Question

A proposed cost-saving device has an installed cost of $735,000. The device will be used in...

A proposed cost-saving device has an installed cost of $735,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $145,000, the marginal tax rate is 23 percent, and the project discount rate is 11 percent. The device has an estimated Year 5 salvage value of $104,000. What level of pretax cost savings do we require for this project to be profitable? MACRS schedule. (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Initial investment, C0 = installed cost of $735,000 + initial net working capital investment is $145,000 = 735,000 + 145,000 =  880,000

Terminal year cash flows:

  • Since the device would be fully depreciated under MACRS schedule, taxable basis will be zero.
  • Post tax salvage value at the end of year 5 = pre tax salvage value x (1 - Tax rate) = 104,000 x (1 - 23%) =  80,080
  • Release of working capital = 145,000
  • Hence terminal year cash flow = 80,080 + 145,000 =  225,080

Discount rate = R = 11%

PV(TCF) = Present value of terminal year cash flow = Terminal year cash flow / (1 + R)5 = 225,080 / (1 + 11%)5 = 133,574

Depreciation tax shield under MACRS 3 year depreciation schedule:

Asset Cost A          735,000
Year N 1 2 3 4
Depreciation rate d 33.33% 44.45% 14.81% 7.41%
Depreciation D = d x A          244,976       326,708       108,854       54,464
Tax rate T 23%
Depreciation tax shield DTS = D x T            56,344          75,143          25,036       12,527
PV Factor @ 11% (1+R)(-N)            0.9009          0.8116          0.7312       0.6587
PV of Depreciation tax shield DTS x PV Factor            50,761          60,988          18,306          8,252
Total PV of Depreciation tax shield; PV (DTS) Sum of all the items in above row          138,306

Let's now assume that pre tax annual cost saving is S. Hence post tax cost savings will be = S x (1 - 23%) = 0.77S

Hence, the present value of post tax cost savings will be = PV of annuity of 0.77S over five years = 0.77S x Sum of PV factors over five years = 0.77S x [1 - (1+R)-N] / R = 0.77S x [1 - (1 + 11%)-5] / 11% =  2.84584S

NPV equation will be:

NPV = -C0 + PV (DTS) + PV(TCF) + PV of post tax annual cost savings over five years = -880,000 + 138,306 + 133,574 + 2.84584S

For this project to be profitable, NPV = 0

or, -880,000 + 138,306 + 133,574 + 2.84584S = 0

Hence, S = (880,000 - 138,306 - 133,574) / 2.84584 =  213,687.21

Level of pretax cost savings do we require for this project to be profitable = S = $ 213,687.21

Add a comment
Know the answer?
Add Answer to:
A proposed cost-saving device has an installed cost of $735,000. The device will be used in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A proposed cost-saving device has an installed cost of $665,000. The device will be used in...

    A proposed cost-saving device has an installed cost of $665,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $75,000, the marginal tax rate is 24 percent, and the project discount rate is 13 percent. The device has an estimated Year 5 salvage value of $62,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...

  • A proposed cost-saving device has an installed cost of $660,000. The device will be used in...

    A proposed cost-saving device has an installed cost of $660,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $70,000, the marginal tax rate is 23 percent, and the project discount rate is 12 percent. The device has an estimated Year 5 salvage value of $59,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...

  • A proposed cost-saving device has an installed cost of $815,000. The device will be used in...

    A proposed cost-saving device has an installed cost of $815,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $87,000, the marginal tax rate is 21 percent, and the project discount rate is 11 percent. The device has an estimated Year 5 salvage value of $133,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...

  • A proposed cost-saving device has an installed cost of $654,000. The device will be used in...

    A proposed cost-saving device has an installed cost of $654,000. The device will be used in a five-year project but is classified as three-year MACRS (MACRS Table) property for tax purposes. The required initial net working capital investment is $48,500, the marginal tax rate is 30 percent, and the project discount rate is 15 percent. The device has an estimated Year 5 salvage value of $73,500.    What level of pretax cost savings do we require for this project to...

  • A proposed cost-saving device has an installed cost of $654,000. The device will be used in...

    A proposed cost-saving device has an installed cost of $654,000. The device will be used in a five-year project but is classified as three-year MACRS (MACRS Table) property for tax purposes. The required initial net working capital investment is $48,500, the marginal tax rate is 30 percent, and the project discount rate is 15 percent. The device has an estimated Year 5 salvage value of $73,500.    What level of pretax cost savings do we require for this project to...

  • A proposed cost-saving device has an installed cost of $760,000. The device will be used in...

    A proposed cost-saving device has an installed cost of $760,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $65,000, the marginal tax rate is 25 percent, and the project discount rate is 8 percent. The device has an estimated Year 5 salvage value of $100,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...

  • A proposed cost-saving device has an installed cost of $750,000. The device will be used in a five-year project but is...

    A proposed cost-saving device has an installed cost of $750,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $61,000, the marginal tax rate is 23 percent, and the project discount rate is 10 percent. The device has an estimated Year 5 salvage value of $94,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...

  • A proposed cost-saving device has an installed cost of $810,000. The device will be used in...

    A proposed cost-saving device has an installed cost of $810,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $85,000, the marginal tax rate is 25 percent, and the project discount rate is 10 percent. The device has an estimated Year 5 salvage value of $130,000. What level of pretax cost savings do we require for this project to be profitable?

  • A proposed cost-saving device has an installed cost of $760,000. The device will be used in...

    A proposed cost-saving device has an installed cost of $760,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $65,000, the tax rate is 25 percent, and the project discount rate is 8 percent. The device has an estimated Year 5 salvage value of $100,000. What level of pretax cost savings do we require for this project to be profitable? MACRS schedule...

  • A proposed cost-saving device has an installed cost of $450,000.    The device will be used in...

    A proposed cost-saving device has an installed cost of $450,000.    The device will be used in a five-year project, but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $30,000, the marginal tax rate is 35 percent, and the project discount rate is 12 percent.   The device has an estimated Year 5 salvage value of $75,000. What level of per year pretax cost savings do we require for this project to be profitable?...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT