i have to compute the nominal strength of the
composite section below and i have slab and deck so by using the
equation of
Cc = 0.85 fc' beff ts for the compressive force in the
concret.
which value should i take for ts thickness slab ? is it ts= 3.25 or
ts= 3.25+3?
Cc = 0.85 Fc' b t
here b is the width of the concrete slab
t is the thickness of the slab
Fc' is the compressive strength of concrete.
take t = 3.25 that is the thickness of the slab
here the total thickness is 6.25 just subtract the deck thickness from it.
i have to compute the nominal strength of the composite section below and i have slab...
2. The composite beam cross section shown below consists of a W16 x 45 steel with ASTM A572 grade 50 and 4in. normal weight (145 pef) concrete slab, with 28-day strength of 3ksi. Assume full-composite action. Consider only the loads shown in the figure. b = 66 Service Leads Construction Dead Load: 0.75 k. Superimposed Dead Load: 0.25 kft. Live Load-1.1 kft. -W16 X 45 L-36-0 a) Determine the design bending strength in k-ft of the composite section using formula....
5:06 0 < HW #7 HW #7-Due 4/10/2019.doc t] .Calculate strain in tension steel and nominal moment strength for the precast section shown below. Given:f C." 4,000 psi,f,-60,000 psi (a) A-3.00 i 2 (b) A,-5.641 2 30 in 26 A, in 2. A reinforced slab (3.5 inch thickness) built integrally with beam consists of four spans (8'6" ft. on-center). The clear span of the slab is 7" 6" for all spans including the end span. The service live load on...
I. The overhanging beam in the figure below, has a timber section of nominal size 100 x 300. Determine the maximum shear stress, the maximum tensile stress, and the maximum compressive stress in the beam due to the loading shown. (25 points) 20 kN/m INSTRUCTIONS For PROBLEM do the following steps: 1.Show ALL your work 2. Draw appropriately labeled FBDs 3. Use appropriate segments to develop expressions for the shear force and bending moment. diagrams in a standard format the...
How do I solve this? Problem 2(50 points) The roof of the Edwin A. Stevens building is to be redesigned to accommodate a billboard for Stevens Institute of Technology. The new billboard will weigh 40 kips and be supported equally by two columns located 9 ft from the rear of the building. The beams supporting the new roof will be simply supported as shown. (Note there is a 5 ft overhang at the front of the building). For the grade...
I provided an example problem, the question asked is the last photo included. I also provided the tables used. Span leng DL-1550 LL-1400b/ Desigh this r da fHetion and bendmg 5000 fsi :5Ksi Grade G0 steel fyr Goks d shrvup 6.5" No. 4 stimpr 名 De Flechon ChantGo ection min h llo llo 30-1.5b 3b b. guess h-5(18")-27'. h-2.0(К")-36 b-an," b: 15" Try 1-3a 1.2. (215 /1. (1400)4,gaol/ 964, 000l- 0ooa 00 Fc-5 ksi y G0,000pst E-0.85-[065 (5 ksi-4)-DXO 15...