CARDELL COMPANY
(a) Pre-determined overhead rate=$ 0.8 overheads per $ of direct labor cost
Estimated annual overhead=$ 7,60,000
Estimated annual direct labor cost=$ 9,50,000
Pre-determined overhead rate=$760000/$950000=$0.8 overheads per $ of direct labor cost
(b) Manufacturing Overheads underapplied=$2400
Total Overheads=Indirect Material+Indirect Labor+Other manufacturing overheads
Total overheads incurred=$3000+$2000+$ 59800=$64800
Total overheads applied =$41600+$ 20800=$ 62400
Overheads underapplied=$ 64800-$ 62400=$ 2400
Particulars |
Job A16 |
Job B17 |
Direct Materials |
$ 27000 |
$ 21000 |
Direct Labor |
$ 52000 |
$ 26000 |
Overheads |
$ 41600 (52000*0.8) |
$ 20800 (26000*0.8) |
Total Cost |
$ 120600 |
$ 67800 |
Predetermined overhead rate Class Problem Cardell Company applies overhead based on direet labor costs. The company...
Waterways Problem 02 a-c (Part Level Submission) Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company’s inventory on December 2 for $5,091; on December...
Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company’s inventory on December 2 for $5,064; on December 8 for $1,068; and on December 14...
Waterways Problem 02 a-c Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company’s inventory on December 2 for $5,097; on December 8 for $1,065;...
Waterways has two major public park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special- order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company's inventory on December 2 for $5,031; on December 8 for $1,065; and on...
Waterways has two major public park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company's inventory on December 2 for $5,094; on December 8 for $1,056; and on December...
NE Waterways Problem 02 a-c Waterways has two major public park projects to provide with comprehensive irrigation in one of its service locations this month. Job 357 and Job K52 Involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company's Inventory on December 2 for $5,067; on December 8...
Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company’s inventory on December 2 for $5,091; on December 8 for $1,050; and on December 14...
Class drill3 Cardella Company applies overhead on the basis of direct labor costs. The company estimates annual overhead costs will be $760,000 and annual direct labor costs will be $950,000. During February, Cardella works on two jobs: A16 and B17. Summary data concerning these jobs are as follows. Manufacturing Costs Incurred Purchased $54,000 of raw materials on account. Factory labor $76,000, plus $4,000 employer payroll taxes. Manufacturing overhead exclusive of indirect materials and indirect labor $59,800. Assignment of Costs Direct...
Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company's inventory on December 2 for $5,106; on December 8 for $1,056; and on December 14...
Question 2 View Policies Current Attempt in Progress Waterways has two major public park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December Raw materials were requisitioned from the company's inventory on December 2 for $5067;...