Question

Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

Job Costs Using Activity-Based Costing

Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows:

Activity Cost Driver Amount of Driver
Materials handling $92,400 Number of moves 4,000
Engineering 93,600 Number of change orders 6,000
Other overhead 230,300 Direct labor hours 49,000

Heitger worked on four jobs in July. Data are as follows:

Job 13-43 Job 13-44 Job 13-45 Job 13-46
Beginning balance $23,900 $18,200 $2,000 $0
Direct materials $5,400 $9,100 $10,200 $9,800
Direct labor cost $880 $1,020 $1,560 $120
Job 13-43 Job 13-44 Job 13-45 Job 13-46
Number of moves 47 53 31 6
Number of change orders 33 35 21 15
Direct labor hours 880 1,020 1,560 120

By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process.

. Calculate the activity rates for each of the three overhead activities. Round all activity rates to the nearest cent.

Materials handling rate
Engineering rate
Other overhead rate

2. Calculate the balance in Work in Process on July 31.

3. Calculate the cost of goods sold for July.

4. What if Job 13-46 required no engineering change orders? What is the difference in the new cost of Job 13-46? How would the cost of the other jobs be affected?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Calculate the activity rates for each of the three overhead activities. Round all activity rates to the nearest cent.

Activity Cost Amount of Driver Activity Rate
Materials handling 92,400 4,000 23.10 per move
Engineering 93,600 6,000 15.60 per change order
Other overhead 2,30,300 49,000 4.70 per direct labor hour

2. Calculate the balance in Work in Process on July 31.

Job 13-43 Job 13-44 Job 13-45 Job 13-46
Beginning balance 23,900 18,200 2,000 0
Direct materials 5,400 9,100 10,200 9,800
Direct labor cost 880 1,020 1,560 120
Material handling @23.10 1,086 1,224 716 139
Engineering @ 15.60 514.8 546 327.6 234
Other overhead @ 4.70 4,136 4,794 7,332 564
Total costs 35,917 34,884 22,136 10,857
Balance in Work in Process on July 31 Cost of Jobs
Job 13-45 22,136
Job 13-46 10,857
balance in Work in Process on July 31 32,992

3. Calculate the cost of goods sold for July.

Cost of goods sold for July
Job 13-43 35,917
Job 13-44 34,884
Cost of goods sold for July 70,801

4. What if Job 13-46 required no engineering change orders? What is the difference in the new cost of Job 13-46? How would the cost of the other jobs be affected?

Job 13-46
Beginning balance 0
Direct materials 9,800
Direct labor cost 120
Material handling @23.10 139
Other overhead @ 4.70 564
New Total costs 10,623

The cost of the other jobs will get increased

Add a comment
Know the answer?
Add Answer to:
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

    Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $49,400 Number of moves 2,000 Engineering 129,000 Number of change orders 7,500 Other overhead 321,300 Direct labor hours 51,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...

  • Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

    Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $55,000 Number of moves 2,500 Engineering 101,500 Number of change orders 7,000 Other overhead 180,000 Direct labor hours 50,000 Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

  • Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

    Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $121,000 Number of moves 5,000 Engineering 125,250 Number of change orders 7,500 Other overhead 272,600 Direct labor hours 47,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...

  • Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

    Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $71,100 Number of moves 3,000 Engineering 105,300 Number of change orders 6,500 Other overhead 238,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...

  • Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

    Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $56,250 Number of moves 2,500 Engineering 142,500 Number of change orders 9,500 Other overhead 209,100 Direct labor hours 51,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...

  • Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

    Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $ 72,000 Number of moves 3,000 Engineering 165,000 Number of change orders 10,000 Other overhead 280,000 Direct labor hours 50,000 Heitger worked on four jobs in July. Data are as follows: Beginning balance $0 Job...

  • Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

    Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $56,250 Number of moves 2,500 Engineering 142,500 Number of change orders 9,500 Other overhead 209,100 Direct labor hours 51,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...

  • Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs....

    Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $48,200 Number of moves 2,000 Engineering 157,700 Number of change orders 9,500 Other overhead 256,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job 13-45 Job 13-46 Beginning balance...

  • How would you answer this? Calculator Heitger Company is a job-order costing firm that uses activity-based...

    How would you answer this? Calculator Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $ 72,000 Number of moves 3,000 Engineering Number of change orders 10,000 165,000 280,000 Other overhead Direct labor hours 50,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job...

  • Beginning $24,100 $17,600 $3,700 $0 balance Direct $6,000 materials $8,800 $10,500 $9,700 Direct labor $980 cost...

    Beginning $24,100 $17,600 $3,700 $0 balance Direct $6,000 materials $8,800 $10,500 $9,700 Direct labor $980 cost $980 $1,660 $150 Job 13- Job 13- Job 13- Job 13- 43 44 45 46 Number of moves 43 54 26 5 Number of 29 39 17 16 change orders Direct labor hours 980 980 1,660 150 By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process, Required: 1. Calculate the activity rates for each...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT