Problem 10-9 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3] Marvel Parts, Inc., manufactures auto accessories. One of the company’s products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 2,850 hours each month to produce 1,900 sets of covers. The standard costs associated with this level of production are: Total Per Set of Covers Direct materials $ 42,560 $ 22.40 Direct labor $ 17,100 9.00 Variable manufacturing overhead (based on direct labor-hours) $ 6,840 3.60 $ 35.00 During August, the factory worked only 2,800 direct labor-hours and produced 2,000 sets of covers. The following actual costs were recorded during the month: Total Per Set of Covers Direct materials (12,000 yards) $ 45,600 $ 22.80 Direct labor $ 18,200 9.10 Variable manufacturing overhead $ 7,000 3.50 $ 35.40 At standard, each set of covers should require 5.6 yards of material. All of the materials purchased during the month were used in production. Required: 1. Compute the materials price and quantity variances for August. (Input all amounts as positive values. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e, zero variance).) 2. Compute the labor rate and efficiency variances for August. (Input all amounts as positive values. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e, zero variance).) 3. Compute the variable overhead rate and efficiency variances for August. (Input all amounts as positive values. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e, zero variance

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) Material price variance = (4*12000-45600) = 2400 F

Material quantity variance = (2000*5.6-12000)*4 = 3200 U

2) Labor rate variance = (6*2800-18200) = 1400 U

Labor efficiency variance = (2000*1.5-2800)*6 = 1200 F

3) variable overhead rate variance = (2.4*2800-7000) = 280 U

variable overhead efficiency variance = (3000-2800)*2.4 = 480 F

Add a comment
Know the answer?
Add Answer to:
Problem 10-9 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3] Marvel Parts, Inc., manufactures auto accessories. One of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT