Question

Kolby’s Korndogs is looking at a new sausage system with an installed cost of $675,000. This...

Kolby’s Korndogs is looking at a new sausage system with an installed cost of $675,000. This cost will be depreciated straight-line to zero over the project’s 5-year life, at the end of which the sausage system can be scrapped for $89,000. The sausage system will save the firm $191,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $43,000. If the tax rate is 24 percent and the discount rate is 8 percent, what is the NPV of this project?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Time line 0 1 2 3 4 5
Cost of new machine -675000
Initial working capital -43000
=Initial Investment outlay -718000
100.00%
Savings 191000 191000 191000 191000 191000
-Depreciation Cost of equipment/no. of years -135000 -135000 -135000 -135000 -135000 0 =Salvage Value
=Pretax cash flows 56000 56000 56000 56000 56000
-taxes =(Pretax cash flows)*(1-tax) 42560 42560 42560 42560 42560
+Depreciation 135000 135000 135000 135000 135000
=after tax operating cash flow 177560 177560 177560 177560 177560
reversal of working capital 43000
+Proceeds from sale of equipment after tax =selling price* ( 1 -tax rate) 67640
+Tax shield on salvage book value =Salvage value * tax rate 0
=Terminal year after tax cash flows 110640
Total Cash flow for the period -718000 177560 177560 177560 177560 288200
Discount factor= (1+discount rate)^corresponding period 1 1.08 1.1664 1.259712 1.360489 1.4693281
Discounted CF= Cashflow/discount factor -718000 164407.4074 152229.0809 140952.8527 130511.9 196144.08
NPV= Sum of discounted CF= 66245.32
Add a comment
Know the answer?
Add Answer to:
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $675,000. This...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Kolby’s Korndogs is looking at a new sausage system with an installed cost of $740,000. This...

    Kolby’s Korndogs is looking at a new sausage system with an installed cost of $740,000. This cost will be depreciated straight-line to zero over the project’s 7-year life, at the end of which the sausage system can be scrapped for $102,000. The sausage system will save the firm $217,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $69,000. If the tax rate is 22 percent and the discount rate is...

  • Kolby’s Korndogs is looking at a new sausage system with an installed cost of $730,000. This...

    Kolby’s Korndogs is looking at a new sausage system with an installed cost of $730,000. This cost will be depreciated straight-line to zero over the project’s 7-year life, at the end of which the sausage system can be scrapped for $100,000. The sausage system will save the firm $213,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $65,000. If the tax rate is 25 percent and the discount rate is...

  • Kolby’s Korndogs is looking at a new sausage system with an installed cost of $660,000. This...

    Kolby’s Korndogs is looking at a new sausage system with an installed cost of $660,000. This cost will be depreciated straight-line to zero over the project’s 5-year life, at the end of which the sausage system can be scrapped for $86,000. The sausage system will save the firm $185,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $37,000. If the tax rate is 21 percent and the discount rate is...

  • Kolby’s Korndogs is looking at a new sausage system with an installed cost of $710,000. This...

    Kolby’s Korndogs is looking at a new sausage system with an installed cost of $710,000. This cost will be depreciated straight-line to zero over the project’s 6-year life, at the end of which the sausage system can be scrapped for $96,000. The sausage system will save the firm $205,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $57,000. If the tax rate is 21 percent and the discount rate is...

  • Kolby’s Korndogs is looking at a new sausage system with an installed cost of $665,000. This...

    Kolby’s Korndogs is looking at a new sausage system with an installed cost of $665,000. This cost will be depreciated straight-line to zero over the project’s 5-year life, at the end of which the sausage system can be scrapped for $87,000. The sausage system will save the firm $187,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $39,000. If the tax rate is 22 percent and the discount rate is...

  • Kolby’s Korndogs is looking at a new sausage system with an installed cost of $725,000. This cost will be depreciated st...

    Kolby’s Korndogs is looking at a new sausage system with an installed cost of $725,000. This cost will be depreciated straight-line to zero over the project’s 7-year life, at the end of which the sausage system can be scrapped for $99,000. The sausage system will save the firm $211,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $63,000. If the tax rate is 24 percent and the discount rate is...

  • Kolby’s Korndogs is looking at a new sausage system with an installed cost of $715,000. This cost will be depreciated st...

    Kolby’s Korndogs is looking at a new sausage system with an installed cost of $715,000. This cost will be depreciated straight-line to zero over the project’s 6-year life, at the end of which the sausage system can be scrapped for $97,000. The sausage system will save the firm $207,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $59,000. If the tax rate is 22 percent and the discount rate is...

  • Kolby’s Korndogs is looking at a new sausage system with an installed cost of $720,000. This cost will be depreciated st...

    Kolby’s Korndogs is looking at a new sausage system with an installed cost of $720,000. This cost will be depreciated straight-line to zero over the project’s 6-year life, at the end of which the sausage system can be scrapped for $98,000. The sausage system will save the firm $209,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $61,000. If the tax rate is 23 percent and the discount rate is...

  • Kolby’s Korndogs is looking at a new sausage system with an installed cost of $725,000. This...

    Kolby’s Korndogs is looking at a new sausage system with an installed cost of $725,000. This cost will be depreciated straight-line to zero over the project’s 7-year life, at the end of which the sausage system can be scrapped for $99,000. The sausage system will save the firm $211,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $63,000. If the tax rate is 24 percent and the discount rate is...

  • Kolby’s Korndogs is looking at a new sausage system with an installed cost of $705,000. This...

    Kolby’s Korndogs is looking at a new sausage system with an installed cost of $705,000. This cost will be depreciated straight-line to zero over the project’s 6-year life, at the end of which the sausage system can be scrapped for $95,000. The sausage system will save the firm $203,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $55,000. If the tax rate is 25 percent and the discount rate is...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT