4. What is the NPV (assuming a discount rate of 8%) and the IRR of the...
3(a)-3(c) based on the following table. 3(a) What is NPV for project A? Discount rate 11% YearProject A Project B 1000 500 500 500 500 500 200 350 360 200 200 200 -800 420 420 420 420 420 300 300 300 450 260 260 4 6 10 QUESTION 7 what is the IRR for project B? QUESTION 8 which project will you choose A or 87 Please only answer with A or B in the answer area
Intemal rate of return (IRR) is computed by finding the discount rate that a. NPV of a project to be zero b. NPV of a project to be greater than zero c. NPV of a project to be less than zero d. IRR of a project to be zero Select one: a NPV of a project to be greater than zero
NPV and Uher nvestment CrNErTa For Problems 1-4, use a 5% discount rate and the following cash flows for projects A and B.: A: (-$2000, $500, $600, $700, $800) B: -$2000, $950, $850, $400, $300) 3. If A and B are mutually exclusive and the required rate of return is 5%, which should be ассеpted? 4. If the discount rate is 12%, and A and B are mutually exclusive, which project should be ассеpted? You can borrow $8,000, to be...
CH. 9 WORKSHEET NPV and Other Investment Criteria For Problems 1-4, use a 5% discount rate and the following cash flows for projects A and B.: A: (-$2000, $500, $600, $700, $800) B: (-$2000, $950, $850, $400, $300) 1. Calculate the payback period for projects A and B. 2. Calculate the internal rate of return for projects A and B. 3. If A and B are mutually exclusive and the required rate of return is 5%, which should be accepted?...
Internal Rate of Return (IRR) can be understood as the discount rate that should be applied to a project such that Net Present Value (NPV) = $0. If the discount rate applied in a certain 5 year project is 10%, the resultant NPV is $50K, and the cost is $100K, what is the IRR? (Assume that all costs for the project are incurred at the start of the project, and the payout for this project occurs in one payment at...
Internal Rate of Return (IRR) can be understood as the discount rate that should be applied to a project such that Net Present Value (NPV) = $0. If the discount rate applied in a certain 5 year project is 10%, the resultant NPV is $50K, and the cost is $100K, what is the IRR? (Assume that all costs for the project are incurred at the start of the project, and the payout for this project occurs in one payment at...
First Blank: always, sometimes, never
Second Blank: IRR, MIRR, required rate of return
Third Blank: IRR, MIRR, required rate of return
Fourth Blank: IRR method, NPV method
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree....
A project has a profitability index (PI) of 1.1. If the initial investment of $10,000. What do you know about the NPV and IRR? a) NPV may be smaller than zero b)NPV must be $1000 c) The IRR is the prevailing discount D) none of the above
Calculate the IRR and NPV of this project utilizing a 12% discount rate and a 15% cap rate. Ms. Brownwas able to secure a loan for $1,540,000, and an equity investor agreed to invest the remaining$660,000 in exchange for 20% ownership in the project
Internal Rate of Return (IRR) can be understood as the discount rate that should be applied to a project such that Net Present Value (NPV) = $0. If the discount rate applied in a certain 5 year project is 10% and the resultant NPV is $50K, what is the IRR?