Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (L02-1, LO2-2, LO2-3) Landen Corporation uses a job-order costin
$ 6.60 per DLH 1. Direct labor-hours: a. Predetermined overhead rate b. Total manufacturing cost of Job 550 c. Selling price
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

Plantwide predetermined overhead rate = Estimated manufacturing overhead / Estimated direct labor hours

Plantwide predetermined overhead rate = $350,000/125,000 + $3.80 = $6.6 per direct labor hour

Job 550
Direct material $201
Direct labor 240
Manufacturing overhead applied (15*$6.6) 99
Total manufacturing cost $540

Selling price = $540 + 200% = $1,620

2.

Plantwide predetermined overhead rate = Estimated manufacturing overhead / Estimated machine hours

Plantwide predetermined overhead rate = $350,000/62,500 + $7.60 = $13.2 per machine hour

Job 550
Direct material $201
Direct labor 240
Manufacturing overhead applied (5*$13.2) 66
Total manufacturing cost $507

Selling price = $507 + 200% = $1,521

Add a comment
Know the answer?
Add Answer to:
Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (L02-1, LO2-2, LO2-3) Landen Corporation uses a job-order costing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (L02-1, LO2-2, LO2-3) Landen Corporation uses a job-order costing...

    Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (L02-1, LO2-2, LO2-3) Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 1 40,000 70,000 $784, eee $ 2.00 $ 4.00 During the year, Job 550 was started and completed. The following information...

  • Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (L02-1, LO2-2, LO2-3) Landen Corporation uses a job-order costing...

    Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (L02-1, LO2-2, LO2-3) Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 130,000 65,000 $364,000 $ 4.00 $ 8.00 During the year, Job 550 was started and completed. The following information is available...

  • Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing...

    Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 60,000 30,000 $180,000 $ 1.00 $ 2.00 During the year, Job 550 was started and completed. The following information is available...

  • Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing...

    Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 120,000 60,000 $336,000 $ 3.60 $ 7.20 During the year, Job 550 was started and completed. The following information is available with...

  • Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing...

    Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 80,000 40,000 $ 240,000 $ 1.80 $ 3.60 During the year, Job 550 was started and completed. The following information is...

  • Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3) Landen Corporation uses a job-order costing...

    Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3) Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 80,000 40,000 $240.000 $ 1.80 $ 3.60 During the year, Job 550 was started and completed. The following information is available...

  • Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing...

    Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production 140,000 Machine-hours required to support estimated production 70,000 Fixed manufacturing overhead cost $ 784,000 Variable manufacturing overhead cost per direct labor-hour $ 2.00 Variable manufacturing overhead cost per machine-hour $ 4.00 During the year, Job 550 was started and completed. The following information is...

  • Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing...

    Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production 150,000 Machine-hours required to support estimated production 75,000 Fixed manufacturing overhead cost $ 420,000 Variable manufacturing overhead cost per direct labor-hour $ 4.60 Variable manufacturing overhead cost per machine-hour $ 9.20 During the year, Job 550 was started and completed. The following information is...

  • Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3) Landen Corporation uses a job-order costing...

    Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3) Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed Manufacturing overhead cost Variable manufacturing overhead cont per direct labor-hour Variable manufacturing overhead cost per machine-hour 95,000 47,500 $266,000 $ 2.60 $ 5.20 During the year, Job 550 was started and completed. The following information is available...

  • Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3] 0.66 Landen Corporation uses a job-order...

    Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3] 0.66 Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: points eBook Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 140,000 70,000 $784,000 $ 2.00 $ 4.00 Print References During the year, Job 550 was started and completed....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT