Prichard Manufacturing Company expects to normally operate at 75% of its productive capacity of 120.000 units per month. The
vanadie Overhead Fixed Overhead $220,000 365.000 (1) Compute the overhead volume variance. (2) Compute the overhead controlla


Prichard Manufacturing Company expects to normally operate at 75% of its productive capacity of 120,000 units per month. The
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution 1 and 2:

10:37 MM = Excel Poo-1.1.xlsx File View Edit Cell Insert Data Draw Q & 3 AL 21 E11! Find Go To Freeze Panes Filter Ascending

Add a comment
Know the answer?
Add Answer to:
Prichard Manufacturing Company expects to normally operate at 75% of its productive capacity of 120.000 units...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • World Company expects to operate at 80% of its productive capacity of 50,000 units per month....

    World Company expects to operate at 80% of its productive capacity of 50,000 units per month. At this planned level, the company expects to use 24,400 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.610 direct labor hour per unit. At the 80% capacity level, the total budgeted cost includes $53,680 fixed overhead cost and $273,280 variable overhead cost. In the current month, the company incurred $320,000 actual overhead and 21,400 actual...

  • World Company expects to operate at 80% of its productive capacity of 72,500 units per month....

    World Company expects to operate at 80% of its productive capacity of 72,500 units per month. At this planned level, the company expects to use 31,900 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.550 direct labor hour per unit. At the 80% capacity level, the total budgeted cost includes $79,750 fixed overhead cost and $414,700 variable overhead cost. In the current month, the company incurred $488,000 actual overhead and 28,900 actual...

  • World Company expects to operate at 80% of its productive capacity of 68,750 units per month....

    World Company expects to operate at 80% of its productive capacity of 68,750 units per month. At this planned level, the company expects to use 31,900 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.580 direct labor hour per unit. At the 80% capacity level, the total budgeted cost includes $70,180 fixed overhead cost and $405,130 variable overhead cost. In the current month, the company incurred $473,000 actual overhead and 28,900 actual...

  • World Company expects to operate at 80 % of its productive capacity of 55,000 units per...

    World Company expects to operate at 80 % of its productive capacity of 55,000 units per month. At this planned level, the company expects to use 23,100 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.525 direct labor hours per unit At the 80% capacity level, the total budgeted cost includes $60.060 fixed overhead cost and $267,960 variable overhead cost. In the current month, the company incurred $342,000 actual overhead and 20100...

  • World Company expects to operate at 80% of its productive capacity of 70,000 units per month....

    World Company expects to operate at 80% of its productive capacity of 70,000 units per month. At this planned level, the company expects to use 25,200 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.450 direct labor hour per unit. At the 80% capacity level, the total budgeted cost includes $57,960 fixed overhead cost and $322.560 variable overhead cost. In the current month, the company incurred $386,000 actual overhead and 22,200 actual...

  • Help please! World Company expects to operate at 80% of its productive capacity of 55,000 units...

    Help please! World Company expects to operate at 80% of its productive capacity of 55,000 units per month. At this planned level, the company expects to use 23,100 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.525 direct labor hour per unit. At the 80% capacity level, the total budgeted cost includes $60,060 fixed overhead cost and $267,960 variable overhead cost. In the current month, the company incurred $342.000 actual overhead and...

  • World Company expects to operate at 80% of its productive capacity of 56,250 units per month....

    World Company expects to operate at 80% of its productive capacity of 56,250 units per month. At this planned level, the company expects to use 27,900 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.620 direct labor hours per unit. At the 80% capacity level, the total budgeted cost includes $64,170 fixed overhead cost and $315,270 variable overhead cost. In the current month, the company incurred $340,000 actual overhead and 24,900 actual...

  • World Company expects to operate at 80% of its productive capacity of 70,000 units per month....

    World Company expects to operate at 80% of its productive capacity of 70,000 units per month. At this planned level, the company expects to use 25,200 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.450 direct labor hours per unit. At the 80% capacity level, the total budgeted cost includes $57,960 fixed overhead cost and $322,560 variable overhead cost. In the current month, the company incurred $386,000 actual overhead and 22,200 actual...

  • World Company expects to operate at 80% of its productive capacity of 50,000 units per month....

    World Company expects to operate at 80% of its productive capacity of 50,000 units per month. At this planned level, the company expects to use 25,000 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.625 direct labor hours per unit. At the 80% capacity level, the total budgeted cost includes $50,000 fixed overhead cost and $275,000 variable overhead cost. In the current month, the company incurred $305,000 actual overhead and 22,000 actual...

  • HOW DO I CALCULATE? World Company expects to operate at 80% of its productive capacity of...

    HOW DO I CALCULATE? World Company expects to operate at 80% of its productive capacity of 56,250 units per month. At this planned level, the company expects to use 22,500 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.500 direct labor hour per unit. At the 80% capacity level, the total budgeted cost includes $60,750 fixed overhead cost and $263,250 variable overhead cost. In the current month, the company incurred $338,000 actual...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT