Thane Company is
interested in establishing the relationship between electricity
costs and machine hours. Data have been collected and a regression
analysis prepared using Excel. The monthly data and the regression
output follow:
Month | Machine Hours | Electricity Costs | ||
January | 3,000 | $ | 18,650 | |
February | 3,400 | $ | 21,500 | |
March | 2,400 | $ | 13,750 | |
April | 3,600 | $ | 23,500 | |
May | 4,300 | $ | 28,500 | |
June | 3,800 | $ | 22,500 | |
July | 4,600 | $ | 25,000 | |
August | 4,000 | $ | 23,000 | |
September | 2,500 | $ | 16,000 | |
October | 4,200 | $ | 26,500 | |
November | 5,600 | $ | 31,500 | |
December | 5,200 | $ | 28,000 | |
Summary Output | |
Regression Statistics | |
Multiple R | 0.952 |
R Square | 0.906 |
Adjusted R2 | 0.897 |
Standard Error | 1,676.51 |
Observations | 12.00 |
Coefficients | Standard Error | t Stat | P-value | Lower 95% | Upper 95% | |
Intercept | 3,639.33 | 2,048.60 | 1.78 | 0.11 | (925.25) | 8,203.90 |
Machine Hours | 5.04 | 0.51 | 9.83 | 0.00 | 3.89 | 6.18 |
Based on the results of the regression analysis, the estimate of
electricity costs in a month with 2,700 machine hours would be:
(rounded to the nearest whole dollar)
Answer : $ 17,247.33 (or) $17,247.
Cost Equation :
Total cost = Intercept +( Machine hours co-efficient * Machine Hours )
Total Cost = 3,639.33+( 5.04*2700) =$ 17,247.33
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 3,100 $ 18,700 February 3,500 $ 21,600 March 2,500 $ 13,800 April 3,700 $ 23,600 May 4,400 $ 28,550 June 3,900 $ 22,600 July 4,700 $ 25,050 August 4,100 $ 23,050 September 2,600 $ 16,100 October 4,300 $ 26,600 November...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,600 3,000 2,000 3,200 3,900 3,400 4,200 3,600 2,100 3,800 4,800 4,300 Electricity Costs $19, 250 $22,700 $14,350 $24,700 $29,100 $23,700 $25,600 $23,600 $17,200 $27,700 $32,700 $28,600 Summary Output Regression Statistics Multiple...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 2.500 $ 18.400 February 2,900 21,000 March 1.900 13,500 April 3,100 23,000 May 3.800 28,250 3,300 22,000 4,500 24,750 August 3.500 22,750 September 2,000 15,500 October 3,700 26,000 November 4,700 31.000 December 4.200 27,750 Summary Output Regression Stonistics Multiple 0.965 0.932...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,500 2,900 1,900 3,100 3,800 3,300 4,100 3,500 2,000 3,700 4,700 4,200 Electricity Costs $19, 200 $22,600 $14,300 $24,600 $29,050 $23,600 $25,550 $23,550 $17, 100 $27,600 $32,600 $28,550 Summary Output Regression Statistics...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 2,600 $ 19,250 February 3,000 $ 22,700 March 2,000 $ 14,350 April 3,200 $ 24,700 May 3,900 $ 29,100 June 3,400 $ 23,700 July 4,200 $ 25,600 August 3,600 $ 23,600 September 2,100 $ 17,200 October 3,800 $ 27,700 November...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 3,500 $ 18,900 February 3,900 $ 22,000 March 2,900 $ 14,000 April 4,100 $ 24,000 May 4,800 $ 28,750 June 4,300 $ 23,000 July 5,500 $ 25,250 August 4,500 $ 23,250 September 3,000 $ 16,500 October 4,700 $ 27,000 November...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,300 2,700 1,700 2,900 3,600 3,100 3,900 3,300 1,800 3,500 4,500 4,000 Electricity Costs $19, 100 $22,400 $14,200 $24,400 $28,950 $23,400 $25,450 $23,450 $ 16,900 $27,400 $32,400 $28,450 Summary Output Regression Statistics...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,500 2,900 1,900 3,100 3,800 3,300 4,100 3,500 2,000 3,700 4,700 4,200 Electricity Costs $ 18,400 $ 21,000 $ 13,500 $ 23,000 $ 28,250 $ 22,000 $ 24,750 $ 22,750 $ 15,500...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,500 2,900 1,900 3,100 3,800 3,300 4,100 3,500 2,000 3,700 4,700 4,200 Electricity Costs $ 18,400 $ 21,000 $ 13,500 $ 23,000 $ 28,250 $ 22,000 $ 24,750 $ 22,750 $ 15,500...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 2,900 $ 18,600 February 3,300 $ 21,400 March 2,300 $ 13,700 April 3,500 $ 23,400 May 4,200 $ 28,450 June 3,700 $ 22,400 July 4,500 $ 24,950 August 3,900 $ 22,950 September 2,400 $ 15,900 October 4,100 $ 26,400 November...