Question

e 210: Chapters: 8-11 Seved The following are the cash flows of two independent projects: Year Project A $(330) 160 160 160 1
0 0
Add a comment Improve this question Transcribed image text
Answer #1

e 210: Chapters: 8-11 Seved The following are the cash flows of two independent projects: Year Project A $(330) 160 160 160 1

NPV = Present Value of Cash Inflow - Present Value of Cash Outflow

NPV of Project A = Cash Flown Cash Flowi Cash Flow2 (1+r)2 -330 (1 + r)

= 160 160 160 160 (1+0.12)*(1+0.12) 2 *(1+0.12) (1+0.12)

= 485.98 - 330 = 155.98

NPV of Project B = Cash Flown Cash Flowi Cash Flow2 (1+r)2 -330 (1 + r)

= 230 3030 (1+0.12)*(1+0.12)2(1+0.12)

= 552.42 - 330 = 222.42

Prroject B should be selected. If the projects are not mutually exclusive both of the projects can be accepted.

Accept Both.

NOTE: The answer to your question has been given below/above. If there is any query regarding the answer, please ask in the comment section. If you find the answer helpful, do upvote. Help us help you.

  

Add a comment
Know the answer?
Add Answer to:
e 210: Chapters: 8-11 Seved The following are the cash flows of two independent projects: Year...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following are the cash flows of two independent projects: Year Project A Project B 0...

    The following are the cash flows of two independent projects: Year Project A Project B 0 (210) (210) 1 90 110 2 90 110 3 90 110 4 90    If the opportunity cost of capital is 12%, calculate the NPV for both projects. (Do not round intermediate calculations. Round your answers to 2 decimal places.) b. Which of these projects is worth pursuing? Project A Project B Both Neither

  • The following are the cash flows of two projects: Year Project A Project B 0 −$260...

    The following are the cash flows of two projects: Year Project A Project B 0 −$260        −$260        1 140        160        2 140        160        3 140        160        4 140        a. If the opportunity cost of capital is 11%, calculate NPV for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project NPV          A $    B    b. Which of these projects is worth pursuing if you...

  • 3- ApplyWk3 uz (Que Mon The following are the cash flows of two independent projects 11...

    3- ApplyWk3 uz (Que Mon The following are the cash flows of two independent projects 11 Year Protect a (280) Project B (20) 180 a. If the opportunity cost of capital is 10%, calculate the NPV for both projects. (Do not round Intermediate cale answers to 2 decimal places.) NPV Project Pepeda Project B

  • The following are the cash flows of two projects: Year Project $(370) 200 Proiect B $...

    The following are the cash flows of two projects: Year Project $(370) 200 Proiect B $ (370) 270 209 270 280 270 200 a:Calculate the NPV for both projects if the opportunity cost of capital is 15% (Do not round intermediate calculations. Round your answers to 2 decimal places.) NPV Project A B b. Suppose that you can choose only one of these projects. Which would you choose? Project A Neither Project B

  • The following are the cash flows of two projects: Year Nam Project A $ (370) 200...

    The following are the cash flows of two projects: Year Nam Project A $ (370) 200 200 200 200 Project B $ (370) 270 270 270 a. Calculate the NPV for both projects if the discount rate is 10%. (Do not round intermediate calculations. Round your answers to 2 decimal places.) NPV Project Project A Project B b. Suppose that you can choose only one of these projects. Which would you choose? Project B Project A Neither

  • #1 Questions a) to e) refer to two projects with the following cash flows: Year Project...

    #1 Questions a) to e) refer to two projects with the following cash flows: Year Project B Project A -$200 -$200 80 100 100 100 a) If the opportunity cost of capital is 10%, which of these projects is worth pursuing? Explain. b) Suppose that you can choose only one of these projects. Which would you choose? The discount rate is still 10%. Justify your reasoning. c) Which project would you choose if the opportunity cost of capital were 16%?...

  • Here are the cash-flow forecasts for two mutually exclusive projects: Cash Flows (dollars) Year Project A...

    Here are the cash-flow forecasts for two mutually exclusive projects: Cash Flows (dollars) Year Project A Project B 0 − 107 − 107 1 37 56 2 57 56 3 77 56 a-1. What is the NPV of each project if the opportunity cost of capital is 3%? (Do not round intermediate calculations. Round your answers to 2 decimal places.) a-2. Which project would you choose? Project A Project B b-1. What is the NPV of each project if the...

  • by hand #1 Questions a) to c) refer to two projects with the following cash flows:...

    by hand #1 Questions a) to c) refer to two projects with the following cash flows: Year Project B Project A - $200 80 -$200 100 80 100 80 100 Projects A and B are mutually exclusive. a) Calculate the Payback, Discounted Payback, NPV, IRR, and Profitability Index for Projects A and B using an opportunity cost of capital of 10% (where applicable). Which of these projects is worth pursuing? Explain. b) Calculate the Payback, Discounted Payback, NPV, IRR, and...

  • NEED ASAP IN 10 MIN PLEASE!!! THANK YOU!!! The following are the cash flows of two...

    NEED ASAP IN 10 MIN PLEASE!!! THANK YOU!!! The following are the cash flows of two projects: 18 Year Project A O -$260 140 2. 140 3 140 4 140 Project B -$260 160 160 1 00:37:17 160 a. Calcula, che NPV for both projects if the discount rate is 11%. (Do not round intermediate calculations. Round your answers to 2 decimal places Project А B NPV $ b. Suppose that you can choose only one of these projects. Which...

  • The following are the cash flows of two projects: Year Project A $ (200) 80 80...

    The following are the cash flows of two projects: Year Project A $ (200) 80 80 80 Project B $ (200) 100 100 100 AWN If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Answer is complete but not entirely correct. Project Profitability Index 1.2410 % 1.2218 B

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT