Maximum inventory level= Q (1-d/p)
Q- order quantity, here, taken as optimal production quantity
d-daily demand in units
p-daily production capacity in units
Maximum inventory level = 817 (1- 40/100)
= 490.2 units
Therefore option (c) is correct
QUESTION 14 In a non-instantaneous receipt model (i.e., production run model), daily demand is 40 units...
in a noninstantaneous receipt model daily is 85 units and daily production is 120 units. the C o is $70 and Cc is $10 per unit per year what is the maximum inventory level? they are open 365 days a year.
PLEASE DO BY HAND! DQuestion 12 6 pts Ace Manufacturing produces commercial lawnmowers units in batches. the company estimates the demand for the year is 10,000 units. It costs about $80 to set up the manufacturing process, and the carrying cost is about 70 cents per unit per year. When the production process has been set up, 120 lawnmowers units can be made daily. The demand during the production period is approximately 60 units per day. The company operates its...
4. Dream Weavers manufactures wool-mix carpets. The cost of setting up the production process for a production run is $800. The annual demand is estimated to be 28,000 yards of carpet. The annual carrying cost is S5 per yard. The manufacturing facility operates 350 days per year and produces 400 yards of carpet per day a. Find the optimal production run quantity for Dream Weavers. b. Find the minimum total inventory cost per year. c. Find the optimal length of...
4.a) Find the savings between the total cost of the current production run size and the optimal run size. b) Find the additional savings in production costs and ordering and holding costs with the proposed project. Calculate the payback period for the investment in the project. The anticipated annual demand for a chemical product distributed by the Seanna Chemical Group is 25,000 tons per year for the coming year. The company is currently producing the product with a capacity of...
An automobile manufacturer stocks a certain inventory item. The daily demand for the inventory item is 20 units. The company estimates its annual holding cost for this item to be $10 per unit. The cost to place and process an order from the supplier is $200. The company operates 300 days per year, and the lead time to receive an order from the supplier is 3 working days on average. (a) Find the economic order quantity. (b) Find...
Smith's Florist popular flower bouquet has a weekly demand of 40 units. Each bouquet is sold for $100. The ordering cost is $60 per order. The carrying cost is 30% of the selling price per unit per year. The store operates 50 weeks a year. Required: i. Compute the Economic Order Quantity (EOQ) ii. What is the total annual carrying cost this year? iii. What is the time between orders (i.e. length of an order cycle) in weeks using EOQ.
Given an EOQ model with shortages in which annual demand is 5000 units, Co = $120, Cc = $15 per unit per year, and Cs = $40, what is the order quantity?
A company follows an EPQ model with production rate -180 units per month and a demand of 1,000 units per year the cost for production 35% of annual interest rate 4. 90. Starting the production line has a cost of $950 the holding cost is V hi a) b) Calculate optimal Q Draw the EPQ process and calculate total cycle time and production time use the diagram to get equations
4) S uppose that lead-time demand is normally distributed with a mean of 100 units and a standard deviation of 20 units, If the firm wants to maintain 92% service Jevel, what should the reorder point be? 2-1.88 Pop-137.6units 5) We use 1,500 per year of a certain subassembly that has an annual holding cost of $45 placed costs us $150. We operate 300 days per year and have found that an order must be placed with our supplier 6...
A chemical plant produces sodium bisulfate in 150 kg bags. Demand for this product is 20 tonnes per day. The capacity for producing this product is 55 tonnes per day. Setup cost is $320, and storage and handling costs are $150 per tonne per year. The company operates 220 days a year. (Note: 1 tonne = 1,000 kg). a. What is the optimal number of bags per production run? (Round your intermediate calculations to 2 decimal places and the final...