Question

PLease answer all queations ASAP! wil rate 1. Georgia, Inc. has collected the following data on...

PLease answer all queations ASAP! wil rate

1.

Georgia, Inc. has collected the following data on one of its products. The actual cost of the direct materials used is:

Direct materials standard (3 lbs @ $2/lb) $6 per finished unit
Total direct materials cost variance—unfavorable $14,250
Actual direct materials used 100,000 lbs.
Actual finished units produced 25,000 units

Multiple Choice

  • $135,750.

  • $164,250.

  • $150,000.

  • $182,000.

  • $100,000.

  • 2.

    Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period.

    Direct labor standard (4.00 hrs. @ $7.10/hr.) $ 28.40 per unit
    Actual hours worked 11,900
    Actual rate per hour $ 7.70

    Multiple Choice

  • $8,400 unfavorable.

  • $7,770 favorable.

  • $11,900 favorable.

  • $7,770 unfavorable.

  • $8,400 favorable

  • 3.

    Grant Co. uses the following standard to produce a single unit of its product: Variable overhead (1.60 hrs. per unit @ $3.70/hr.) Actual data for the month show total variable overhead costs of $138,640, and 22,000 units produced. The total variable overhead variance is:

    Multiple Choice

  • $8,400F.

  • $8,400U.

  • $62,400U.

  • $62,400F.

  • $0.

  • 4.

    The following information relating to a company's overhead costs is available.

    Actual total variable overhead

    $ 100,000

    Actual total fixed overhead

    $ 19,000

    Budgeted variable overhead rate per machine hour

    $ 3.00

    Budgeted total fixed overhead

    $ 15,000

    Budgeted machine hours allowed for actual output

    37,000


    Based on this information, the total variable overhead variance is:

    Multiple Choice

  • $11,000 favorable.

  • $5,000 favorable.

  • $11,000 unfavorable.

  • $5,000 unfavorable.

  • $4,459 favorable

  • 5.

    Sanchez Company's output for the current period was assigned a $434,000 standard direct labor cost. The direct labor variances included a $10,850 unfavorable direct labor rate variance and a $4,340 favorable direct labor efficiency variance. What is the actual total direct labor cost for the current period?

    Multiple Choice

  • $418,810.

  • $449,190.

  • $444,850.

  • $440,510.

  • $427,490.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 1-

Total unit produced =25000

Standard cost/unit =$6

Total standard cost= 150000

Add unfavorable variance = 14250

Actual cost of direct material used= 164250

Answer 2-

Actual direct labor cost=

Actual Hours worked×Actual rate per hour

= 11900×7.7= 91630

Standard direct labor= 28.40×3500 =99400

If actual is less than standard than variance is favorable

Hence 99400-91630= 7700 favorable

Answer 3-

Standard per unit variable overhead= 1.6×3.7=5.92

Total production= 22000,

Standard variable overhead = 5.92×22000=130240

Actual variable overhead= 138640

Standard- Actual

= 130240-138640

=8400 Unfavorable

Answer 4-

Total standard variable cost = Budgeted hour rate × Budgeted hours

= 3 × 37000 = 111000

Actual variable cost = 100000

Total variable overhead variance = Budgeted - Actual

=111000 - 100000

=11000 favorable

Answer 5-

Standard direct labour cost = 434000

Less Direct labour variances = 10850

Add Direct labour rate variance = 4340

Actual total direct labour cost = 434000 - 10850 + 4340

= 427490

Note: All the answers are in Dollar($) only.

Add a comment
Know the answer?
Add Answer to:
PLease answer all queations ASAP! wil rate 1. Georgia, Inc. has collected the following data on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Georgia, Inc. has collected the following data on one of its products. The direct materials quantity variance IS. Dir...

    Georgia, Inc. has collected the following data on one of its products. The direct materials quantity variance IS. Direct materials standard (3 lbs $1/1b) Total direct materials cost variance-unfavorable $24,250 $3 per finished unit Actual direct materials used 108,000 lbs. 27,000 units Actual finished units produced Multiple Choice $24,250 unfavorable. $27,000 favorable. $2,750 favorable. $24,250 favorable. $27,000 unfavorable. A company has an overhead application rate of 128% of direct labor costs. How much overhead would be allocated to a job...

  • Georgia, Inc. has collected the following data on one of its products. The direct materials quantity...

    Georgia, Inc. has collected the following data on one of its products. The direct materials quantity variance is: Direct materials standard (2 lbs @ $1/lb) $2 per finished unit Total direct materials cost variance—unfavorable $20,750 Actual direct materials used 72,000 lbs. Actual finished units produced 24,000 units Multiple Choice $24,000 unfavorable. $20,750 unfavorable. $3,250 favorable. $20,750 favorable. $24,000 favorable.

  • Fletcher Company collected the following data regarding production of one of its products. Compute the variable...

    Fletcher Company collected the following data regarding production of one of its products. Compute the variable overhead efficiency variance. Direct labor standard (2 hrs. @ $12.40/hr.) $ 24.80 per finished unit Actual direct labor hours 96,500 hrs. Budgeted units 56,000 units Actual finished units produced 47,500 units Standard variable OH rate (2 hrs. @ $15.00/hr.) $ 30.00 per finished unit Standard fixed OH rate ($526,400/56,000 units) $ 9.40 per unit Actual cost of variable overhead costs incurred $ 1,417,000 Actual...

  • PLEASE ANSWER QUESTIONS CORRECTLY !!!! 1. 2. 3. 4. PLEASE ANSWER QUESTIONS CORRECTLY !!!! Use the...

    PLEASE ANSWER QUESTIONS CORRECTLY !!!! 1. 2. 3. 4. PLEASE ANSWER QUESTIONS CORRECTLY !!!! Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period. Direct labor standard (4.00 hrs. @ $6.20/hr.) Actual hours worked Actual rate per hour $ 24.80 per unit 12,050 $ 6.30 Multiple Choice . $12,050 favorable 0 $10.885 unfavorable. 0 $10,885 favorable. 0 $1,400 favorable. O $1,400 unfavorable. Fletcher Company collected the following data regarding...

  • Georgia, Inc. has collected the following data on one of its products. The direct materials quantity...

    Georgia, Inc. has collected the following data on one of its products. The direct materials quantity variance is: Direct materials standard (2 lbs @ $1/lb) $ 2 per finished unit Total direct materials cost variance—unfavorable $ 17,750 Actual direct materials used 60,000 lbs Actual finished units produced 20,000 units $17,750 unfavorable. $20,000 favorable. $17,750 favorable. $20,000 unfavorable. $2,250 favorable.

  • Georgia, Inc. has collected the following data on one of its products. The actual cost of...

    Georgia, Inc. has collected the following data on one of its products. The actual cost of the direct materials used is: Direct materials standard (2 lbs @ $3/lb) $6 per finished unit Total direct materials cost variance—unfavorable $25,250 Actual direct materials used 75,000 lbs. Actual finished units produced 25,000 units Multiple Choice $200,750. $75,000. $175,250. $124,750. $150,000.

  • Use the following data to find the total direct labor cost variance if the company produced...

    Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period. Direct labor standard (4.00 hrs. @ $6.70/hr.) $ 26.80 per unit Actual hours worked 12,300 Actual rate per hour $ 7.30 Multiple Choice $4,010 favorable. $12,300 favorable. $4,010 unfavorable. $8,400 favorable. $8,400 unfavorable.

  • Use the following data to find the total direct labor cost variance if the company produced...

    Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period. Direct labor standard (4.00 hrs. @ $6.70/hr.) $ 26.80 per unit Actual hours worked 12,300 Actual rate per hour $ 7.30 Multiple Choice $12,300 favorable. $8,400 favorable. $4,010 unfavorable. $8,400 unfavorable. $4,010 favorable.

  • Georgia, Inc. has collected the following data on one of its products. The actual cost of the direct materials used is:...

    Georgia, Inc. has collected the following data on one of its products. The actual cost of the direct materials used is: Direct materials standard (3 lbs @ $2/lb) $6 per finished unit Total direct materials cost variance—unfavorable $14,250 Actual direct materials used 100,000 lbs. Actual finished units produced 25,000 units $135,750. $150,000. $100,000. $164,250. $182,000.

  • W 13. Woods, Inc. budgeted the following overhead costs for the current year assuming operations at...

    W 13. Woods, Inc. budgeted the following overhead costs for the current year assuming operations at 80% of capacity, of 40,000 units Please show all your work. Attach a separate sheet to the exam if necessary. Total variable overhead .. Total fixed overhead. Total overhead. $240,000 560.000 $800,000 The standard cost per unit when operating at this same 80% capacity level is: con Direct materials (5 lbs. @ S4/lb.) ..... Direct labor (2 hrs. @ 58.75 hr.) ..... $20.00 17.50...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT