Question

Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92...

Exercise 2-3

A job order cost sheet for Ryan Company is shown below.

Job No. 92

For 2,000 Units


Date

Direct
Materials

Direct
Labor

Manufacturing
Overhead

Beg. bal. Jan. 1 5,200 6,000 4,200
8 6,000
12 10,000 7,500
25 2,700
27 4,000 3,000
13,900 20,000 14,700
Cost of completed job:
   Direct materials $13,900
   Direct labor 20,000
   Manufacturing overhead 14,700
Total cost $48,600
Unit cost ($48,600 ÷ 2,000) $24.30


(a) On the basis of the foregoing data, answer the following questions.

(1) What was the balance in Work in Process Inventory on January 1 if this was the only unfinished job?

Balance in Work in Process Inventory on January 1 $


(2) If manufacturing overhead is applied on the basis of direct labor cost, what overhead rate was used in each year? (Round answers to 0 decimal places, e.g. 55%.)

Last year Current year
Overhead rate

%

%


(b) Prepare summary entries at January 31 to record the current year’s transactions pertaining to Job No. 92. (Credit account titles are automatically indented when amount is entered. Do not indent manually.)

Date

Account Titles and Explanation

Debit

Credit

Jan. 31

(To record raw materials used)

31

(To record factory labor used)

31

(To record manufacturing overhead)

31

(To record job completed)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution Balance in work in process Inventory on January 1 = 5200 + 6000 + 4200 = 15400 2) Manufacturing overhead rate = MaDate ! Account title and Explanation Debit Gredit Jan 31 | 33200 8700 14000 10500 work in process Inventory Job No 92 Dlouct

Add a comment
Know the answer?
Add Answer to:
Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Direct Materials Direct Labor Manufacturing Overhead Date Beg. bal. Jan. 1 5,100 7,000 4.900 7,000 8,000 6,000 2,800 5,000 3,750 14,900 20,000 14,650 Cost of completed job: Direct materials $14,900 Direct labor 20,000 Manufacturing overhead 14,650 Total cost $49,550 Unit cost ($49,550 = 2,000) $24.78 (a) On the basis of the foregoing data, answer the following questions. (a) On the basis of the...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead 4,900 Date 7,000 Beg. bal. Jan. 1 8 6,000 7,000 12 10,000 8,500 25 2,500 27 4,000 3,400 16,800 15,500 21,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($53,300 = 2,000) $15,500 21,000 16,800 $53,300 $26.65 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92...

    Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing | Overhead Date Beg. bal. Jan. 1 6,700 7,000 4,900 7,000 10,000 7,500 2,800 4,000 21,000 3,000 15,400 16,500 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($52,900 + 2,000) $16,500 21,000 15,400 $52,900 $26.45 (a) On the basis of the foregoing data, answer the following questions. (1) What was...

  • A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Manufacturing Direct Materials Labor Date Overhead Beg. bal 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor Direct Materials 5,200 7,000 For 2,000 Units Manufacturing Overhead 4,900 7,000 Date Beg. bal. Jan. 1 8 12 25 27 10,000 8,000 2,900 5,000 4,000 16,900 15,100 22,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($54,000 = 2,000) $15,100 22,000 16,900 $54,000 $27.00 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 1 5,500 6,700 4,690 6,700 8,800 7,040 2,900 4,000 19,500 3,200 14,930 15,100 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($49,530 + 2,000) $15,100 19,500 14,930 $49,530 $24.77 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...

  • A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Materials Labor Direct Manufacturing Date Overhead Beg. bal. 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Manufacturing overhead Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 5,300 6,000 4,200 8 6,000 12 7,000 5,600 25 2,500 27 4,000 3,200 13,800 17,000 13,000 Cost of completed job:    Direct materials $13,800    Direct labor 17,000    Manufacturing overhead 13,000 Total cost $43,800 Unit cost ($43,800 ÷ 2,000) $21.90 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • Current Attempt in Progress A job order cost sheet for Ryan Company is shown below. Job...

    Current Attempt in Progress A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials 6,300 7,000 Direct Labor 7,000 For 2,000 Units Manufacturing Overhead 4,900 Date Beg. bal. Jan. 1 8 12 25 27 9,000 7,200 3,000 4,000 20,000 3,200 15,300 16,300 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($51,600 + 2,000) $16,300 20,000 15,300 $51,600 $25.80 (a) On the basis of the foregoing data, answer the...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 6,500 6,000 4,200 6,000 8,000 6,800 25 3,000 4,000 18,000 15,500 3,400 14,400 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (547,900 = 2.000) $15,500 18,000 14,400 $47.900 $23.95 (a) on the basis of the foregoing data, answer the following questions. (1) What was the balance...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT