a) Assign overhead cost

Processing Setting up Other Total
Factory utilities 10950 7300 18250 36500
Indirect labor 5500 3300 2200 11000
Total 16450 10600 20450 47500

b) Overhead rate

Overhead rate
Processing 16450/11200 = 1.47 per MH
Setting up 10600/2400 = 4.42 per Batch

c) Amount of overhead

Product S8 Product F1
Processing 5292 11172
Setting up 6630 3978
Total 11922 15150

d) Product margin

Product S8 Product F1
Sales 70900 100100
Direct material 25400 37500
Direct labor 32400 44000
Overhead 11922 15150
Product margin 1178 3450
Add a comment
Know the answer?
Add Answer to:
Groleau Corporation has an activity-based costing system with three activity cost pools--Processing, Setting Up, and Other....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Groleau Corporation has an activity-based costing system with three activity cost pools--Processing, Setting Up, and Other....

    Groleau Corporation has an activity-based costing system with three activity cost pools--Processing, Setting Up, and Other. The company's overhead costs, which consist of factory utilities and indirect labor, are allocated to the cost pools in proportion to the activity cost pools' consumption of resources. Costs in the Processing cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other...

  • Groleau Corporation has an activity-based costing system with three activity cost pools--Processing, Setting Up, and Other....

    Groleau Corporation has an activity-based costing system with three activity cost pools--Processing, Setting Up, and Other. The company's overhead costs, which consist of factory utilities and indirect labor, are allocated to the cost pools in proportion to the activity cost pools' consumption of resources. Costs in the Processing cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other...

  • Groleau Corporation has an activity-based costing system with three activity cost pools: Processing, Setting Up, and...

    Groleau Corporation has an activity-based costing system with three activity cost pools: Processing, Setting Up, and Other. The company's overhead costs, which consist of factory utilities and indirect labor, are allocated to the cost pools in proportion to the activity cost pools' consumption of resources. Costs in the Processing cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the...

  • Groleau Corporation has an activity-based costing system with three activity cost pools--Processing, Setting Up, and Other....

    Groleau Corporation has an activity-based costing system with three activity cost pools--Processing, Setting Up, and Other. The company's overhead costs, which consist of factory utilities and indirect labor, are allocated to the cost pools in proportion to the activity cost pools' consumption of resources. Costs in the Processing cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other...

  • Groleau Corporation has an activity-based costing system with three activity cost pools--Processing. Setting Up, and Other....

    Groleau Corporation has an activity-based costing system with three activity cost pools--Processing. Setting Up, and Other. The company's overhead costs, which consist of factory utilities and indirect labor, are allocated to the cost pools in proportion to the activity cost pools' consumption of resources. Costs in the Processing cost pool are assigned to products based on machine-hours (MHS) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other...

  • Groleau Corporation has an activity-based costing system with three activity cost pools--Processing, Setting Up, and Other....

    Groleau Corporation has an activity-based costing system with three activity cost pools--Processing, Setting Up, and Other. The company's overhead costs, which consist of factory utilities and indirect labor, are allocated to the cost pools in proportion to the activity cost pools' consumption of resources. Costs in the Processing cost pool are assigned to products based on machine-hour (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other...

  • TB Problem Qu. 7-189 Groleau Corporation has an activity-based costing ... 8 10 points Groleau Corporation...

    TB Problem Qu. 7-189 Groleau Corporation has an activity-based costing ... 8 10 points Groleau Corporation has an activity-based costing system with three activity cost pools--Processing, Setting Up, and other. The company's overhead costs, which consist of factory utilities and indirect labor, are allocated to the cost pools in proportion to the activity cost pools' consumption of resources. Costs in the Processing cost pool are assigned to products based on machine-hours (MHS) and costs in the Setting Up cost pool...

  • Howell Corporation's activity-based costing system has three activity cost pools--Machining, Setting Up, and Other. The company's...

    Howell Corporation's activity-based costing system has three activity cost pools--Machining, Setting Up, and Other. The company's overhead costs, which consist of equipment depreciation and indirect labor, are allocated to the cost pools in proportion to the activity cost pools' consumption of resources. Equipment depreciation (total) $ 35,600 Indirect labor (total) $ 7,350 Distribution of Resource Consumption Across Activity Cost Pools Machining Setting Up Other Equipment depreciation 0.20 0.50 0.30 Indirect labor 0.30 0.30 0.40 Costs in the Machining cost pool...

  • Howell Corporation's activity based costing system has three activity cost pools-Machining, Setting Up, and other. The...

    Howell Corporation's activity based costing system has three activity cost pools-Machining, Setting Up, and other. The company's overhead costs, which consist of equipment depreciation and indirect labor, are allocated to the cost pools in proportion to the activity cost pools' consumption of resources. Equipment depreciation (total) Indirect labor (total) $27.300 $ 7.510 Distribution of Resource Consumption Across Activity Cost Pools Equipment depreciation reciation Indirect labor Machining 0.50 0.40 Setting Up Other 0.20 0.30 0.30 Costs in the Machining cost pool...

  • Howell Corporation's activity-based costing system has three activity cost pools--Machining, Setting Up, and Other. The company's...

    Howell Corporation's activity-based costing system has three activity cost pools--Machining, Setting Up, and Other. The company's overhead costs, which consist of equipment depreciation and indirect labor, are allocated to the cost pools in proportion to the activity cost pools' consumption of resources Equipment depreciation (total) Indirect labor (total) $32,300 $7.250 Distribution of Resource Consumption Across Activity Cost Pools Machining Setting up Equipment depreciation ceciation 0.50 0.30 0.30 Indirect labor other 0.30 0.20 Costs in the Machining cost pool are assigned...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT