1) Total manufacturing cost
direct material 231
direct labor 153
overhead (153/17*14) 126
Total manufacturing cost 510
2) Unit product cost = 510/40 = 12.75 perunit
b)
Direct labor hours
assembly = 180/20 =9
testing & packaging = 40/20 =2
Total manufacturing cost
Direct material (340+25) 365
direct labor (180+40) 220
overhead applied
assembly (16*9) 144
testing & packaging (12*2 24
Total manufacturing cost 753
2) unit product cost = 753/10 = 75.3 per unit
Add a comment
Know the answer?
Add Answer to:
Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate...

    Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate [LO2-3) Mickley Company's plantwide predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $11.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your...

  • Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate...

    Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate [LO2-3] Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $14.00 per hour. The following information pertains to Job A-500: $ 240 $140 Direct materials Direct labor Required: 1. What is the total manufacturing cost assigned 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your...

  • Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate...

    Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate [LO2-3] Mickley Company's plantwide predetermined overhead rate is $22.00 per direct labor-hour and its direct labor wage rate is $15.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 210 $ 300 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 30 units, what is the unit product cost for...

  • Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate...

    Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate (LO2-3] Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $10.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 260 $ 100 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 70 units, what is the unit product cost for...

  • Exercise 2-3 (Algo) Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead...

    Exercise 2-3 (Algo) Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate [LO2-3) Mickley Company's plantwide predetermined overhead rate is $23.00 per direct labor-hour and its direct laborwage rate is $13.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 270 $ 195 ces Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 60 units, what is the unit product cost...

  • Saved Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead...

    Saved Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate (LO2-3) Mickley Company's plantwide predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $17.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 231 $153 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 40 units, what is the unit product cost for...

  • Exercise 2-3 (Algo) Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead...

    Exercise 2-3 (Algo) Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate (LO2-3] Mickley Company's plantwide predetermined overhead rate is $20.00 per direct labor-hour and its direct labor wage rate is $11.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 210 $ 165 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 50 units, what is the unit product cost...

  • Exercise 2-3 (Algo) Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead...

    Exercise 2-3 (Algo) Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate (LO2-3] Mickley Company's plantwide predetermined overhead rate is $18.00 per direct labor-hour and its direct labor wage rate is $13.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 230 $ 195 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 80 units, what is the unit product cost...

  • Exercise 2-4 (Algo) Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates...

    Exercise 2-4 (Algo) Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4) Fickel Company has two manufacturing departments—Assembly and Testing & Packaging. The predetermined overhead rates in Assembly and Testing & Packaging are $20.00 per direct labor-hour and $16.00 per direct labor-hour, respectively. The company's direct labor wage rate is $22.00 per hour. The following information pertains to Job N-60: Testing & Packaging $41 $99 Assembly $380 $187 Direct materials Direct labor Required: 1. What...

  • Exercise 2-4 (Algo) Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates...

    Exercise 2-4 (Algo) Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates [LO2-4) Fickel Company has two manufacturing departments-Assembly and Testing & Packaging. The predetermined overhead rates in Assembly and Testing & Packaging are $20.00 per direct labor-hour and $16.00 per direct labor-hour , respectively. The company's direct labor wage rate is $22.00 per hour. The following information pertains to Job N-60: Testing & Assembly Packaging Direct materials Direct labor $380 $187 $99 Required: 1. What...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT