activity | To | Tm | Tp | Te | (V)^0.5 | v |
A | 9 | 10 | 23 | 12 | 2.333333 | 5.444444 |
B | 8 | 10 | 18 | 11 | 1.666667 | 2.777778 |
C | 4 | 8 | 18 | 9 | 2.333333 | 5.444444 |
D | 5 | 7 | 15 | 8 | 1.666667 | 2.777778 |
E | 7 | 14 | 27 | 15 | 3.333333 | 11.11111 |
F | 4 | 13 | 28 | 14 | 4 | 16 |
G | 6 | 10 | 20 | 11 | 2.333333 | 5.444444 |
H | 8 | 12 | 22 | 13 | 2.333333 | 5.444444 |
I | 10 | 14 | 18 | 14 | 1.333333 | 1.777778 |
J | 5 | 10 | 21 | 11 | 2.666667 | 7.111111 |
Te = 4*Tm+Tp+To /6
Var = [Tp-To/6]2
Critical path is BEI with duration 40.
Variance of critical path is 12.8888
SD of critical path is 3.59
activity | ES | EF | Ls | LF | Slack |
A | 0 | 12 | 7 | 19 | 7 |
B | 0 | 11 | 0 | 11 | 0 |
C | 0 | 9 | 9 | 18 | 9 |
D | 12 | 20 | 19 | 27 | 7 |
E | 11 | 26 | 11 | 26 | 0 |
F | 11 | 25 | 12 | 26 | 1 |
G | 9 | 20 | 18 | 29 | 9 |
H | 26 | 39 | 27 | 40 | 1 |
I | 26 | 14 | 26 | 40 | 0 |
J | 25 | 36 | 29 | 40 | 4 |
Probability that the project will be completed in 45 weeks is given by
z = 45-40/3.59 =1.392
which corresponds to the probability of 0.917
Expected completion time for 95% probability with z =1.64
1.64 = T-40/3.59
T = 40+1,64x3,59 = 45.88 weeks = 46 weeks