Harnett Corporation has two manufacturing departments--Molding and Assembly. The company used the following data at the beginning of the period to calculate predetermined overhead rates:
:
a | |||
Total | Molding | Assembly | |
Fixed manufacturing overhead cost | 46000 | 21600 | 24400 |
Variable manufacturing overhead cost | 35000 | 15000 | 20000 |
Total overhead cost | 81000 | 36600 | 44400 |
Divide by Total machine hours | 10000 | ||
Predetermined overhead rate | 8.10 | per MH | |
b | |||
Machine hours Job E | 5000 | ||
X Predetermined overhead rate | 8.10 | ||
Manufacturing overhead applied | 40500 | ||
c | |||
Direct materials | 13700 | ||
Direct labor | 20800 | ||
Manufacturing overhead applied | 40500 | ||
Manufacturing cost | 75000 | ||
d | |||
Manufacturing cost | 75000 | ||
Add: Markup | 15000 | ||
Selling price | 90000 | ||
e | |||
Molding department overhead | 36600 | ||
Divide by Total machine hours | 6000 | ||
Molding Predetermined overhead rate | 6.10 | per MH | |
f | |||
Assembly department overhead | 44400 | ||
Divide by Total machine hours | 4000 | ||
Assembly Predetermined overhead rate | 11.10 | per MH | |
g | |||
Molding department overhead applied | 15250 | =2500*6.10 | |
Assembly department overhead applied | 27750 | =2500*11.10 | |
Manufacturing overhead applied Job E | 43000 | ||
h | |||
Direct materials | 13700 | ||
Direct labor | 20800 | ||
Manufacturing overhead applied | 43000 | ||
Manufacturing cost | 77500 | ||
Add: Markup | 15500 | ||
Selling price for Job E | 93000 |
Harnett Corporation has two manufacturing departments--Molding and Assembly. The company used the following data at the...
Harnett Corporation has two manufacturing departments--Molding and Assembly. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Molding 7,000 $ 39,900 $ 2.00 Assembly 3,000 $ 18,600 $ 4.00 Total 10,000 $ 58,500 During the period, the company started and completed two jobs--Job E and Job M. Data concerning those two jobs follow: Direct materials...
Harnett Corporation has two manufacturing departments --Molding and Assembly. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estinated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Molding 8,000 $32,800 $ 3.ee Assembly 2,eee $9,400 $ 6.00 Total 10,000 $42,200 During the period, the company started and completed two jobs-Job E and Job M. Data cancerning those two jobs follow: Direct materials Direct labor...
Harnett Corporation has two manufacturing departments--Molding and Assembly. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Molding Assembly Total Estimated total machine-hours (MHs) 2,000 8,000 10,000 Estimated total fixed manufacturing overhead cost $ 12,200 $ 64,000 $ 76,200 Estimated variable manufacturing overhead cost per MH $ 3.00 $ 6.00 During the period, the company started and completed two jobs--Job E and Job M. Data concerning those two jobs follow: Job E...
Harnett Corporation has two manufacturing departments--Molding and Assembly. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Molding Assembly Total Estimated total machine-hours (MHs) 2,000 8,000 10,000 Estimated total fixed manufacturing overhead cost $ 8,800 $ 39,200 $ 48,000 Estimated variable manufacturing overhead cost per MH $ 1.50 $ 3.00 During the period, the company started and completed two jobs--Job E and Job M. Data concerning those two jobs follow: Job E...
Harnett Corporation has two manufacturing departments--Molding and Assembly. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Molding Assembly Total Estimated total machine-hours (MHs) 6,000 4,000 10,000 Estimated total fixed manufacturing overhead cost $ 36,600 $ 24,400 $ 61,000 Estimated variable manufacturing overhead cost per MH $ 2.00 $ 4.00 During the period, the company started and completed two jobs--Job E and Job M. Data concerning those two jobs follow: Job E...
Harnett Corporation has two manufacturing departments--Molding and Assembly. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Molding Assembly Total Estimated total machine-hours (MHs) 3,000 7,000 10,000 Estimated total fixed manufacturing overhead cost $ 24,000 $ 53,200 $ 77,200 Estimated variable manufacturing overhead cost per MH $ 1.00 $ 2.00 During the period, the company started and completed two jobs--Job E and Job M. Data concerning those two jobs follow: Job E...
Harnett Corporation has two manufacturing departments--Molding and Assembly. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Molding Assembly Total Estimated total machine-hours (MHs) 3,000 7,000 10,000 Estimated total fixed manufacturing overhead cost $ 24,000 $ 53,200 $ 77,200 Estimated variable manufacturing overhead cost per MH $ 1.00 $ 2.00 During the period, the company started and completed two jobs--Job E and Job M. Data concerning those two jobs follow: Job E...
TB Problem Qu. 2-281 Harnett Corporation has two manufacturing ... Harnett Corporation has two manufacturing departments--Molding and Assembly. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Molding Assembly Total Estimated total machine-hours (MHs) 6,000 4,000 10,000 Estimated total fixed manufacturing overhead cost $ 36,600 $ 24,400 $ 61,000 Estimated variable manufacturing overhead cost per MH $ 2.00 $ 4.00 During the period, the company started and completed two jobs--Job E and...
Harnett Corporation has two manufacturing departments--Molding and Assembly. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Molding Assembly Total Estimated total machine-hours (MHs) 3,000 7,000 10,000 Estimated total fixed manufacturing overhead cost $ 24,000 $ 53,200 $ 77,200 Estimated variable manufacturing overhead cost per MH $ 1.00 $ 2.00 During the period, the company started and completed two jobs--Job E and Job M. Data concerning those two jobs follow: Job E...
1 comtinued 2. 2 continued Harnett Corporation has two manufecturing departments-Molding and Assembly. The company used the following dato at the beginning of the period to calculate predetermined overheed rates: 9,000 $ 45,900 7,600 후 53,500 1.503.00 1,000 10,000 Estinated total fixed manufacturing overhead cost During the period, the company started and completed two jobs-Job E and Job M. Data concerning those two jobs follow. $21,800 $9,000 22,100 $8,500 2,500 6,500 500 500 a. Assume that the company uses a...