Solution 1:
Predetermined plantwide overhead rate = $4160000/ $128000 = $32.50
plantwide overhead applied to Job Bravo = $32.50* 26 = $845
Solution 2:
Computation of departmental Overhead rate | ||
Assembly | Fabrication | |
Overhead Cost | $19,20,000 | $22,40,000 |
/ Direct Labor hours | 80000 | |
/ Machine hours | 160000 | |
Departmental Overhead rate | $24 | $14 |
Allocation of Overhead to Job Bravo | ||
Assembly | Fabrication | |
Direct labor hours | 17 | |
Machine hours | 12 | |
* Departmental Overhead rate | $24 | $14 |
Allocated Overhead | $408 | $168 |
Total = 408 + 168 = $576
Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs...
Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year--Job Bravo. Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $ 1,920,000 80,000 32,000 Fabrication $2,240,000 48,000 160,000 Total $ 4,160,000 128,000 192,000 Assembly Fabrication Job Bravo...
Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year--Job Bravo. Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Asserbly $ 1,920,000 80,000 32,000 Fabrication $ 2, 240,000 48,000 160,000 Total $ 4,160,000 128,000 192,000 Total 26...
Wilmington Company has two manufacturing departments—Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year—Job Bravo. Estimated Data Assembly Fabrication Total Manufacturing overhead costs $ 1,920,000 $ 2,240,000 $ 4,160,000 Direct labor-hours 80,000 48,000 128,000 Machine-hours 32,000 160,000 192,000 Job Bravo Assembly...
Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year--Job Bravo. $ Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $ 600,000 50,000 20,000 Fabrication $ 800,000 30,000 100,000 Total 1,400,000 80,000 120,000 Assembly Fabrication Total...
Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year--Job Bravo. Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $3,570,000 105,000 42,000 Fabrication $3,990,000 63.000 Total $ 7,560,000 168.000 252,000 Job Bravo Direct labor-hours Machine-hours chours...
Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year--Job Bravo. Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $ 2,210,000 85,000 34,000 Fabrication $ 2,550,000 51,000 170,000 Total $4,760,000 136,000 204,000 Job Bravo Direct labor-hours...
Wilmington Company has two manufacturing departments-Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year-Job Bravo. Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $5,250,000 125.000 50,000 Fabrication $5,750,000 75.000 250.000 Total $11,000,000 200,000 300.000 Assembly Fabrication Total Job Bravo Direct...
Wilmington Company has two manufacturing departments-Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year-Job Bravo. Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $ 770,000 55,000 22,000 Fabrication $ 990,000 33,000 110,000 Total $ 1,760,000 88,000 132,000 Job Bravo Direct...
Wilmington Company has two manufacturing departments-Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year-Job Bravo. Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $ 3,570,000 105,000 42,000 Fabrication $ 3,990,000 63,000 210.000 Total $ 7,560,000 168,000 252.000 Assembly Fabrication Total...
Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year--Job Bravo. Estimated Data Assembly Fabrication Total Manufacturing overhead costs $ 1,650,000 $ 1,950,000 $ 3,600,000 Direct labor-hours 75,000 45,000 120,000 Machine-hours 30,000 150,000 180,000 Job Bravo Assembly...