Question

A project's base case or most likely NPV is $50,000, and assume its probability of occurrence...

A project's base case or most likely NPV is $50,000, and assume its probability of

occurrence is 60%. Assume the best case scenario NPV is 60% higher than the

base case and assume the worst scenario NPV is 30% lower than the base case. Both

the best case scenario and the worst case scenario have a 20% probability of

occurrence. Find the project's coefficient of variation.   Enter your answer rounded to

two decimal places. For example, if your answer is 12.345 then enter as 12.35 in the

answer box.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
NPV (in $) Probability
Base case     50,000.00                  0.60
Best case     80,000.00                  0.20
Worst case     35,000.00                  0.20

Now coefficient of variation = standard deviation/mean

Let us first find the mean NPV. Mean = (0.6*50,000) + (0.2*80,000) + (0.2*35,000)

= $53,000

Standard deviation = [0.6*(50,000-53000)^2 + 0.2*(80,000-53,000)^2 + 0.2*(50000-53000)^2]^1/2

= 14,696.94

Thus coefficient of variation = 14,696.94/$53,000 * 100

= 27.73 %

Add a comment
Know the answer?
Add Answer to:
A project's base case or most likely NPV is $50,000, and assume its probability of occurrence...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project's base case or most likely NPV is $50,000, and assume its probability of occurrence is 60%. Assume the best ca...

    A project's base case or most likely NPV is $50,000, and assume its probability of occurrence is 60%. Assume the best case scenario NPV is 60% higher than the base case and assume the worst scenario NPV is 30% lower than the base case. Both the best case scenario and the worst case scenario have a 20% probability of occurrence. Find the project's coefficient of variation. Enter your answer rounded to two decimal places. For example, if your answer is...

  • A project's base case or most likely NPV is $50,000, and assume its probability of occurrence is 60%. Assume the best ca...

    A project's base case or most likely NPV is $50,000, and assume its probability of occurrence is 60%. Assume the best case scenario NPV is 60% higher than the base case and assume the worst scenario NPV is 30% lower than the base case. Both the best case scenario and the worst case scenario have a 20% probability of occurrence. Find the project's coefficient of variation.

  • 15. Florida Enterprises, Inc. is considering a new project whose data are shown below. The equipment that will be us...

    15. Florida Enterprises, Inc. is considering a new project whose data are shown below. The equipment that will be used has a 3-year class life and will be depreciated by the MACRS depreciation system. Revenues and Cash operating costs are expected to be constant over the project's 10-year life. What is the Year 1 after-tax net operating cash flow? Enter your answer rounded to two decimal places. Do not enter $ or comma in the answer box. For example, if...

  • Question 10 10 pts Roenfeld Corp uses scenario analysis in order to determine an expected NPV...

    Question 10 10 pts Roenfeld Corp uses scenario analysis in order to determine an expected NPV for its projects. The base case, best case, and worse case scenarios as well as their probabilities of occurrence are provided below for a new project. What is the project's coefficient of variation (CV) of NPV and what is the (cumulative) probability of a negative NPV for the project? Probability of Occurrence 0.20 Scenario Best case Base case Worst case Project's NPV $28,000 $13,000...

  • The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost:...

    The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: $ 60 $ 40 $420,000 47,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated straight-line...

  • The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost:...

    The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: $ 80 $ 60 $460,000 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated straight-line...

  • The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...

    The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 250,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated...

  • The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80...

    The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80 Variable cost: $ 60 Fixed cost: $ 380,000 Expected sales: 37,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.7 million, which will be depreciated...

  • Scenario Modeler’s prospective stock has a 15% chance of producing a 65% return, a 25% chance...

    Scenario Modeler’s prospective stock has a 15% chance of producing a 65% return, a 25% chance of producing a 22% return, a 40% chance of producing a 9% return, and a 20% chance of producing a –28% return. What is the firm’s coefficient of variation of return? Enter your answer rounded to two decimal places. For example, if your answer is 12.345 then enter as 12.35 in the answer box.

  • URGENTTT The most likely outcomes for a particular project are estimated as follows: Unit price: Variable...

    URGENTTT The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: 80 68 $280,eee 30,eee units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.0 million, which will be depreciated straight-line over...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT