a) As mentioned that transaction price for the contract. at 70% chance of the building will be completed by August 1, 2018, therefore, Sheridian Corp. will most likely estimate the amount $148,200
b) There is a limited information available to develop a reliable estimate of completion by the August 1, 2018, therefore no revenue can be recognized till the assurance of completion of contract get resolved. Therefore, there will be no revenue will be recognized till the contract gets completed.
part A and b user to budan spartment buiding for $1,030,000. The 1, 2018 Theo d...
Sheridan Corp. enters into a contract with a customer to build an apartment building for $1,039,000. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $148,200 to be paid if the building is ready for rental beginning August 1,2018.The bonus is reduced by $49,400 each week that completion is delayed. Sheridan commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: August...
Pearl Corp. enters into a contract with a customer to build an apartment building for $1,000,800. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $135,600 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $45,200 each week that completion is delayed. Pearl commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion...
Carla Corp. enters into a contract with a customer to build an apartment building for $1,040,800. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $161,700 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $53,900 each week that completion is delayed. Carla commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion...
Blue Corp. enters into a contract with a customer to build an apartment building for $1,015,200. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $159,900 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $53,300 each week that completion is delayed. Blue commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion...
please explain your answer CALCULATOR FULL SCREEN PRINTER VERSION 4BACK NE Brief Exercise 18-6 Windsor Corp. enters into a contract with a customer to build an apartment building for $1,015,200. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $159,900 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $53,300 each week that completion is delayed. Windsor commonly includes these...
How do you calculate the Transaction Price? Ayayai Corp. enters into a contract with a customer to build an apartment building for $930,000. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $151,500 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $50,500 each week that completion is delayed. Ayayai commonly includes these completion bonuses in its contracts and, based...
Brief Exercise 18-7 Oriole Corp. enters into a contract with a customer to build an apartment building for $1,045,500. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $139,800 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $46,600 each week that completion is delayed. Oriole commonly includes these completion bonuses in its contracts and, based on prior experience, estimates...
uestion 1 Concord Corp, enters into a contract with a customer to build an apartment building for $1,079,000. The customer hopes to rent apartments at the beginning of the school year and provides a erformance bonus of $153,000 to be paid if the building is ready for rental beginning August 1, 2021. The bonus is reduced by $51,000 each week that completion is delayed. Concord commonly mcludes these completion bonuses in its contracts and, based on prior experience, estimates the...
please help with questions 1 - 6. Thanks M N O B C D E G H KL Your task is to make an estimate of McCormick & Company's weighted Average cost of Capital (WACC) to use as the discount rate for evaluating capital projects. Interest rates have risen and the CFO plans to borrow $350 million using the 20 year bond that you recommended in Project 4. For most of the past 10 years the company has used 7%...