If Sandler Industries re-engineer the production process, the machine drool would be reduced by 40% each month.
Amount of reduction in drool = 120 * 40% = 48 tonnes per month
Annual reduction = 48 * 12 = 576 tonnes
Remaining drool = (120 - 48) = 72 tonnes per month
The reduction of 576 tonnes will result in savings in direct material and waste disposal costs.
Reduction in Direct Materials Costs (576*78) = $44,928
Reduction in Waste Disposal Costs (576*53) =$30,528
Amount received from local recycler [ 72* 12 * 20) = $17,280
Annual Cost to Engineer = $40,000
Total annual savings(net) = $44,928 + $30,528 + $17,280 - $40,000 = $52,736