Question

You are subcontracting 3 vendors. Vendor 1 charges $45 per unit and can supply the required...

You are subcontracting 3 vendors. Vendor 1 charges $45 per unit and can supply the required quantity in four days. Vendor 2 charges $65 per unit and can supply the required quantity in two days. Vendor 3 charges $50 per unit and can supply the required quantity in three days. The organization's policy states that you cannot order more than 40% of your requirements to any one vendor. (Hint: Quantity ordered on any one vendor has to be less than equal to 40% of the total quantity subcontracted). The total budget you have for subcontracting is $300,000. Formulate a linear programming model that minimizes the total time taken to complete the deliveries.

1. What are the Decision Variables?

2. What is the Objective Function?

3. What are the constraints?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer a- The decision variables are given below=

x1= total quantities ordered to vendor 1

x2= total quantities ordered to vendor 2

x3= total quantities ordered to vendor 3

Answer b= The objective function is to minimize the total time in receiving the total number of required quantities

Min Z=4x1+2x2+3x3

Answer C= The constrains are as below=

x1\leqslant0.4(x1+x2+x3)

x2\leqslant0.4(x1+x2+x3)

x3\leqslant0.4(x1+x2+x3)

45x1+65x2+50x3 \leqslant 300000

x1,x2,x3\geqslant0

KINDLY RATE THE ANSWER AS THUMBS UP. THANKS, A LOT

Add a comment
Know the answer?
Add Answer to:
You are subcontracting 3 vendors. Vendor 1 charges $45 per unit and can supply the required...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below....

    Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below. Cost of regular production is $5 per unit, the cost of producing the same unit on overtime is $7.50, the cost of subcontracting is S9 per unit, an<d the cost of carrying a unit in inventory from one month to the next is $2 The labor contract at the plant prohibits overtime output to exceed 300 units in any five month window (that is...

  • The Surest Concrete Company produces cement in a continuous process.  Two ingredients in the cement are sand,...

    The Surest Concrete Company produces cement in a continuous process.  Two ingredients in the cement are sand, which Surest purchases for $8 per ton, and gravel, which costs $10 per ton.  The other ingredients are lumped together and referred to as “Other”. The cost of the other ingredients is $7 per ton. No more than 40 percent of the cement can be sand, and at least 30 percent of the cement must be gravel.  The maximum amount of gravel available is 100 tons.  The...

  • 3. Estimate Supply a. Suppose you are given this information from a movie theater making rational,...

    3. Estimate Supply a. Suppose you are given this information from a movie theater making rational, optimized decisions. Sketch a graph of supply (total cost and quantity) for “theater movies” using the available data. b. Estimate the quadratic cost function (i.e., ??? = ? + ???? 2 ) for “theater movies” that best approximates the data and add it to your graph c. What are the average and marginal cost equations based on your estimate? Is there a non-zero quantity...

  • 3. Estimate Supply a. Suppose you are given this information from a movie theater making rational,...

    3. Estimate Supply a. Suppose you are given this information from a movie theater making rational, optimized decisions. Sketch a graph of supply (total cost and quantity) for “theater movies” using the available data. b. Estimate the quadratic cost function for “theater movies” that best approximates the data and add it to your graph c. What are the average and marginal cost equations based on your estimate? Is there a non-zero quantity that minimizes these unit cost measures? Price of...

  • A firm charges $40 per unit for the first three units of a good purchased, and...

    A firm charges $40 per unit for the first three units of a good purchased, and $20 for each additional unit thereafter. The firm’s marginal cost and average total cost are both constant at $15. A consumer purchases six units. How much profit will the firm earn? Group of answer choices $70 $110 $90 $80 $50 2. Suppose there are two types of consumers for cell phones and accessories (cases, extra chargers, etc.) Consumers of type A are willing to...

  • 3. Referring to the graph above, what can you conclude about the elasticity of the supply...

    3. Referring to the graph above, what can you conclude about the elasticity of the supply curve S, in comparison to supply curve $,7 a Supply curve S, is more inelastic than supply curve S b. Supply curve S is more elastic than supply curve S c. Both curves have the same degree of clasticity d. Supply curve S, is infininely elastic, and supply cuve S, is infinitely iselastie e. There is not enough information to answer the question. 36....

  • Question 3: An Electrical Company has two manufacturing plants. The cost in dollars of producing an...

    Question 3: An Electrical Company has two manufacturing plants. The cost in dollars of producing an Amplifier at each of the two plants is given below. The cost of producing Q. Amplifiers at the first plant is: 65Q. + 40 +90 and the cost of producing Q2 Amplifiers at the second plant is 2002 +223 +120 The company needs to manufacture at least 60 Amplifiers to meet the received orders. Pro- duction time required for the Amplifiers at these plants...

  • You must SHOW ALL WORK ON NEXT PAGE to get credit and MUST ROUND to 2...

    You must SHOW ALL WORK ON NEXT PAGE to get credit and MUST ROUND to 2 decimal points (you can use back of page or below for calculations)! If you use a graphing calculator and simply write answers you will get ZERO CREDIT A company wants to maximize profits for two products: Green (earning $10 profit per unit) and Blue (earning $14 profit per unit). Machine Machine A B Green 3 3 Blue Total Available 2 120 1 90 To...

  • hi, can you please answer required 1, 2, and 3. can you show me the explanation....

    hi, can you please answer required 1, 2, and 3. can you show me the explanation. thanks and have a wonderful day. DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has...

  • 3. Integer Programming Problem (Chapter 6) A manufacturer can sell product 1 at a price of...

    3. Integer Programming Problem (Chapter 6) A manufacturer can sell product 1 at a price of $30 per unit and product 2 at a price of $40 per unit. Three units of raw material and 1.5 labor hours are needed to manufacturer one unit of product 1. Six units of raw material and 2 labor hours are need to manufacture one unit of product 2. The unit variable cost for product 1 is $20, and for product 2 is $20....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT