A proposed cost-saving device has an installed cost of $735,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $145,000, the marginal tax rate is 23 percent, and the project discount rate is 11 percent. The device has an estimated Year 5 salvage value of $104,000. What level of pretax cost savings do we require for this project to be profitable? MACRS schedule. (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
Initial investment, C0 = installed cost of $735,000 + initial net working capital investment is $145,000 = 735,000 + 145,000 = 880,000
Terminal year cash flows:
Discount rate = R = 11%
PV(TCF) = Present value of terminal year cash flow = Terminal year cash flow / (1 + R)5 = 225,080 / (1 + 11%)5 = 133,574
Depreciation tax shield under MACRS 3 year depreciation schedule:
Asset Cost | A | 735,000 | |||
Year | N | 1 | 2 | 3 | 4 |
Depreciation rate | d | 33.33% | 44.45% | 14.81% | 7.41% |
Depreciation | D = d x A | 244,976 | 326,708 | 108,854 | 54,464 |
Tax rate | T | 23% | |||
Depreciation tax shield | DTS = D x T | 56,344 | 75,143 | 25,036 | 12,527 |
PV Factor @ 11% | (1+R)(-N) | 0.9009 | 0.8116 | 0.7312 | 0.6587 |
PV of Depreciation tax shield | DTS x PV Factor | 50,761 | 60,988 | 18,306 | 8,252 |
Total PV of Depreciation tax shield; PV (DTS) | Sum of all the items in above row | 138,306 |
Let's now assume that pre tax annual cost saving is S. Hence post tax cost savings will be = S x (1 - 23%) = 0.77S
Hence, the present value of post tax cost savings will be = PV of annuity of 0.77S over five years = 0.77S x Sum of PV factors over five years = 0.77S x [1 - (1+R)-N] / R = 0.77S x [1 - (1 + 11%)-5] / 11% = 2.84584S
NPV equation will be:
NPV = -C0 + PV (DTS) + PV(TCF) + PV of post tax annual cost savings over five years = -880,000 + 138,306 + 133,574 + 2.84584S
For this project to be profitable, NPV = 0
or, -880,000 + 138,306 + 133,574 + 2.84584S = 0
Hence, S = (880,000 - 138,306 - 133,574) / 2.84584 = 213,687.21
Level of pretax cost savings do we require for this project to be profitable = S = $ 213,687.21
A proposed cost-saving device has an installed cost of $735,000. The device will be used in...
A proposed cost-saving device has an installed cost of $665,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $75,000, the marginal tax rate is 24 percent, and the project discount rate is 13 percent. The device has an estimated Year 5 salvage value of $62,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...
A proposed cost-saving device has an installed cost of $660,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $70,000, the marginal tax rate is 23 percent, and the project discount rate is 12 percent. The device has an estimated Year 5 salvage value of $59,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...
A proposed cost-saving device has an installed cost of $815,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $87,000, the marginal tax rate is 21 percent, and the project discount rate is 11 percent. The device has an estimated Year 5 salvage value of $133,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...
A proposed cost-saving device has an installed cost of $654,000. The device will be used in a five-year project but is classified as three-year MACRS (MACRS Table) property for tax purposes. The required initial net working capital investment is $48,500, the marginal tax rate is 30 percent, and the project discount rate is 15 percent. The device has an estimated Year 5 salvage value of $73,500. What level of pretax cost savings do we require for this project to...
A proposed cost-saving device has an installed cost of $654,000. The device will be used in a five-year project but is classified as three-year MACRS (MACRS Table) property for tax purposes. The required initial net working capital investment is $48,500, the marginal tax rate is 30 percent, and the project discount rate is 15 percent. The device has an estimated Year 5 salvage value of $73,500. What level of pretax cost savings do we require for this project to...
A proposed cost-saving device has an installed cost of $760,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $65,000, the marginal tax rate is 25 percent, and the project discount rate is 8 percent. The device has an estimated Year 5 salvage value of $100,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...
A proposed cost-saving device has an installed cost of $750,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $61,000, the marginal tax rate is 23 percent, and the project discount rate is 10 percent. The device has an estimated Year 5 salvage value of $94,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...
A proposed cost-saving device has an installed cost of $810,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $85,000, the marginal tax rate is 25 percent, and the project discount rate is 10 percent. The device has an estimated Year 5 salvage value of $130,000. What level of pretax cost savings do we require for this project to be profitable?
A proposed cost-saving device has an installed cost of $760,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $65,000, the tax rate is 25 percent, and the project discount rate is 8 percent. The device has an estimated Year 5 salvage value of $100,000. What level of pretax cost savings do we require for this project to be profitable? MACRS schedule...
A proposed cost-saving device has an installed cost of $450,000. The device will be used in a five-year project, but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $30,000, the marginal tax rate is 35 percent, and the project discount rate is 12 percent. The device has an estimated Year 5 salvage value of $75,000. What level of per year pretax cost savings do we require for this project to be profitable?...