Question

Compute the discounted payback statistic for Project if the appropriate cost of capital is 8 percent and the maximum allowabl

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Using excel to calculate

0.00 1 2 3 4 5
Project A -1600 720 660 700 420 520
Discounted Cash Flow -1600.00 666.67 565.84 555.68 308.71 353.90
Cumulative Cash flow -1600.00 -$933.33 -$367.49 $188.19 $496.91 $850.81
Discounted Payback Period 2.66
excel formula 2+367.49/555.68

The Project should be accepted.

Add a comment
Know the answer?
Add Answer to:
Compute the discounted payback statistic for Project if the appropriate cost of capital is 8 percent...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12...

    Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: Cash flow: 0 -$11,600 1 $3,410 $4,300 34 $1,640 $0 $1,120 Discounted payback period 0 years Should the project be accepted or rejected? accepted rejected...

  • Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...

    Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project C Time Cash flow -$1,300 $600 $570 $610 $360 $160 2 4 5 years Should the project be accepted or rejected? O Rejected O Accepted

  • Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6...

    Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project C Time Cash flow -$2,700 $1,160 $990 $1,030 $640 $440 0 2 4 Discounted payback period years Should the project be accepted or rejected? Rejected Accepted

  • Compute the discounted payback statistic for Project D if the appropriate cost of capital is 13...

    Compute the discounted payback statistic for Project D if the appropriate cost of capital is 13 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: 2 4 Cash flow:-$11,500 $3,400 $4,280 $1,620 $0 $1,100 Discounted payback period years Should the project be accepted or rejected? O accepted O rejected

  • Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent...

    Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: Cash flow: -$2,800 $1,070 $1,020 $889 $660 $460 Payback years Should the project be accepted or rejected? accepted rejected

  • Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12...

    Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).) Project D Time: 0 1 2 3 4 5 Cash flow: –$11,000 $3,350 $4,180 $1,520 $300 $1,000 Should the project be accepted or rejected? accepted rejected

  • Compute the discounted payback statistic for Project D if the appropriate cost of capital is 10...

    Compute the discounted payback statistic for Project D if the appropriate cost of capital is 10 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: Cash flow: 1 1 -$12,900 $3,540 2 $4,560 3 $1,900 4 $0 5 $1,380 Discounted payback period years

  • Compute the discounted payback statistic for Project D if the appropriate cost of capital is 11...

    Compute the discounted payback statistic for Project D if the appropriate cost of capital is 11 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).) Project D Time: 0 1 2 3 4 5 Cash flow: –$12,700 $3,520 $4,520 $1,860 $0 $1,340 Discounted Payback Statistic:

  • Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent...

    Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: Cash flow: 0 -$2,300 1 $870 2 $870 3 $780 4 $560 5 $360 Payback years Should the project be accepted or rejected? accepted O rejected

  • Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent...

    Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: Cash flow: 0 -$2,300 1 $870 2 $870 3 $780 4 $560 5 $360 Payback years Should the project be accepted or rejected? accepted O rejected

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT