>Actual Labor cost = 40600 hours x
$ 13.25 = $ 537,950
>Standard labor cost = 11200 units x 3.60 hours x $ 13.10 = $
528,192
Labor Rate Variance |
||||||
( |
Standard Rate |
- |
Actual Rate |
) |
x |
Actual Labor Hours |
( |
$ 13.10 |
- |
$ 13.25 |
) |
x |
40600 |
-6090 |
||||||
Variance |
$ 6,090.00 |
Unfavourable-U |
Labour Quantity Variance |
||||||
( |
Standard Hours |
- |
Actual Hours |
) |
x |
Standard Rate |
( |
40320 |
- |
40600 |
) |
x |
$ 13.10 |
-3668 |
||||||
Variance |
$ 3,668.00 |
Unfavourable-U |
Labor Rate Variance |
||||||
( |
Standard Rate |
- |
Actual Rate |
) |
x |
Actual Labor Hours |
( |
$ 13.35 |
- |
$ 13.25 |
) |
x |
40600 |
4060 |
||||||
Variance |
$ 4,060.00 |
Favourable-F |
||||
Labour Quantity Variance |
||||||
( |
Standard Hours |
- |
Actual Hours |
) |
x |
Standard Rate |
( |
43680 |
- |
40600 |
) |
x |
$ 13.35 |
41118 |
||||||
Variance |
$ 41,118.00 |
Favourable-F |
CALCULATOR PRINTER VERBON I ACK Exercise 11-6 (Video) Lewis Company's standard labor cost of producing one...
Exercise 11-6 (Video) Lewis Company's standard labor cost of producing one unit of Product DD is 3.60 hours at the rate of $13.10 per hour. During August, 40,600 hours of labor are incurred at a cost of $13.25 per hour to produce 11,200 units of Product DD. (a) Compute the total labor variance. Total labor variance (b) Compute the labor price and quantity variances. Labor price variance $ Labor quantity variance (c) Compute the labor price and quantity variances, assuming...
Exercise 11-6 (video) Lewis Company's standard labor cost of producing one unit of Product DD is 3.60 hours at the rate of $13.10 per hour. During August, 40,600 hours of labor are incurred at a cost of $13.25 per hour to produce 11,200 units of Product DD. (a) Compute the total labor variance. Total labor variance (b) Compute the labor price and quantity variances. Labor price variance s Labor quantity variance (c) Compute the labor price and quantity variances, assuming...
Exercise 25-6 Lewis Company's standard labor cost of producing one unit of Product DD is 3.6 hours at the rate of $13.1 per hour. During August, 40,600 hours of labor are incurred at a cost of $13.25 per hour to produce 11,200 units of Product DD. (a) Compute the total labor variance. Total labor variances (b) Compute the labor price and quantity variances. Labor price variance <> Labor quantity variances (c) Compute the labor price and quantity variances, assuming the...
Exercise 11-6 (Video) Lewis Company's standard labor cost of producing one unit of Product DD is 3.10 hours at the rate of $12.50 per hour. During August, 42,000 hours of labor are incurred at a cost of $12.70 per hour to produce 13,400 units of Product DD. (a) Compute the total labor variance. Total labor variances (6) Compute the labor price and quantity variances. Labor price variance Labor quantity variances (c) Compute the labor price and quantity variances, assuming the...
Exercise 11-6 (Video) Lewis Company’s standard labor cost of producing one unit of Product DD is 3.40 hours at the rate of $13.80 per hour. During August, 43,700 hours of labor are incurred at a cost of $14.00 per hour to produce 12,600 units of Product DD. (a) Compute the total labor variance. Total labor variance $ (b) Compute the labor price and quantity variances. Labor price variance $ Labor quantity variance $ (c) Compute the labor price and quantity...
- VE) Lewis Company's standard labor cost of producing one unit of Product DD is 3.20 hours at the rate of $12.50 per hour. During August, 42,600 hours of labor are incurred at a cost of 512 65 per hour to produce 13,200 units of Product DD. Compute the total labor variance Total labor variance (b) Compute the labor price and quantity variances Labor price variance Labor quantity variance Compute the labor price and quantity variances, assuming the standard is...
Exercise 11-6 Lewis Company's standard labor cost of producing one unit of Product DD is 3.9 hours at the rate of $13.0 per hour. During August, 42,000 hours of labor are incurred at a cost of $13.20 per hour to produce 10,600 units of Product DD. Compute the total labor variance. Total labor variance 102 Compute the labor price and quantity variances. Labor price variance Labor quantity variance Compute the labor price and quantity variances, assuming the standard is 4.2...
LALLULATUR PULL SCREEN PRINTER VERSIUN BALK NEAI Exercise 23-6 Lewis Company's standard labor cost of producing one unit of Product DD is 3.7 hours at the rate of $12.6 per hour. During August, 43,500 hours of labor are incurred at a cost of $12.80 per hour to produce 11,600 units of Product DD. (a) Compute the total labor variance. Total labor variance $ (b) Compute the labor price and quantity variances. Labor price variance $ Labor quantity variance (c) Compute...
Exercise 25-6 Lewis Company's standard labor cost of producing one unit of Product DD is 3.9 hours at the rate of $13.2 per hour. During August, 40,800 hours of labor are incurred at a cost of $13.30 per hour to produce 10,300 units of Product DD. (a) Compute the total labor variance. Total labor variance (b) Compute the labor price and quantity variances. Labor price variance Labor quantity variance A (c) Compute the labor price and quantity variances, assuming the...
Lewis Company's standard labor cost of producing one unit of Product DD is 3.4 hours at the rate of $13.8 per hour. During August, 43,700 hours of labor are incurred at a cost of $14.00 per hour to produce 12,600 units of Product DD Compute the total labor variance Total labor variance Compute the labor price and quantity variances. Labor price variance Labor quantity variance Compute the labor price and quantity variances, assuming the standard is 3.8 hours of direct...