Question

[13) Pingo plc has the following estimates of the net present value of a project using different interest rates: Discount rates 10% NPV 366 230 103 -76 0 0 15% Which pair of interest rates will provide the most accurate estimate if interpolation is used to estimate the projects internal rate of return? a) b) c) d) e) 8% and 10% 8% and 12% 10% and 12% 8% and 15% 12% and 15%

0 0
Add a comment Improve this question Transcribed image text
Answer #1

IRR is that discount rate at which NPV of the project is zero.

Based on the information above, we note that

  • NPV decreases as discount rate increases
  • At a discount rate of 12%, NPV is 103
  • At a discount rate of 15%, NPV is -76

This means somewhere between the discount rate 12% to 15%, NPV turns zero. So, IRR can be best obtained by interpolating between discount rate of 12% and 15%. So the correct answer is option (e)

Add a comment
Know the answer?
Add Answer to:
[13) Pingo plc has the following estimates of the net present value of a project using...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You calculate the net present value (NPV) for a project your firm is considering. Using a...

    You calculate the net present value (NPV) for a project your firm is considering. Using a 12% discount rate, the NPV is $600,000. The cost of the project is $1,200,000. What decision do you make? Group of answer choices Reject because the NPV is less than the cost of the project. Accept because $600,000 divided by $1,200,000 is 50%, which is greater than the discount rate. None of these are correct. Reject because the NPV should be negative. Accept because...

  • You calculate the net present value (NPV) for a project your firm is considering. Using a...

    You calculate the net present value (NPV) for a project your firm is considering. Using a 12% discount rate, the NPV is $600,000. The cost of the project is $1,200,000. What decision do you make? Group of answer choices Accept because the NPV is greater than $0. Reject because the NPV should be negative. None of these are correct. Reject because the NPV is less than the cost of the project. Accept because $600,000 divided by $1,200,000 is 50%, which...

  • Calculate the net present value of the following project for discount rates of 0, 50, and...

    Calculate the net present value of the following project for discount rates of 0, 50, and 100%: (Leave no cells blank - be certain to enter "0" wherever required. Do not round intermediate calculations. Round your answers to 2 decimal places.) C0 C1 C2 −$7,233.75 +$4,680.00 +$19,575.00 Discount Rate NPV          0%           $    50%              100%              b. What is the IRR of the project?   IRR %  

  • Problems with the IRR method Acme Oscillators is considering an investment project that has the following...

    Problems with the IRR method Acme Oscillators is considering an investment project that has the following rather unusual cash flow pattern. Year AWNIO Cash Flow $100 - 460 793 - 602.3 171.3 a. Calculate the project's NPV at each of the following discount rates: 0%, 5%, 10%, 20%, 30%, 40%, 50%. b. What do the calculations tell you about this project's IRR? The IRR rule tells managers to invest if a project's IRR is greater than the cost of capital....

  • Net present value. Lepton Industries has a project with the following projected cash flows: a. Using...

    Net present value. Lepton Industries has a project with the following projected cash flows: a. Using a discount rate of 10% for this project and the NPV model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 17%? c. Should the company accept or reject it using a discount rate of 20%? a. Using a discount rate of 10%, this project should be V. (Select from...

  • NPV and IRR Benson Designs has prepared the following estimates for a long-term project it is...

    NPV and IRR Benson Designs has prepared the following estimates for a long-term project it is considering. The initial investment is $30,160, and the project is expected to yield after-tax cash inflows of $4,000 per year for 12 years. The firm has a cost of capital of 15%. a. Determine the net present value (NPV) for the project. b. Determine the internal rate of return (IRR) for the project. c. Wauld you recommend that the firm accept or reject the...

  • Help and verified and be clear. The net present value (NPV) and internal rate of return...

    Help and verified and be clear. The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Blue Hamster Manufacturing Inc.: Last Tuesday, Blue Hamster Manufacturing Inc. lost a portion of its planning and financial data when both its main and its backup servers crashed. The company's CFO remembers that the internal rate of return (IRR) of Project Lambda is...

  • Net Present Value Use Exhibit 120.1 and Exhibit 128.2 to locate the present value of an...

    Net Present Value Use Exhibit 120.1 and Exhibit 128.2 to locate the present value of an annuity of $1, which is the amount to be multiplied times the future annual cash flow amount. Each of the following scenarios is independent. Assume that all cash flows are after-tax cash flows. a. Campbell Manufacturing is considering the purchase of a new welding system. The cash benefits will be $480,000 per year. The system costs $2,250,000 and will last 10 years. b. Evee...

  • answer Comparison of Capital Budgeting Methods 1. Determine the payback period for an investment 2. Evaluate the acceptability of an investment project using the net present value method 3. Eval...

    answer Comparison of Capital Budgeting Methods 1. Determine the payback period for an investment 2. Evaluate the acceptability of an investment project using the net present value method 3. Evaluate the acceptability of an investment project using the internal rate of return method. 4. Compute the simple rate of return for an investment FILE HOME INSERT PAGE LAYOUT FORMULAS DATA REVIEW VIEW LEH Sign In в r u . B- 5- Number Formation 1 Format as Styles. Alignment Cells Editing...

  • Part A - Net Present Value A project has estimated annual net cash flows of $10,000 for one years and is estimated to co...

    Part A - Net Present Value A project has estimated annual net cash flows of $10,000 for one years and is estimated to cost $50,000. Assume a minimum acceptable rate of return of 10%. Use the Present Value of an Annuity of $1 at Compound Interest table below. Present Value of an Annuity of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2 1.833 1.736 1.690 1.626 1.528 3 2.673 2.487 2.402...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT