Predetermined overhead rate [Refer working note 1] | $9.86 | per machine hour |
Cost per stairway [Refer working note 2] | $1,499.44 | |
Activity-based overhead rate for each activity [Refer working note 5] | ||
Purchasing | $125.00 | Per order |
Handling materials | $10.25 | Per move |
Production | $2.20 | per d/L hour |
Setting up machines | $84.00 | Per setup |
Inspecting | $18.00 | Per inspection |
Inventory control | $0.75 | Per component |
Utilities | $3.00 | Per sq. ft. |
Total overhead assigned [Refer working note 6] | $80,300 | |
Total Cost per stairway [Refer working note 7] | $1,499.44 |
.
.
Working note 1 - Computation of predetermined overhead rate | |
Total budgeted overhead costs (a) | $986,000 |
Total budgeted machine hours (b) | $100,000 |
Predetermined overhead rate (a / b) | $9.86 |
.
.
Working note 2 - Computation of cost per unit | |
Total manufacturing cost [Refer working note 3] (a) | $374,860 |
Number of units of stairways (b) | 250 |
Cost per Unit (a / b) | $1,499.44 |
.
.
Working note 3 - Computation of total manufacturing costs | |
Direct material cost (a) | $104,100 |
Direct labor cost (b) | $113,000 |
Factory overhead [Refer working note 4] (c) | $157,760 |
Total manufacturing cost (a + b + c) | $374,860 |
.
.
Working note 4 - Allocation of overhead to the product using predetermined overhead rate | |
Actual number of machine hours (a) | $16,000 |
Predetermined overhead rate [Refer working note 1] (b) | $9.86 |
Total overhead cost allocated (a / b) | $157,760 |
.
.
Working note 5 - Calculation of Activity rate | |||||
Activity Cost Pool |
Estimated overhead costs (a) |
Total expected activity (b) |
Activity rate (a / b) |
||
Purchasing | $75,000 | 600 | orders | $125.00 | Per order |
Handling materials | $82,000 | 8,000 | moves | $10.25 | Per move |
Production | $220,000 | 100,000 | direct labor hours | $2.20 | per direct labor hour |
Setting up machines | $105,000 | 1,250 | setups | $84.00 | Per setup |
Inspecting | $108,000 | 6,000 | inspections | $18.00 | Per inspection |
Inventory control | $126,000 | 168,000 | components | $0.75 | Per component |
Utilities | $270,000 | 90,000 | square feet occupied | $3.00 | Per square feet occupied |
.
.
Working note 6- Allocation of overhead to the product using activity allocation rates | |||||
Activity Cost Pool |
Activity rate [Refer working note 5] |
Activity usage | Allocation amount | ||
(a) | (b) | (a x b) | |||
Purchasing | $125.00 | Per order | 60 | orders | $7,500.00 |
Handling materials | $10.25 | Per move | 800 | moves | $8,200.00 |
Production | $2.20 | per direct labor hour | 5,500 | direct labor hours | $12,100.00 |
Setting up machines | $84.00 | Per setup | 100 | setups | $8,400.00 |
Inspecting | $18.00 | Per inspection | 450 | inspections | $8,100.00 |
Inventory control | $0.75 | Per component | 16,000 | components | $12,000.00 |
Utilities | $3.00 | Per square feet occupied | 8,000 | square feet occupied | $24,000.00 |
Total overhead cost allocated | $80,300.00 |
.
.
Working note 7 - Computation of total cost per unit | |
Total manufacturing cost [Refer working note 8] (a) | $297,400 |
Number of units of stairways (b) | 250 |
Cost per Unit (a / b) | $1,189.60 |
.
.
Working note 8 - Computation of total manufacturing costs | |
Direct material cost (a) | $104,100 |
Direct labor cost (b) | $113,000 |
Factory overhead [Refer working note 6] (c) | $80,300 |
Total manufacturing cost (a + b + c) | $297,400 |
Shaker Stairs Co.designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles,...
Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted overhead costs Amount $75,000 82,000 220,000 100,000 120,000 126,000...
Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows.Overhead Cost PoolsAmountPurchasing$75,000Handling materials82,000Production (cutting, milling, finishing)210,000Setting up machines100,000Inspecting96,000Inventory control (raw materials and finished goods)126,000Utilities450,000Total budgeted overhead costs$1,139,000For the last 4 years, Shaker Stairs Co. has been charging overhead to products on the basis...
Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Amount Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities $75,000 82,000 210,000 100,000 96,000 126,000 270,000 Total budgeted overhead...
Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Amount Purchasing $75,000 Handling materials 82,000 Production (cutting, milling, finishing) 220,000 Setting up machines 105,000 Inspecting 114,000 Inventory control (raw materials and finished goods) 126,000 Utilities 360,000 Total budgeted overhead...
P17-3A--- Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2017 are as follows. Overhead Cost Pools Amount Purchasing $ 75,000 Handling materials 82,000 Production (cutting, milling, finishing) 210,000 Setting up machines 105,000 Inspecting 90,000 Inventory control (raw materials and finished goods) 126,000 Utilities 180,000 Total...
Problem 4-3A a-b, c1-c3 (Video) (Part Level Submission) Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Amount Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted...
ACCT212 SEM 191-ASSIGNM QUESTION Thakin Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2014 are as follows. Amount Overhead Cost Pools $ 69,000 Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities 82,000 210,000 95,000 90,000...
Question 2 Stellar Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are made of white oak wood. The company's budgeted manufacturing overhead costs for 2020 are as follows: Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budget overhead costs Amount $68,000 81,000 204,000...
Please show your calculations! Stellar Stairs Co. designs and builds factory-made premium wooden stairs for homes. The manufactured stair components (spindles, risers, hangers, hand rails) permit installation of stairs of varying lengths and widths. All are made of white oak wood. The company's budgeted manufacturing overhead costs for 2016 are as follows: Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budget overhead costs Amount $69,000...
Problem 17-03A a-b, c-c (Part Level Submission) Shaker Stars Co, designs and builds factory made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, handrais permit installation of starways of varying lengths and widths. All are of white oak wood Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Purchaung Handing materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utaties Total budgeted overhead costs...