Item | Land | Land Improvements | Building | Other Accounts | ||
a | -$288,700.00 | Notes Payable | ||||
b | $288,700.00 | |||||
c | $10,320.00 | |||||
d | $7,760.00 | |||||
e | $10,320.00 | Prepaid Insurance | ||||
f | $8,600.00 | -$1,720.00 | Prepaid Insurance | |||
g | $26,120.00 | |||||
h | $200,300.00 | $52,100.00 | ||||
I | $9,640.00 | |||||
j | $4,390.00 | |||||
k | $11,080.00 | |||||
l | -$5,120.00 | |||||
m | $14,020.00 | |||||
n | $17,430.00 | |||||
o | $13,410.00 | Gardening Expenses | ||||
p | $3,030.00 | |||||
Exercise 10-1 Your answer is partially correct. Try again The expenditures and receipts below are related...
Exercise 10-1 The expenditures and receipts below are related to land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. (a) Money borrowed to pay building contractor (signed a note) $(290,100 ) (b) Payment for construction from note proceeds 290,100 (c) Cost of land fill and clearing 10,580 (d) Delinquent real estate taxes on property assumed by purchaser 7,410 (e) Premium on 6-month insurance policy during construction 12,240 (f) Refund of 1-month...
Exercise 10-1 The expenditures and receipts below are related to land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. (a) Money borrowed to pay building contractor (signed a note) $(289,100 ) (b) Payment for construction from note proceeds 289,100 (c) Cost of land fill and clearing 11,860 (d) Delinquent real estate taxes on property assumed by purchaser 7,990 (e) Premium on 6-month insurance policy during construction 9,480 (f) Refund of 1-month...
The expenditures and receipts below are related to land, land
improvements, and buildings acquired for use in a business
enterprise. The receipts are enclosed in parentheses.
(a)
Money borrowed to pay building
contractor (signed a note)
$(276,900
)
(b)
Payment for construction from note
proceeds
276,900
(c)
Cost of land fill and clearing
10,340
(d)
Delinquent real estate taxes on
property assumed by purchaser
7,530
(e)
Premium on 6-month insurance policy
during construction
10,980
(f)
Refund of 1-month insurance premium...
The following expenditures and receipts are related to land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. (a) (b) (c) (d) (e) () () (h) Money borrowed to pay building contractor (signed a note) Payment for construction from note proceeds Cost of land fill and clearing Delinquent real estate taxes on property assumed by purchaser Premium on 6-month insurance policy during construction Refund of 1-month insurance premium because construction completed early...
The following expenditures and receipts are related to land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. (a) Money borrowed to pay building contractor (signed a note) $(292,600) (b) Payment for construction from note proceeds 292,600 Cost of land fill and clearing 11,790 Delinquent real estate taxes on property assumed by purchaser 7,630 Premium on 6-month insurance policy during construction 11,040 Refund of 1-month insurance premium because construction completed early (1,840)...
The following expenditures and receipts are related to land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. (a) Money borrowed to pay building contractor (signed a note) $(288,800) 2 T Payment for construction from note proceeds 288,800 10,420 (c) Cost of land fill and clearing Delinquent real estate taxes on property assumed by purchaser 8,950 a (e) Premium on 6-month insurance policy during construction 7,200 Refund of 1-month insurance premium because...
F10.1 (LO 1) (Acquisition Costs of Realty) The following expenditures and receipts are related to land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. a. Money borrowed to pay building contractor (signed a note) $(275,000) b. Payment for construction from note proceeds 275,000 c. Cost of land fill and clearing 8,000 d. Delinquent real estate taxes on property assumed by purchaser 7,000 e. Premium on 6-month insurance policy during construction 6,000...
s101(LO 1) (Acquisition Costs of Realty) The following expenditures and receipts are related o land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. . Money borrowed to pay building contractor (signed a note) h Payment for construction from note proceeds $(275,000) 275,000 c. Cost of land fill and clearing d. Delinquent real estate taxes on property assumed by purchaser e. Premium on 6-month insurance policy during construction fRefund of 1-month insurance...
The following expenditures and receipts are related to land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. (a) Money borrowed to pay building contractor (signed a note) $(286,200 ) (b) Payment for construction from note proceeds 286,200 (c) Cost of land fill and clearing 11,120 (d) Delinquent real estate taxes on property assumed by purchaser 9,070 (e) Premium on 6-month insurance policy during construction 10,020 (f) Refund of 1-month insurance premium...
Exercises 533 EXERCISES provence 0-1 (201) (Acquis buildings acquired (a) Money borrowed ( Payment for Cost of land fill and clearing Acquisition C0515 Realty! The following expenditures and receipts are related to land, land red for use in a business enterprise. The receipts are enclosed in parentheses. orrowed to pay building contractor (signed a note) S(275,000) ent for construction from note proceeds 275,000 8,000 ent real estate taxes on property assumed by purchaser 7,000 um on 6-month insurance policy during...