With interest at 10%, what is the benefit-cost ratio for this government project?
Initial Cost | $244,793 |
Additional costs at the end of year 1 and year 2 | $22,478/year |
Benefits at end of year 1 and year 2 | $0/year |
Annual benefits at end of year 3 through year 10 | $96,236/year |
Enter your answer as follow: 12.34
Calculating the B/C Ratio using Present Worth Method.
Step – 1 Calculate the PW of the Costs
PW of the Costs = Initial Cost + PW of additional Cost at 1st and 2nd year
PW of the Costs = $244,793 + $22,478 (P/A, 10%, 2)
PW of the Costs = $244,793 + $22,478 (1.73554) = 283,804
Step – 2 Calculate the PW of Benefits
PW of Benefits = $96,236 (P/A, 10%, 8) (P/F, 10%, 2)
PW of Benefits = $96,236 (5.33493) (0.82645) = 424,310
Step – 3 Calculate the Benefit-Cost Ratio
B/C ratio = PW of Benefits ÷ PW of Costs
B/C ratio = 424,310 ÷ 283,804
B/C Ratio = 1.495 or rounded to two decimal value it will be 1.50
The benefit cost ratio will be 1.50.
As the B/C Ratio is greater than ONE, accept the project.
With interest at 10%, what is the benefit-cost ratio for this government project? Initial Cost $244,793...
With interest at 10%, what is the benefit-cost ratio for this government project? $208,355 Initial Cost Additional costs at the end of year 1 and year $23,720/year Benefits at end of year 1 and year 2 $0/year Annual benefits at end of year 3 through year. $91,825/year 10 Enter your answer as follow: 12.34
uestion6 0.25 pts with interest at 10%, what is the benefit-cost ratio for this government project? nitial Cost Additional costs at the end of year 1 and year 2 Benefits at end of year 1 and year so/year 2 Annual benefits at end of year 3 $101015/year through year 10 $203180 $29800/year Enter your answer as follow: 12.34
Question 18 7 pts At 10% interest, what is the conventional benefit/cost ratio for the following government project using PW? Initial cost-$200,000 Additional costs at end of Years 1 and 2 $30,000 Benefits at end of Years 1 and 2 $0 Annual benefits of end of Years 3 to 10 $90,000
A project has a first cost of $113,164, will produce a $65,390 net annual benefit, and has annual maintenance costs of $25,793 over its 25-year life. It has a salvage value of $36,264 at the end of its life. Using a MARR of 2%, what is the benefit-cost ratio of the project? Enter your answer as: 1.23 (Calculate to 2 decimal places only.)
Problem 09.010 Benefit/Cost Analysis of a Single Project The estimated annual cash flows for a proposed municipal government project are costs of $710,000 per year, benefits of $910,000 per year, and disbenefits of $160,000 per year. Calculate the conventional B/C ratio at an interest rate of 12% per year, and determine if it is economically justified. The B/C ratio is The project is economically (Click to select) A
Problem 09.010 Benefit/Cost Analysis of a Single Project The estimated annual cash flows for a proposed municipal government project are costs of $800,000 per year, benefits of $910,000 per year, and disbenefits of $230,000 per year. Calculate the conventional B/C ratio at an interest rate of 9% per year, and determine if It is economically justified. The B/C ratio is The project is economically not justified
Find the benefit-cost ratio and profitability index for group’s company startup at an interest rate of 10% Initial Investment for Company Startup: $2,000,000 Anticipated Annual Costs: Annual Operating and Maintenance Costs $20,000 Annual Material Costs $50,000 Annual Personnel Costs $80,000 Anticipated Revenue: Year 1: $590,000 Year 2: $570,000 Year 3: $520,000 Year 4: $150,000 Year 5: $580,000 Year 6: $930,000 ...
Benefit-Cost Analysis Table Road Project Analysis Government XYZ is considering the addition of a tool road segment to the regional road system. The projected costs and benefits for it has been estimated and converted into monetary units. The resulting data is outlined in the Table below. Furthermore, the discount rate has been determined to be 7% based on the entity’s weighted average cost of capital (WACC). Based on a benefit-cost analysis, determine whether this “pilot project” will provide a net...
Name 4) Fill in the following table to caloulate the net present vallue and benefit/cost ratio of each investment. Round to the nearest dollar or hundredth in the benefit/cost ratio. Investment B Investment A Yearly After-tax Yearly Present After-tax Present After-tax After-tax Present Value Year Value Present Value Year Value x of Benefits of Benefits Benefit Benefit Factor Factor 3200 1850 2 1925 2 3200 2567 3200 3 4 3850 3000 3000 3850 Total 6 5133 Less Initial Cost 7...
1. [30] A government agency has you to compute benefit cost ratios for the following bridge project Cost: $3,250,000 Salvage: $200,000 Benefits: $800,000 per year O&M Costs: $350,000 per year Interest: 10% Project Life: 100 years