CALCULATOR PRINTER VERSION BACK NEXT Problem IU JA a, b, c (Video) Ratchet Company uses budgets in controlling costs. The Aug
(b) Prepare a budget report for August using flexible budget data. (List variable costs before fixed costs.) RATCHET COMPANY
or both whom
0 0
Add a comment Improve this question Transcribed image text
Answer #1
RATCHET COMPANY
Assembly Department
Manufacturing Overhead Flexible Budget Report
For the Month Ended June 30, 2017
Budget Actual Costs Difference
Direct Labor Hours 63000 63000
Variable Costs
Direct materials $55,440 $56,100 $660 Unfavorable
   Direct labor $59,220 $57,600 $1,620 Favorable
   Indirect materials $25,200 $26,100 $900.00 Unfavorable
   Indirect labor $23,940 $24,300 $360.00 Unfavorable
   Utilities $18,900 $19,330 $430.00 Unfavorable
   Maintenance $7,560 $8,170 $610.00 Unfavorable
Total Variable Costs $190,260.00 $191,600.00 $1,340.00 Unfavorable
Fixed Costs
Supervision $10,300.00 $10,300.00 $0.00 Neither Favorable nor Unfavorable
Depreciation $18,300.00 $18,300.00 $0.00 Neither Favorable nor Unfavorable
Insurance $6,800.00 $6,800.00 $0.00 Neither Favorable nor Unfavorable
Total Fixed Costs $35,400.00 $35,400.00 $0.00 Neither Favorable nor Unfavorable
Total Cost $225,660.00 $227,000.00 $1,340.00 Unfavorable

А C D Е Favorable F 7 8 Manufacturing Costs Unfavorable U Budget Actual Neither Favorable 10 nor Unfavorable N 11 Variable co

Add a comment
Know the answer?
Add Answer to:
CALCULATOR PRINTER VERSION BACK NEXT Problem IU JA a, b, c (Video) Ratchet Company uses budgets...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • CALCULATOR PRINTER VERSION BACK NEXT s Problem 22-JA (Part Level Submission) Ratchet Company uses budgets in...

    CALCULATOR PRINTER VERSION BACK NEXT s Problem 22-JA (Part Level Submission) Ratchet Company uses budgets in controlling costs. The August 2017 budget report for the company's Assembling Department is as RATCHET COMPANY Budget Report Assembling Department For the Month Ended August 31, 2017 Difference Unfavorable Neither Favorable Hanufacturing Costs Budget Actual Variable costs Direct materials $50,740 549,740 $1,000 Favorable Direct labor 54,200 $1,400 2,800 Favorable Indirect materials 25,950 26,260 300 Unfavorable Indirect labor 22,420 21,940 480 Favorable 14,750 14,580 170...

  • CALCULATOR PRINTER VERSION Problem 10-3A a, b1, C (Part Level Submission) (Video) Ratchet Company uses budgets...

    CALCULATOR PRINTER VERSION Problem 10-3A a, b1, C (Part Level Submission) (Video) Ratchet Company uses budgets in controlling costs. The August 2020 budget report for the company's Assembling Department is as follows. RATCHET COMPANY Budget Report Assembling Department For the Month Ended August 31, 2020 Difference Favorable Unfavorable Neither Favorable Manufacturing Costs Budget Actual nor Unfavorable Variable costs Direct materials $50,740 $49,740 $1,000 Favorable Direct labor 54,280 51,480 2,800 Favorable Indirect materials 25,960 26,260 300 Unfavorable Indirect labor 22,420 21,940...

  • CALCULATOR PRINTER VERSI Problem 10-3A a, b1, c (Part Level Submission) (Video) Ratchet Company uses budgets...

    CALCULATOR PRINTER VERSI Problem 10-3A a, b1, c (Part Level Submission) (Video) Ratchet Company uses budgets in controlling costs. The August 2020 budget report for the company's Assembling Department is as follows. RATCHET COMPANY Budget Report Assembling Department For the Month Ended August 31, 2020 Difference Favorable Unfavorable Neither Favorable nor Unfavorable Manufacturing Costs Budget Actual Variable costs Direct materials $50,740 $49,740 $1,000 Favorable Direct labor 54,280 51,480 2,800 Favorable Indirect materials 25,960 26,260 300 Unfavorable Indirect labor 22,420 21,940...

  • CALOURATOR PRINTER VERSION BACK NE Problem 10-3A a, b1, c (Part Level Submission) (Video) Ratchet Company...

    CALOURATOR PRINTER VERSION BACK NE Problem 10-3A a, b1, c (Part Level Submission) (Video) Ratchet Company uses budgets in controlling costs. The August 2020 budget report for the company's Assembling Department is as follows RATCHET COMPANY Budget Report Assembling Department For the Month Ended August 31, 2020 Difference Favorable Unfavorable Neither Favorable nor Unfavorabl Manufacturing Costs Budget Actual Variable costs Direct materials $49,600 $48,500 $1,100 Favorable 57,040 27,280 Direct labor 54,040 3,000 Favorable 300 Unfavorable Indirect materials 27,580 Indirect labor...

  • Problem 23-03A a, b1, c Ratchet Company uses budgets in controlling costs. The August 2020 budget...

    Problem 23-03A a, b1, c Ratchet Company uses budgets in controlling costs. The August 2020 budget report for the company's Assembling Department is as follows. RATCHET COMPANY Budget Report Assembling Department For the Month Ended August 31, 2020 Difference Favorable Unfavorable Neither Favorable nor Unfavorable Manufacturing Costs Budget Actual Variable costs Direct materials $48,380 $47,280 $1,100 Favorable Direct labor 57,820 54,520 3,300 Favorable Indirect materials 26,060 100 Unfavorable 25,960 Indirect labor 450 Favorable 21,240 20,790 140 Favorable Utilities 20,650 20,510...

  • Problem 22-3A (Part Level Submission) Ratchet Company uses budgets in controlling costs. The August 2017 budget...

    Problem 22-3A (Part Level Submission) Ratchet Company uses budgets in controlling costs. The August 2017 budget report for the company's Assembling Department is as follows. RATCHET COMPANY Budget Report Assembling Department For the Month Ended August 31, 2017 Difference Favorable Unfavorable Neither Favorable Manufacturing Costs Budget Actual nor Unfavorable Variable costs Direct materials $51,240 $50,140 $1,100 Favorable Direct labor 59,780 56,580 3,200 Favorable Indirect materials 25,620 25,820 200 Unfavorable Indirect labor 21,960 21,560 400 Favorable Utilities 18,300 18,170 130 Favorable...

  • De LM CALCULATOR PRI Problem 10-3A a, b, c (Part Level Submission) (Video) Ratchet Company uses...

    De LM CALCULATOR PRI Problem 10-3A a, b, c (Part Level Submission) (Video) Ratchet Company uses budgets in controlling costs. The August 2020 budget report for the company's Assembling Department is as follows. RATCHET COMPANY Budget Report Assembling Department For the Month Ended August 31, 2020 Difference Favorable Unfavorable Neither Favorable nor Unfavorable Manufacturing Costs Budget Actual Variable costs Direct materials Direct labor Indirect materials Indirect labor Utilities Maintenance Total variable Fixed costs Rent Supervision Depreciation $49,600 $48,500 $1,100 Favorable...

  • Ratchet Company uses budgets in controlling costs. The August 2020 budget report for the company’s Assembling...

    Ratchet Company uses budgets in controlling costs. The August 2020 budget report for the company’s Assembling Department is as follows. RATCHET COMPANY Budget Report Assembling Department For the Month Ended August 31, 2020 Difference Manufacturing Costs Budget Actual Favorable Unfavorable Neither Favorable nor Unfavorable Variable costs    Direct materials $55,040 $53,940 $1,100 Favorable    Direct labor 62,720 59,320 3,400 Favorable    Indirect materials 30,720 30,820 100 Unfavorable    Indirect labor 21,760 21,260 500 Favorable    Utilities 16,000 15,890 110 Favorable    Maintenance 11,520 11,650 130 Unfavorable...

  • Ratchet Company uses budgets in controlling costs. The August 2020 budget report for the company's Assembling...

    Ratchet Company uses budgets in controlling costs. The August 2020 budget report for the company's Assembling Department is as follows. RATCHET COMPANY Budget Report For the Month Ended August 31, 2020 Difference Favorable Unfavorable Neither Favorable nor Unfavorable Manu 9 Costs Budget Actual Variable costs Direct materials Direct labor Indirect materials Indirect labor Utilities Maintenance 49,560 $48,460 $1,100 Favorable 54,280 51,380 2,900 Favorable 28,320 28,420 100 Unfavorablke 18,880 18,420 460 Favorable 17,700 17,570 130 Favorable 9440 9.670 230 Unfavorable 178,180...

  • Problem 22-3A (Part Level Submission) Ratchet Company uses budgets in controlling costs. The August 2017 budget...

    Problem 22-3A (Part Level Submission) Ratchet Company uses budgets in controlling costs. The August 2017 budget report for the company's Assembling Department is as follows. RATCHET COMPANY Budget Report Assembling Department For the Month Ended August 31, 2017 Difference Favorable Unfavorable Neither Favorable Manufacturing Costs Budget Actual nor Unfavorable Variable costs Direct materials 551,200 $50,200 $1,000 Favorable Direct labor 57,500 54,200 3,400 Favorable Indirect materials 26,880 26,980 100 Unfavorable Indirect labor 19,200 18,740 460 Favorable Utilities 16,000 15,830 170 Favorable...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT