Debit | Credit | |
Work in process inventory | 10,700 | |
Manufacturing overhead | 900 | |
Raw material inventory | 11,600 | |
Work in process inventory | 12,800 | |
Manufacturing overhead | 1,300 | |
Factory labor | 14,100 | |
Work in process inventory | 7,680 | |
Manufacturing overhead | 7,680 | |
(12,800*60% | ||
Finished goods inventory | 7900 | |
Work in process inventory | 7900 | |
(2100+2600+2000+60%*2000) |
Exercise 15-2 (Part Level Submission) Stine Company uses a job order cost system. On May 1,...
Exercise 2-2 Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,920 and two jobs in process: Job No. 429 $2,600, and Job No. 430 $1,320. During May, a summary of source documents reveals the following. Materials Labor Time Job Number Requisition Slips Tickets 429 $3,040 $2,300 430 4,020 3,400 431/ 4,740 $11,800 7,900 $13,600 General use 900 1,310 $12,700 $14,910 Stine Company applies manufacturing overhead to...
E16-2 Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,500. During May, a summary of source documents reveals the following. Job Number 429 430 431 General use Materials Requisition Slips $2,500 3,500 4,400 $10,400 800 $11,200 Labor Time Tickets $1,900 3,000 7,600 $12,500 1,200 $13,700 Stine Company applies manufacturing overhead to jobs...
Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,500. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $2,500 $1,900 430 3,500 3,000 431 4,400 $10,400 7,600 $12,500 General use 800 1,200 $11,200 $13,700 Stine Company applies manufacturing overhead to jobs at...
Exercise 15-02 Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $4,080 and two jobs in process: Job No. 429 $2,590, and Job No. 430 $1,490. During May, a summary of source documents reveals the following. Job Number 429 430 431 Materials Requisition Slips $2,870 3,660 4,500 $11,030 990 $12,020 Labor Time Tickets $2,100 3,600 7,700 $13,400 1,630 $15,030 General use Stine Company applies manufacturing overhead to...
Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,610 and two jobs in process: Job No. 429 $2,140, and Job No. 430 $1,470. During May, a summary of source documents reveals the following Materials Requisition Slips Labor Time Tickets Job Number 429 430 431 General use $2,940 4,090 4,920 $2,060 3,600 8,060 $11,950 930 $12,880 $13,720 1,590 $15,310 Stine Company applies manufacturing overhead to jobs at...
E2-2 Stine Company uses a job order cost system. On May 1, the company has a balance Prepare in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and manugfa Job No. 430 $1,500. During May, a summary of source documents reveals the following. (LO 1, 2 Materials Labor Time Tickets Job Number 429 430 431 General use Requisition Slips $2,500 3,500 4,400 $1,900 3,000 7,600 $10,400 800 $11,200 $12,500 1,200 $13,700 Stine Company...
Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $4,240 and two jobs in process: Job No. 429 $2,580, and Job No. 430 $1,660. During May, a summary of source documents reveals the following Job Number 429 Materials Requisition Slips $3,040 3.680 4,710 $11.430 940 430 Labor Time Tickets $2,100 3,300 8,100 $13,500 1.360 $14,860 431 General use $12,370 Stine Company applies manufacturing overhead to jobs at...
E15.2 (LO 1, 2, 3, 4) Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,500. During May, a summary of source documents reveals the following. Materials Labor Job Number Requisition Slips Time Tickets 429 $2,500 3,500 4,400 $1,900 430 3,000 431 $10,400 $12,500 7,600 General use 800 1,200 $11,200 $13,700 Stine Company...
New help filling this out Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $4,210 and two jobs in process: Job No. 429 $2,550, and Job No. 430 $1,660. During May, a summary of source documents reveals the following. Stine Company applies manufacturing overhead to jobs at an overhead rate of 66% of direct labor cost. Job No. 429 is completed during the month. Materials Labor Time...
Exercise 15-2 Exercise 15-2 Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $4,080 and two jobs in process: Job No. 429 $2,330, and Job No. 430 $1,750. During May, a summary of source documents reveals the following Materials Requisition Slip:s Labor Time Tickets Job Number 429 430 431 General use $2,790 4,080 4,830 $2,130 3,460 8,160 $11,700 960 $12,660 $13,750 1,680 $15,430 Stine Company applies manufacturing...