job sheet | ||||||||
Materials | labor | overhead | total | |||||
job 301 | 3,290 | 3,080 | 1508 | 7,878 | ||||
job 302 | 4,025 | 4,160 | 2204 | 10,389 | ||||
job 303 | 2,660 | 2,080 | 1740 | 6,480 | ||||
job 304 | 9,030 | 7,640 | 4640 | 21,310 | ||||
job305 | 5,740 | 5,810 | 2320 | 13,870 | ||||
job 306 | 4,170 | 3,710 | 1508 | 9,388 | ||||
total | 28,915 | 26,480 | 13920 | 69,315 | ||||
Entries | Description | Debit | Credit | |||||
a. | Raw materials inventory | 32,760 | ||||||
Accounts payable | 32,760 | |||||||
b. | Work in process inventory | 55,395 | ||||||
Factory overhead | 5750 | |||||||
Raw materials inventory | 30,115 | |||||||
Factory payroll | 31,030 | |||||||
c. | Factory overhead | 6,300 | ||||||
Accounts payable | 6,300 | |||||||
d. | Factory overhead | 2,200 | ||||||
Accumulated depreciation | 2,200 | |||||||
e. | Work in process inventory | 13,920 | ||||||
Factory overhead | 13,920 | |||||||
f. | Finished goods inventory | 38,617 | ||||||
work in process inventory | 38,617 | |||||||
g. | Accounts receivable | 38100 | ||||||
sale | 38,100 | |||||||
cost of good sold | 32,137 | |||||||
finished goods inventory | 32,137 | |||||||
2) | work in process | |||||||
b. | 55,395 | 38,617 | f. | |||||
e. | 13,920 | |||||||
bal | 30,698 | |||||||
Finished goods | ||||||||
f. | 38,617 | 32,137 | g. | |||||
bal | 6,480 | |||||||
3) | Schedule of unfinished jobs | |||||||
job | Direct | direct | FOH | total | ||||
materials | labor | |||||||
job 304 | 9,030 | 7,640 | 4640 | 21,310 | ||||
job 306 | 4,170 | 3,710 | 1508 | 9,388 | ||||
Balance in work in process ,april 30 | 30,698 | |||||||
4) | Schedule of completed jobs | |||||||
job | Direct | direct | FOH | total | ||||
materials | labor | |||||||
job 303 | 2,660 | 2,080 | 1,740 | 6,480 | ||||
Only need # 3&4 PR 17-2A Entries and schedules for unfinished jobs and completed jobs Sinatra...
uu e the entries to record the summarized operations. PR 16-2A Entries and schedules for unfinished jobs and complete Kurtz Fencing Inc. uses a job order cost system. The following related to production for March, the first month of operations. A. Materials purchased on account, $45,000. B. Materials requisitioned and factory labor used: hed jobs and completed jobs Obj. 2 The following data summarize the operations Job 301 302 303 304 305 306 For general factory use Materials $1,850 3,150...
Entries and Schedules for Unfinished Jobs and Completed Jobs Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations: Materials purchased on account, $3,390. Materials requisitioned and factory labor used: Job Materials Factory Labor 301 $2,800 $2,870 302 3,420 3,870 303 2,270 1,890 304 7,670 7,120 305 4,870 5,420 306 3,560 3,440 For general factory use 950 4,250 Factory overhead costs incurred on account, $5,350....
Entries and Schedules for Unfinished Jobs and Completed Jobs Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations: a. Materials purchased on account, $2,860 b. Materials requisitioned and factory labor used Job 301 302 303 304 305 306 For general factory use Materials Factory Labor $3,380 4,120 2,740 9,260 5,880 4,290 1,150 $2,940 3,970 1,940 7,290 5,560 3,530 4,350 C. Factory overhead costs incurred...
Entries and Schedules for Unfinished Jobs and Completed Jobs Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations: a. Materials purchased on account, $3,090. b. Materials requisitioned and factory labor used: Job Materials Factory Labor 301 $1,950 $3,010 302 2,380 4,060 303 1,580 1,990 304 5,340 7,460 305 3,390 5,690 3,610 306 2,480 For general factory use 660 4,450 C. Factory overhead costs incurred...
Entries and Schedules for Unfinished Jobs and Completed Jobs Staircase Equipment Company uses a job order cost system. The following data summarize the operations related to production for April 2014, the first month of operations: a. Materials purchased on account, $3,360. b. Materials requisitioned and factory labor used: Job Materials Factory Labor No. 301 $2,780 $2,320 No. 302 3,390 3,130 No. 303 2,250 1,530 No. 304 7,620 5,750 No. 305 4,840 4,380 No. 306 3,530 2,780 For general factory use...
Entries and schedules for unfinished jobs and completed Jobs Instructions Chart of Accounts Amount Descriptions Journal Accounts Schedule of Unfinished Jobs Instructions Kurtz Fencing Inc. uses a job order cost system. The following data summarize the operations related to production for March, the first month of operations: a. Materials purchased on account, $28,580. b. Materials requisitioned and factory labor used: Job Factory Labor $2.760 301 302 3,770 303 1,860 Materials $3.030 3,490 2,520 8,290 5,000 3,890 1,130 305 306 For...
Entries and schedules for unfinished jobs and completed jobs Instructions Chart of Accounts Amount Descriptions Journal Accounts Schedule of Unfinished Jobs Schedule of Instructions Tybee Industries Inc, uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations a Materials purchased on account, $29,800 b. Materials requisitioned and factory labor used: Job 301 Materials $ 2,960 3,620 2,400 8,100 5,100 3.750 1,080 Factory Labor 52.775 3,750 1.875 6.360 5.250...
Need only 4 this Schedule of Unfinished Jobs Instructions Kurtz Fencing Inc. uses a job order cont system. The following data summarize the operations related to production for March, the first month of operations a Materials purchased on account. $45,000. b. Materials requisitioned and factory labor used: Job Materials Factory Labor 301 $ 1,850 $2.500 3.150 2,200 5250 304 305 306 For general factory use 4.230 1.770 1.200 2.400 8.225 2.000 5.000 c. Factory overhead costs incurred on account. $1.800...
Schedule of Completed Jobs and only to entries You have all the information that was provided for this assignment the instructions and amount description is what answers this! Instructions Kurtz Fencing Inc, uses a job order cost systern. The following data summarize the operations related to production for March, the first month of operations a Materials purchased on account, $45,000. b. Materials requisitioned and factory labor used: Job Materials Factory Labor 301 $ 1,850 500 7220 303 2,200 5250 304...
of goodS sond, i. Cost Instructions Journalize the entries to record the summarized operations J1,I PR 19-2A Entries and schedules for unfinished jobs and com Tybee Industries Inc. uses a job order cost system. The foll operations related to production for January, the first month of o a. Materials purchased on account, $29,800. following data summarize data b. Materials requisitioned and factory labor used: Chapter 19 Job Order Costing 957 Job 301 302 Materials $2,960 Factory Labor $2,775 3,750 1,875...