Compute the payback statistic for Project B and decide whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 12 percent and the maximum allowable payback is three years.
Project B
Time |
0 |
1 |
2 |
3 |
4 |
5 |
Cash Flow |
-$11,000 |
$3,350 |
$4,180 |
$1,520 |
$0 |
$1,000 |
SEE THE IMAGE. ANY DOUBTS, FEEL FREE TO ASK. THUMBS UP PLEASE
Compute the payback statistic for Project B and decide whether the firm should accept or reject...
Payback Compute the payback statistic for Project A and recommend whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 8 percent and the maximum allowable payback is four years. Project A Time 0 1 2 3 4 5 Cash Flow -$1,000 $350 $480 $520 $300 $100
Compute the Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 9 percent and the maximum allowable payback is 3 years.Time:012345Cash flow:-2,800875600850800550
Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: Cash flow: -$11,000 $3,350 $4,130 $1,520 $0 $1,000 Payback years Should the project be accepted or rejected? accepted rejected
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).) Project D Time: 0 1 2 3 4 5 Cash flow: –$11,000 $3,350 $4,180 $1,520 $300 $1,000 Should the project be accepted or rejected? accepted rejected
Compute the Pl statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 11 percent. Time: Cash flow: 0 12 13 14 15 -78 -7810 103178 153 Multiple Choice 0 8.90, reject 0 1.11, accept 0 29.95, accept 0 11.00, reject
Compute the Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent and the maximum allowable payback is 3 years. Time:012345Cash flow:-2,800675550850750700Multiple Choice 2.97 years, Accept 3.97 years, Accept 2.97 years, Reject 3.97 years, Reject
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 11 percent. Time:012345Cash flow:-78-7801138863Multiple Choice51.00, accept29.71, accept11.00, reject138, accept
IRR Compute the IRR statistic for Project E and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 8 percent. Project E Time 0 1 2 3 4 5 Cash Flow -$1,000 $350 $480 $520 $300 $100
IRR Compute the IRR statistic for Project E and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 8 percent. Project E Time 0 1 2 3 4 5 Cash Flow -$1,000 $350 $480 $520 $300 $100
Compute the Pl statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 9 percent Time: 4 5 Cash flow -76 -76 101 76 51 Multiple Choice 125, ассерt 42.86, accept 9.00, reject Multiple Choice 1.25, ассеpt 42.86, ассеpt 9.00, reject 19.25, accept