Question

Consider a single activity “Precast Wall Panels” of a certain project. Assume that the quantity of...

Consider a single activity “Precast Wall Panels” of a certain project. Assume that the quantity of this activity is 2000 ft2 of 8’ X 8’ X 4” wall panels. Assume that crew C-11 will be used for this activity and that this crew is composed of one foreman, 6 workers, one equipment operator, and one 150-ton crane. Use the following data to estimate the unit price and total price of this activity and the time needed to finish the activity: - The daily output for crew C-11 is 320 ft2 . - Direct hourly rates for crew C-11 are as follows: - Foreman: $45 per hour. - Worker: $40 per hour. - Equipment operator: $60 per hour. - 150-ton crane: $235 per hour. - Material cost is $20/ft2 . - Total direct cost for this project: $1,000,000. - Project overheads: $100,000. - General overheads to be distributed over all company projects: $2,000,000. - Total direct cost for all projects: $10,000,000. - Assume 10% profit. - Assume 8 work hours per day..

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Hi,

Solution as follows:

STEP 1: Calculation of percentage of project overheads:

Given Data:

  • Total Direct costs for this project = $1,000,000
  • Project overheads = $100,000

STEP 2: Calculation of percentage of general overheads:

Given Data:

  • General overheads = $2,000,000
  • Total Direct costs for all projects = $10,000,000

STEP 3: Calculation of direct cost of crew for one hour:

Given Data:

  • Crew C-11 Size = 1 foreman + 6 workers + 1 operator + 1 crane
  • Rate of foreman = $45 per hr
  • Rate of worker = $40 per hr
  • Rate of operator = $60 per hour
  • Rate of Crane = $235 per hour

Hourly cost of crew calculated in below table:

Sl. No.

Particulars

Unit Rate

Unit

Quantity

Cost

1

foreman

$45

per hour

1

$45

2

worker

$40

per hour

6

$240

3

operator

$60

per hour

1

$60

4

Crane

$235

per hour

1

$235

Total cost per hour

$580

STEP 4: Calculation of required working hours of crew:

Given Data:

  • Total Quantity = 2000 sq.ft
  • Daily output of crew = 320 sq.ft per day
  • Working hours = 8 hours per day

STEP 5: Estimation of unit price and total price for the activity:

Given Data:

  • Total Quantity = 2000 sq.ft
  • Material cost = $20 per sq.ft
  • Profit = 10%
  • General overheads = 20% [Calculated above]
  • Project overheads = 10% [Calculated above]
  • Required time = 50 hours[Calculated above]
  • Crew rate = $580 per hour[Calculated above]

Total price and unit price calculated in below table:

Sl. No.

Particulars

Unit Rate

Unit

Quantity

Cost

1

Material Cost of Panels

$20

sq.ft

2000

$40,000

2

Labor Cost of Crew C-11

$580

per hour

50

$29,000

Total Direct Costs

A

$69,000

General overheads @ 20%

B

=

Ax20%

$13,800

Project overheads @ 10%

C

=

Ax10%

$6,900

Total Costs (Direct + Indirect)

D

=

A+B+C

$89,700

Profit @ 10% of total costs

E

=

Dx10%

$8,970

Total Price for the activity

F

=

D+E

$98,670

Total Quantity (Sq.ft)

G

2,000

Unit Price (Per sq.ft)

H=F/G

$49.34

Answers:

Total time = 50 hours i.e. 6 days 2 hours

Total price = $98,670

Unit price = $49.34 per sq.ft

Add a comment
Know the answer?
Add Answer to:
Consider a single activity “Precast Wall Panels” of a certain project. Assume that the quantity of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In a construction project, the unit labor cost for pouring concrete is $8.25 per cubic yard....

    In a construction project, the unit labor cost for pouring concrete is $8.25 per cubic yard. One activity needs 125 cubic yard of concrete with the material cost of $60 per cubic yard of concrete. If a crew of 3 laborers is working normal 8-hour days and is paid $11/hr per worker, what is the activity’s approximate duration to the nearest integer

  • The Armstrong Manufacturing Company is considering two projects, however only one project can be chosen. Prepare an incremental analysis using the data provided. Include internal rate of return (IRR)...

    The Armstrong Manufacturing Company is considering two projects, however only one project can be chosen. Prepare an incremental analysis using the data provided. Include internal rate of return (IRR) for each alternative. Prepare a report to be presented to vice-president of manufacturing with your recommendation. The company uses a depreciation. The company’s effective income tax rate is 35%. The Armstrong Manufacturing Company is considering two projects, however only one project can be chosen. Prepare an incremental analysis using the data...

  • Klumper Corporation is a diversified manufacturer of industrial goods. The company’s activity-based costing system contains the...

    Klumper Corporation is a diversified manufacturer of industrial goods. The company’s activity-based costing system contains the following six activity cost pools and activity rates: Activity Cost Pool Activity Rates Supporting direct labor $ 8 per direct labor-hour Machine processing $ 5 per machine-hour Machine setups $ 40 per setup Production orders $ 150 per order Shipments $ 120 per shipment Product sustaining $ 800 per product Activity data have been supplied for the following two products: Total Expected Activity K425...

  • JAVA language CSE110 Principles of Programming Assignment 02.10 pts Assignment 02:100 pts CSE110 Principles of Programming...

    JAVA language CSE110 Principles of Programming Assignment 02.10 pts Assignment 02:100 pts CSE110 Principles of Programming Test #2 Given Inputs Length of road project (miles) : 3 Number of lanes Depth of asphalt (inches) 18 Days to complete project : 50 1. The trucks hauling asphalt have a maximum capacity of 5 US tons (10,000 lbs 2. The standard road lane is 12 feet wide. 3. Asphalt welghs 150 lbs per cubic foot 4. Asphalt costs $200 per ton 5....

  • Your company makes Product 1 and Product 2 using Activity A and Activity B. The cost...

    Your company makes Product 1 and Product 2 using Activity A and Activity B. The cost driver for Activity A is direct labor hours and the cost driver for Activity B is number of setups. Activity A costs $125,000 and Activity B costs $675,000. If Product 1 had activity proportions of 10% for Activity A and 40% for Activity B, then what is the total indirect cost assigned to Product 1? what is the total indirect cost assigned to Product...

  • 12. A slab on grade measures 120 long x 60" wide x 2' 6" thick. What is the cost to form the slab...

    12. A slab on grade measures 120 long x 60" wide x 2' 6" thick. What is the cost to form the slab if formwork costs S1 per square foot of contact area? A. $72 B.S90 C.S162 D.S180 13. A place concrete' activity requires the placement of 2,080 cubic yards. If the individual production rate is 2 cubic yards per workhour per person, with a 10-person crew and 8-hour workday, how many days are needed to complete this activity? A....

  • Your company is planning to bid a contract to lay 60,000 square yards of asphalt pavement...

    Your company is planning to bid a contract to lay 60,000 square yards of asphalt pavement to improve the Carolinas airport runway. You have been asked to estimate the duration and direct equipment cost of the project. The contract specifications require that the pavement be 3 inches thick after compaction. The mix design is such that you estimate the asphalt to weigh 3,100 pounds per cubic yard when loose and 3,900 pounds per cubic yard after it has been compacted....

  • Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity...

    Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in Table 1. If the indirect costs for each duration is as follows, compute the direct and total cost for each duration. What is the optimum cost-time schedule? Indirect cost 27 weeks – RM 350 26 weeks – RM 270 25 weeks – RM 160 24 weeks – RM 100 12 weeks – RM 70 (12...

  • Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing...

    Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $240,000, consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Assembly setups $63,000 Setup hours Materials handling 33,000 Number of moves Assembly 120,000 Assembly hours Maintenance 24,000 Maintenance hours Total $240,000 Activity Level 1,500 300 12,000 1,200 Total direct labor hours used during the month were 8,000....

  • hiii please help me $200 each $5,000 $150 each $4,000 $100 each $1 each bike Let...

    hiii please help me $200 each $5,000 $150 each $4,000 $100 each $1 each bike Let build a car / bike and dertemine its cost and selling price: 1. Cash balance $500,000 2. Purchase direct material to build the bike. 3. Two assembly workers to build the bike get paid $40 per hour. It will take 8 hours to build a 4. One Production Manager get paid $500 per day. 5. One Factory supervisor to perform quality control on the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT