Question

Show me step by step on how to solve this problem in Excel, thanks. Tempura, Inc.,...

Show me step by step on how to solve this problem in Excel, thanks.

Tempura, Inc., is considering two projects. Project A requires an investment of $50,000. Estimated annual receipts for 20 years are $20,000; estimated annual costs are $12,500. An alternative project, B, requires an investment of $75,000, has annual receipts for 20 years of $28,000, and has annual costs of $18,000. Assume both projects have zero salvage value and that MARR is 12 percent/year.

a. What is the annual worth of each project?

b. Which project should be recommended?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a) For each project, Net annual benefit = Annual receipts - Annual cost

Project A: $(20,000 - 12,500) = $7,500

Project B: $(28,000 - 18,000) = $10,000

(i) Cash flow dagram (All values in $)

20000 20000 20000 .. a 3 ... ... 20 Soooo 2500 12500 11500...... 1230D 28000 28000 28000....... 75000 1000 18000 18000 .....

(ii) Present worth (PW) is computed as follows.

PW, Project A ($) = - 50,000 + 7,500 x P/A(12%, 20) = - 50,000 + 7,500 x 7.4694** = - 50,000 + 56,021 = 6,021

PW, Project B ($) = - 75,000 + 10,000 x P/A(12%, 20) = - 75,000 + 10,000 x 7.4694** = - 75,000 + 74,694 = - 306

(b) Since Project A has a positive PW, this should be recommended.

**From PP/A factor table

Add a comment
Know the answer?
Add Answer to:
Show me step by step on how to solve this problem in Excel, thanks. Tempura, Inc.,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Tempura, Inc., is considering two projects. Project A requires an investment of $44,000. Estimated annual receipts...

    Tempura, Inc., is considering two projects. Project A requires an investment of $44,000. Estimated annual receipts for 20 years are $23,000; estimated annual costs are $12,500. An alternative project, B, requires an investment of $77,000, has annual receipts for 20 years of $33,000, and has annual costs of $18,000. Assume both projects have a zero salvage value and that MARR is 13.0 %/year.

  • A company is considering two investment alternatives Alternative A is a new machine that costs $50,000...

    A company is considering two investment alternatives Alternative A is a new machine that costs $50,000 and will last for ten years with no salvage value. It will save the company $9445 per year. Alternative B is a is a machine that will cost $75,000 and last 10 years. The salvage value at the end of 10 years is $25,000. It will save $12390 per year Find the Annual worth of each alternative if the company as a MARR of...

  • "Engineering Economics" How do you solve this using excel? 1. A machine costs $35,000 to buy...

    "Engineering Economics" How do you solve this using excel? 1. A machine costs $35,000 to buy and $5,000 per year to operate and maintain. It will have a salvage value of $8,000 in 9 years. It will generate $10,000 per year in net revenue for the first four years, and then the revenue will fall by $1,000 each year after. If the company purchasing the machine uses a MARR of 7% to make project, find the NPW, NEW, and AW....

  • Please show code if you use excel thank you. Project A has a first cost of...

    Please show code if you use excel thank you. Project A has a first cost of $3,500, annual operating and maintenance costs of $1,900, annual savings of $2,300, and a salvage value of $1,800 at the end of its 5 year useful life. Project B has a first cost of $6,000, annual operating and maintenance costs of $1,600, annual savings of $2,500, and a salvage value of $2,000 at the end of its 7 year useful life. Using a MARR...

  • 15 points (5 for correct AW of each, 5 for correct decision) 15. + Final Finishing...

    15 points (5 for correct AW of each, 5 for correct decision) 15. + Final Finishing is considering three mutually exclusive alternatives for a new polisher. Each alternative has an expected life of 10 years and no salvage value. Polisher 1 requires an initial investment of $20,000 and provides annual benefits of $4,465. Polisher 2 requires an initial investment of $10,000 and provides annual benefits of $1,770. Polisher 3 requires an initial investment of $15,000 and provides annual benefits of...

  • please show excel formulas so I can understand the problem THANKS 9-50 Consider four mutually exclusive...

    please show excel formulas so I can understand the problem THANKS 9-50 Consider four mutually exclusive alternatives: (Α) A B C D Cost $75.0 $50.0 $15.0 $90.0 Uniform annual 18.8 13.9 4.5 23.8 benefit Each alternative has a 5-year useful life and no sal- vage value. The MARR is 10%. Which alternative should be selected, based on (a) The payback period (b) Future worth analysis (c) Benefit-cost ratio analysis

  • USE SOLVER IN EXCEL TO ANSWER PROBLEM. Show step by step how you got your answer...

    USE SOLVER IN EXCEL TO ANSWER PROBLEM. Show step by step how you got your answer SOLVER | 387 18-2. Seven new projects are being proposed for our division. Each would require investments over the next three years, but each ultimately would result in a positive return on our investment Project A B с D E F G Expenditures in $ Millions Year 1 Year 2 Year 3 5 8 4 7 9 3 8 4 3 9 2 7...

  • Please do not use Excel to solve this problem, using financial calculator and show steps. 5....

    Please do not use Excel to solve this problem, using financial calculator and show steps. 5. CAD Corporation is considering some new equipment whose data are shown below. The equipment has a 3-year tax life and would be fully depreciated by the straight-line method over 3 years, but it would have a positive pre-tax salvage value at the end of Year 3, when the project would be closed down. Also, additional inventories would be required, but it would be recovered...

  • There are two vendors submitting bids for a new parking lot gate. The first company expects...

    There are two vendors submitting bids for a new parking lot gate. The first company expects the gate to last 5 years. The second company expects their gate to last 6 years. Both companies provide quotes for purchase price, operating costs, and estimated future salvage value. Explain the three methods for considering the difference in service life for these two products that are being considered (10 points) A company has a choice between 2 projects. The first option requires an...

  • My Not A company is considering two investment alternatives. Alternative A is a new machine that...

    My Not A company is considering two investment alternatives. Alternative A is a new machine that costs $50,000 and will last for ten years with no salvage value. It will save the company $8445 per year. Alternative B is a is a machine that will cost $75,000 and last 10 years. The salvage value at the end of 10 years is $25,000. It will save $11743 per year Find the Annual worth of each alternative if the company as a...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT