Calculation of Direct labor(h) for case C:
Direct material used + Direct labor + Manufacturing overhead(i.e to be applied on the basis of direct labor cost) = Total manufacturing costs
$73650 + h + (h*60%) = 212850
Therefore h = $87,000
Calculation of manufacturing overhead(i) for case C:
Direct material used + Direct labor + Manufacturing overhead = Total manufacturing costs
$73650+h+i = 212850
$73650+$87000+i = 212850
Therefore i = $52,200
Calculation of total cost of work in progress(j) for case C:
Total manufacturing costs + work in progress 1/1/17 = Total cost of work in progress
$212850 + $18400 = j
Therefore j = $2,31,250
Calculation of work in progress 12/31/17 for case C:
Total cost of work in progress - work in progress 12/31/17 = Cost of goods manufactured
$2,31,250 - k = $2,27,000
k = $4,250
Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below...
Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to 0 decimal places, e.g. 5,275.) Case A Case B Case C Direct materials used $ (a) $86,200 $68,150 Direct labor 52,000 144,800...
Manufacturing cost data for Orlando Company, which uses a job order cost system are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, eg. 15.25 and final answers to decimal places, eg 5,275.) Case A Case B Direct materials used (a) $91,800 Direct labor 60.000 144.800 36,000 Manufacturing overhead applied Total...
Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to O decimal places, e.g. 5,275.) Case A Case B Case C Direct materials used (a) $86,200 $69,650 Direct labor 58,000 149,400 (n)...
Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to 0 decimal places, e.g. 5,275.) Case A Case B Case C $89,300 $73,050 (a) Direct materials used 63850 149,800 (h) Direct labor...
Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to O decimal places, e.g. 5,275.) Case A Case B Direct materials used $ (a) $86,200 Direct labor 58,000 149,400 Manufacturing overhead applied...
Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to 0 decimal places, e.g. 5,275.) Case A Case B Direct materials used $enter a dollar amount (a) $90,100 Direct labor 60,000 146,100...
Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below Indicate fie missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. overhead rate to 2 decimal places, e.g. 15.25 and final answers to 0 decimal places, e.g. 5,275.) Case A Case C Direct materials used Direct labor Manufacturing overhead applied $88,000 $66,650 8,000 46,400 147,950 150,700...
Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to 0 decimal places, e.g. 5,275.) Case A Case B Case C Direct materials used (a) $83,000 $63,150 Direct labor 50,000 140,000 E...
Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume in all cases that manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. Case A Case B Case C Direct materials used $ (a) $91,200 $69,000 Direct labor 52,200 143,800 (h) Manufacturing overhead applied 42,804 (d) (i) Total manufacturing costs 149,800 (e) 216,100 Work in process 1/1/14 (b)...
Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to O decimal places, e.g. 5,275.) Case A Case B Direct materials used $93,600 Direct labor 54,000 146,500 Manufacturing overhead applied 32,400 Total...