1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020.
Prepare Bridgeport’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.
2- Waterway, Inc. began work on a $7,071,000 contract in 2020 to
construct an office building. Waterway uses the completed-contract
method. At December 31, 2020, the balances in certain accounts were
Construction in Process $1,877,000, Accounts Receivable $237,000,
and Billings on Construction in Process $958,000.
Indicate how these accounts would be reported in Waterway’s
December 31, 2020, balance sheet
Answer to Question No. 1 :
(a) Percentage of Completion Method
1. Total Estimated Contract Revenue = $ 407,000 (given)
2. Total Costs incurred in 2020 = $ 272,000 (given)
3. Total Estimated Additional Costs = $ 157,020 (given)
4. Therefore Total Estimated Costs = 2. + 3. = $ 429,020
5. Percentage Complete (Cost to Cost Method) = Total Costs incurred / Total Estimated Costs = 2./3. x 100 = 63.40%
6. Therefore Revenue to be recognized for the year 2020 = Total Estimated Contract Revenue x Percentage Complete
= 1. x 5. = $ 407,000 x 63.40% = $ 258, 038
7. Profit/Loss during the Year = Revenue for the year 2020 - Costs incurred for the year 2020 = 6. - 2.
= $ 258,038 - $ 272,000 = ($ 13,962) [Loss]
8. Journal Entry for Recording the Loss =
Construction Expense A/c ............Dr. $ 272,000
To Construction Revenue A/c Cr. $ 258,038
To Construction in Progress A/c Cr. $ 13,962 (loss)
[Being Contract Revenue, Expense and Loss recognized for the year 2020]
(b) Completed Contract Method
1. No Profit/Loss to be recognized for the Year 2020 as the same is to be recognized in the year the contract is completed.
Answer to Question No. 2 :
Waterway Inc | ||
Balance Sheet as at 31st December 2020 | ||
Particulars | Amount in $ | |
Current Assets | ||
Construction - in - Process | 1,877,000 | |
Less: Billings on Construction - in - Process | (958,000) | 919,000 |
Accounts Receivable | 237,000 |
1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport...
Coronado Construction Company began work on a $407,000 construction contract in 2020. During 2020, Coronado incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Coronado’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.
Bridgeport, Inc. began work on a $7,043,000 contract in 2020 to construct an office building. During 2020, Bridgeport, Inc. incurred costs of $1.891,800, billed its customers for $1,315,000, and collected $939,000. At December 31, 2020. the estimated additional costs to complete the project total $3,363.200. Prepare Bridgeport's 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred costs of $279,500, billed its customer for $204,500, and collected $170,500. At December 31, 2020, the estimated additional costs to complete the project total $150,500. Prepare Cheyenne’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. Cheyenne Construction Company began work on a $424.000 construction contract in 2020. During 2020, Cheyenne incurred costs of...
Vaughn Construction Company began work on a $423,000 construction contract in 2020. During 2020, Vaughn incurred costs of $295,500, billed its customer for $200,500, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $155,645. Prepare Vaughn’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
adland, Inc. began work on a $7,215,000 contract in 2020 to construct an office building. Headland uses the completed-contract method. At December 31, 2020, the balances in certain accounts were Construction in Process $1,813,000, Accounts Receivable $261,000, and Billings on Construction in Process $1,001,000. Indicate how these accounts would be reported in Headland’s December 31, 2020, balance sheet. Headland, Inc. began work on a $7,215,000 contract in 2020 to construct an office building. Headland uses the completed-contract method. At December...
Indigo Construction Company began work on a $420,500 construction contract in 2020. During 2020, Indigo incurred costs of $299,000, billed its customer for $202,000, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $151,030. Prepare Indigo’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Splish Construction Company began work on a $402,000 construction contract in 2020. During 2020, Splish incurred costs of $252,000, billed its customer for $210,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $162,405. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Splish Construction Company began work on a $418,500 construction contract in 2020. During 2020, Splish incurred costs of $285,500, billed its customer for $233,000, and collected $172,000. At December 31, 2020, the estimated additional costs to complete the project total $155,765. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Sarasota, Inc. began work on a $6,339,000 contract in 2020 to construct an office building. During 2020, Sarasota, Inc. incurred costs of $1,537,470, billed its customers for $1,141,000, and collected $961,000. At December 31, 2020, the estimated additional costs to complete the project total $3,121,530. Prepare Sarasota’s 2020 journal entries using the percentage-of-completion method. Sarasota, Inc. began work on a $6,339,000 contract in 2020 to construct an office building. During 2020, Sarasota, Inc. incurred costs of $1,537,470, billed its customers...