Solution
Total manufacturing overhead | / | Expected labor hours | = | Overhead per hour |
$ 828,000.00 | / | 41400 | = | $ 20.00 |
Calculation of manufacturing cost of job 309 | |
Direct material | $ 13,600.00 |
Direct labor | $ 4,560.00 |
Manufacturing overhead applied | $ 3,800.00 |
Total job cost | $ 21,960.00 |
d picnic tabies for public pools and dity parks. Leisure expected to inour $828,00 abor cost...
PG Industries manufactures custom-designed playground equipment for schools and city parks. PG expected to incur $533,000 of manufacturing overhead cost, 41,000 of direct labor hours, and $820,000 of direct labor cost during the year (the cost of direct labor is $20 per hour). The company allocates manufacturing overhead on the basis of direct labor hours. During December, PG completed Job 309. The job used 165 direct labor hours and required $15,400 of direct materials. The City of Adams has contracted...
Love It Industries manufactures custom-designed playground equipment for schools and city parks. Love It expected to incur $906,400 of manufacturing overhead cost, 41,200 of direct labor hours, and $1,153,600 of direct labor cost during the year (the cost of direct labor is $28 per hour). The company allocates manufacturing overhead on the basis of direct labor hours. During December, Love It completed Job 307. The job used 155 direct labor hours and required $14,800 of direct materials. The City of...
Have Fun Industries manufactures custom-designed playground equipment for schools and city parks. Have Fun expected to incur $627,000 of manufacturing overhead cost, 41,800 of direct labor hours, and $1,254,000 of direct labor cost during the year (the cost of direct labor is $30 per hour). The company allocates manufacturing overhead on the basis of direct labor hours. During November Have Fun completed Job 301. The job used 160 direct labor hours and required $15,100 of direct materials. The City of...
All Wood Industries manufactures custom-designed playground equipment for schools and city parks. All Wood expected to incur $707,200 of manufacturing overhead cost, 41,600 of direct labor hours, and $915,200 of direct labor cost during the year (the cost of direct labor is $22 per hour) The company allocates manufacturing overhead on the basis of direct labor hours During January, All Wood completed Job 302. The job used 165 direct labor hours and required $14,800 of direct materials. The City of...
i Requirements 1. Calculate the manufacturing cost of Job 308. 2. How much will the City of Hamptonville pay for this playground equipment? Print Done Park Industries manufactures custom-designed playground equipment for schools and city parks. Park expected to incur $784,700 of manufacturing overhead cost, 41,300 of direct labor hours, and $908,600 of direct labor cost during the year (the cost of direct laboris $22 per hour). The company allocates manufacturing overhead on the basis of direct labor hours. During...
E3-19A (similar to) Question Help * PG Industries manufactures custom-designed playground equipment for schools and city parks. PG expected to incur $533,000 of manufacturing overhead cost 41,000 of direct labor hours, and $820,000 of direct labor cost during the year (the cost of direct labor is $20 per hour) The company allocates manufacturing overhead on the basis of direct labor hours. During December, PG completed Job 309 The job used 165 direct labor hours and required $15.400 of direct materials....
Requirements: 1. Calculate the manufacturing cost of Job 302. 2. How much will the City of Northville pay for this playground equipment? All Wood Industries manufactures custom-designed playground equipment for schools and city parks. All Wood expected to incur $627,000 of manufacturing overhead cost, 41,800 of direct labor hours, and $836,000 of direct labor cost during the year (the cost of direct labor is $20 per hour). The company allocates manufacturing overhead on the basis of direct labor hours. During...
E3-19A (similar to) Question Help Love It Industries manufactures custom-designed playground equipment for schools and city parks. Love It expected to incur $627,000 of manufacturing overhead cost, 41,800 of direct labor hours, and $1,254,000 of direct labor cost during the year (the cost of direct labor is $30 per hour). The company allocates manufacturing overhead on the basis of direct labor hours. During March, Love It completed Job 308. The job used 200 direct labor hours and required $15,100 of...
b. The company's ABC system uses two indirect-cost pools. One cost pool is for set up costs and the other for advertising, Zany Brainy allocates set up costs to the two lamps based on setup labour-hours and advertising costs based on the direct manufacturing labour-hours. Under ABC system, determine total product cost per unit of each of the company's two products. (25 marks) Answer following questions based on the scenario of Zany Brainy: Zany Brainy Corp. manufactures two types of...
Rooftop Solar estimated the following annual costs: Expected annual direct labor hours 12,000 Expected annual direct labor cost $198,000 Expected machine hours 10,400 Expected material cost for the year $65,000 Expected manufacturing overhead $218,400 Job 612 used $350 of direct materials, 26 direct labor hours, and 14 machine hours. Actual labor cost is $17 per hour. a. If Rooftop Solar allocates overhead based upon machine hours, how much is the overhead rate? b. Determine the cost of job 612.