*Please rate thumbs up
Compute the payback statistic for Project B if the appropriate cost of capital is 10 percent...
Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: Cash flow: -$11,000 $3,350 $4,130 $1,520 $0 $1,000 Payback years Should the project be accepted or rejected? accepted rejected
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 10 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: Cash flow: 1 1 -$12,900 $3,540 2 $4,560 3 $1,900 4 $0 5 $1,380 Discounted payback period years
Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: Cash flow: 0 -$12,500 1 $3,500 2 $4,480 3 $1,820 4 $0 5 $1,300 Payback years Should the project be accepted or rejected? accepted rejected
Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: 0 1 2 3 4 5 Cash flow: –$11,400 $3,390 $4,260 $1,600 $0 $1,080 Should the project be accepted or rejected? accepted rejected
Compute the payback statistic for Project B if the appropriate cost of capital is 13 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: 0 1 2 3 4 5 Cash flow: −$11,800 $3,430 $4,340 $1,680 $0 $1,160 NPV? Should the project be accepted or rejected?
Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent and the maximum allowable payback period is three years. Should the project be rejected or accepted? (If the project never pays back, then enter a "0" (zero). Project B Time: 0 1 2 3 4 5 Cash flow: –$11,700 $3,420 $4,320 $1,660 $0 $1,140
Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: 0 1 2 3 4 5 Cash flow: – $12,600 $3,510 $ 4,500 $1,840 $0 $1,320 Should the project be accepted or rejected?
Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (Round your answer to 2 decimal places. If the project never pays back, then enter a "0" (zero).) Project B Time: 0 1 2 3 4 5 Cash flow: –$11,300 $3,380 $4,240 $1,580 $0 $1,060 Payback years ___________ Should the project be accepted or rejected? ______________
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: Cash flow: 0 -$11,600 1 $3,410 $4,300 34 $1,640 $0 $1,120 Discounted payback period 0 years Should the project be accepted or rejected? accepted rejected...
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: Cash flow: -$2,800 $1,070 $1,020 $889 $660 $460 Payback years Should the project be accepted or rejected? accepted rejected