Base

Usage of Activity Base

Activity Rate

Removing Asbestos

1091400

Number of Jobs

850

$1,284.00

Estimating and Job Setup

$187,600.00

Number of non routine jobs

400

$469.00

Working on non routine job

$799,200.00

No allocation

100

$7,992.00

3

3-A

Computation of total cost and average cost per thousand square feet - Routine 1000 Square feet job

Particulars

Amount

Removing Asbestos

$1,284.00

Estimating and Job Setup

$469.00

Working on non routine job

$0.00

Total cost of job

$1,753.00

Average cost per thousand square feet (1753/1)

$1,753.00

3-B

Computation of total cost and average cost per thousand square feet - Routine 2000 Square feet job

Particulars

Amount

Removing Asbestos (1284x2)

$2,568.00

Estimating and Job Setup

$469.00

Working on non routine job

$0.00

Total cost of job

$3,037.00

Average cost per thousand square feet(3037/2)

$1,518.50

3-C

Computation of total cost and average cost per thousand square feet - Routine 2000 Square feet job

Particulars

Amount

Removing Asbestos (1284x2)

$2,568.00

Estimating and Job Setup

$469.00

Working on non routine job

$7,992.00

Total cost of job

$11,029.00

Average cost per thousand square feet(11029/2)

$5,514.50

Routine 1000
Square feet job

Routine 2000
Square feet job

Non routine 2000 Square feet job

Total cost of job

$1,753.00

$3,037.00

$11,029.00

Average cost per thousand square feet

$1,753.00

$1,518.50

$5,514.50

Add a comment
Know the answer?
Add Answer to:
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There...

    Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...

  • Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...

    Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...

  • Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...

    Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...

  • Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...

    Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...

  • 1.34 points Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings....

    1.34 points Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than...

  • Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...

    Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine...

  • Mercer Asbestos Removal Company removes potentially toxic asbestos Insulation and related products from bulldings. There has...

    Mercer Asbestos Removal Company removes potentially toxic asbestos Insulation and related products from bulldings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos Insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos contaminated celling plaster in industrial buildings. The on-site supervision believe that nonroutine work is far more expensive than routine...

  • Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...

    Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...

  • Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...

    Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work such as removal of asbestos insulation around heating pipes in older homes and nonroutine work such as removing asbestos contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine...

  • Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...

    Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT