Standard price of materials per yard = Standard direct materials per set of covers / Standard quantity of materials per set of covers = 14.20 / 2.0 | 7.10 | |
Actual materials rate per yard = Actual total materials cost / Actual materials quantity = 35100 / 6000 | 5.85 | |
Materials price variance = ( Actual price - Standard price ) * Actual quantity = ( 5.85 - 7.10 ) * 6000 | 7500 | F |
Standard quantity of materials for 2600 sets of covers = 2600 * Standard quantity of materials per set of covers = 2600 * 2.0 | 5200 | |
Materials quantity variance = ( Actual quantity - Standard quantity ) * Standard price = ( 6000 - 5200 ) * 7.10 | 5680 | U |
Standard labor hours per sets of cover = Standard hours for 2010 sets of covers / 2010 = 1005 / 2010 | 0.5 | |
Standard rate of labor = Standard direct labor per set of cover / Standard labor hours per sets of covers = 4.00 / 0.5 | 8.00 | |
Actual rate of labor = Actual total direct labor cost / Actual direct labor hours worked = 10920 / 1200 | 9.10 | |
Labor rate variance = ( Actual rate - Standard rate ) * Actual hours = ( 9.10 - 8.00 ) * 1200 | 1320 | U |
Standard direct labor hours for 2600 sets of covers = 2600 * Standard labor hours per sets of covers = 2600 * 0.5 | 1300 | |
labor efficiency varaince = ( Actual hours - Standard hours ) * Standard rate = ( 1200 - 1300 ) * 8.00 | 800 | F |
Standard rate of variable overhead = Standard cost of variable overhead per sets of cover / Standard labor hours per sets of cover = 1.80 / 0.5 | 3.60 | |
Actual rate of variable overhead = Actual total variable overhead cost / Actual direct labor hours worked = 5460 / 1200 | 4.55 | |
Variable overhead rate variance = ( Actual rate - Standard rate ) * Actual hours = ( 4.55 - 3.60 ) * 1200 | 1140 | U |
Variable overhead efficiency variance = ( Actual hours - Standard hours ) * Standard rate = ( 1200 - 1300 ) * 3.60 | 360 | F |
Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat...
Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,005 hours each month to produce 2,010 sets of covers. The standard costs associated with this level of production are: Total $ 28,542...
Marvel Parts, Inc., manufactures auto accessories. One of the company’s products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,005 hours each month to produce 2,010 sets of covers. The standard costs associated with this level of production are: Total Per Set...
Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,005 hours each month to produce 2.010 sets of covers. The standard costs associated with this level of production are: Total $ 28,542 $...
Marvel Parts, Inc., manufactures auto accessories. One of the company’s products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,005 hours each month to produce 2,010 sets of covers. The standard costs associated with this level of production are: Total Per Set...
Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,040 hours each month to produce 2,080 sets of covers. The standard costs associated with this level of production are: Total $ 40,560...
Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,010 hours each month to produce 2,020 sets of covers. The standard costs associated with this level of production are: Total $ 36,360...
Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,010 hours each month to produce 2,020 sets of covers. The standard costs associated with this level of production are: Total $ 36,360...
Please help me figure out variances for August!
Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,005 hours each month to produce 2,010 sets of covers. The standard costs associated with...
Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company uses a standard cost system for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,055 hours each month to produce 2,110 sets of covers. The standard costs associated with this level of production are: Direct materials Direct labor Variable...
Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 2.850 hours each month to produce 1,900 sets of covers. The standard costs associated with this level of production are: Per Set of...