Question

The job costing system at Suzys Custom Framing has ve indirect contpools (purchasing, material handing machine maintenance p
Requirement 1. Compute the total overhead allocated to each job under a simple costing system, where overhead is allocated ba
Requirement 2. Compute the total overhead allocated to each job under an activity-based costing system using the appropriate
Now calculate the total overhead allocated to Job 215 and Job 325 under an activity-based costing system. (Round interim calc
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer Calculation Requirement - of overhead rate under simple Costing system overhead is anocated based on machine hours a Bunder Activity based costing system Calculation of overhead rate Purchasing Purchasing overhead Purchased order Processed 19sAllocation Cost of Job total overhead 325 Purchasing - 13x a = 117 mat, handling - lox 6 & 60 Machi maint - 12 x 80 = 960 Ins

Add a comment
Know the answer?
Add Answer to:
The job costing system at Suzy's Custom Framing has ve indirect contpools (purchasing, material handing machine...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The job costing system at Shannon's Custom Framing has five indirect cost pools (purchasing, material handling,...

    The job costing system at Shannon's Custom Framing has five indirect cost pools (purchasing, material handling, machine maintenance, product inspection, and packaging). The company is in the process of bidding on two jobs, Job 215, an order of 15 intricate personalized frames, and Job 325, an order of 5 standard personalized frames. The controller wants you to compare overhead allocated under the current simple job-costing system and a newly designed activity-based job costing system. Total budgeted costs in each indirect...

  • The job costing system at Shelby's Custom Framing has five indirect cost pools (purchasing, material handling,...

    The job costing system at Shelby's Custom Framing has five indirect cost pools (purchasing, material handling, machine maintenance, product inspection, and packaging). The company is in the process of bidding on two jobs; Job 215, an order of 16 intricate personalized frames, and Job 325, an order of 4 standard personalized frames. The controller wants you to compare overhead alocated under the current simple job-costing system and a newly designed activity-based job-costing system. Total budgeted costs in each indirect cost...

  • The job costing system at Shirley's Custom Framing has five indirect cost pools (purchasing, material handling,...

    The job costing system at Shirley's Custom Framing has five indirect cost pools (purchasing, material handling, machine maintenance, product inspection, and packaging). The company is in the process of bidding on two jobs; Job 215, an order of 17 intricate personalized frames, and Job 325, an order of 6 standard personalized frames. The controller wants you to compare overhead allocated under the current simple job-costing system and a newly designed activity-based job-costing system. Total budgeted costs in each indirect cost...

  • The job costing system at Shirley's Custom Framing has five indirect cost pools (purchasing, material handling,...

    The job costing system at Shirley's Custom Framing has five indirect cost pools (purchasing, material handling, machine maintenance, product inspection, and packaging). The company is in the process of bidding on two jobs; Job 215, an order of 17 intricate personalized frames, and Job 325, an order of 6 standard personalized frames. The controller wants you to compare overhead allocated under the current simple job-costing system and a newly designed activity-based job-costing system. Total budgeted costs in each indirect cost...

  • The job costing system at Suzy's Custom Framing has five indirect cost pools (purchasing, material handling,...

    The job costing system at Suzy's Custom Framing has five indirect cost pools (purchasing, material handling, machine maintenance, product inspection, and packaging). The company is in the process of bidding on two jobs; Job 215, an order of 15 intricate personalized frames, and Job 325, an order of 5 standard personalized frames. The controller wants you to compare overhead allocated under the current simple job-costing system and a newly designed activity-based job-costing system. Total budgeted costs in each indirect cost...

  • 1. Compute the total overhead allocated to each job under a simple costing​ system, where overhead...

    1. Compute the total overhead allocated to each job under a simple costing​ system, where overhead is allocated based on​ machine-hours. 2. Compute the total overhead allocated to each job under an​ activity-based costing system using the appropriate activity drivers. 3. Explain why Shirley's Custom Framing might favor the ABC​ job-costing system over the simple​ job-costing system, especially in its bidding process. *There should be 10 total parts to this problem. The job-costing system at Shirley's Custom Framing has five...

  • 19.62 per mach. hour Now calculate the total overhead allocated to each job under a simple...

    19.62 per mach. hour Now calculate the total overhead allocated to each job under a simple costing system. (Round your answer to the nearest cent) Simple costing system Job 220 Job 330 Indirect cost allocaterd 588.60 S 1,373.40 Requirement 2. Compute the total overhead allocated to each job under an activity-based costing system using the appropriate activity drivers (Rou the allocation rates to three decimal places, X.X0X. Abbreviations used:bgt budgoted, mach. machine, maint.. purch. purchase, aty. quantity, prod. produced.) maintonanoe,...

  • on 3 (30 points) The job-costing system at the Ale material movement machine mai Jobs. Alexander...

    on 3 (30 points) The job-costing system at the Ale material movement machine mai Jobs. Alexander Fabricating the three maintenance, and other. The company is in the The following information is provided com Material movement costs Budested overhead Machine maintenance $ 490,000 5 770,000 Other S 680.000 Acthy Dee Material moves Machine hours Direct Labor hours Budo DO 1.000 0940,000 REQUIRED Show all Work 1. Compute the manufacturing overhead rate to be used to allocate overhead to each job under...

  • MacBook Ar iey based eosting. The job-costing system a Mel and packaging he company is in...

    MacBook Ar iey based eosting. The job-costing system a Mel and packaging he company is in the process of bidding on two Johs: Joi ody's Custom erhead alloca activity-based job-costing system. Total budgeted system and a new.ly designed inlinest cvst peoso and the budged quantity of activity driver are as follows Budgeted Gity Aetivity Driv Budgeted Overhesd 6800 Packaging Unts produced Information related to Job 220 and Job 330 follows. Job 220 incurs more batch-level so because it uses more...

  • FireWorks produces mild-steel outdoor products, including two firepit models. The bulk of firepit sales come from...

    FireWorks produces mild-steel outdoor products, including two firepit models. The bulk of firepit sales come from their standard firepit – a basic half-sphere design. FireWorks’ custom firepit involves innovative designs and some intricate cutting work and, although sales volume is low, custom firepits generate a significantly higher sales price. Increasingly, FireWorks has been struggling competitively on price with its standard product although its custom firepits are a flaming success. Currently, FireWorks uses a simple job-costing system and allocates overhead based...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework