Consider a single activity “Precast Wall Panels” of a certain project. Assume that the quantity of this activity is 2000 ft2 of 8’ X 8’ X 4” wall panels. Assume that crew C-11 will be used for this activity and that this crew is composed of one foreman, 6 workers, one equipment operator, and one 150-ton crane. Use the following data to estimate the unit price and total price of this activity and the time needed to finish the activity: - The daily output for crew C-11 is 320 ft2 . - Direct hourly rates for crew C-11 are as follows: - Foreman: $45 per hour. - Worker: $40 per hour. - Equipment operator: $60 per hour. - 150-ton crane: $235 per hour. - Material cost is $20/ft2 . - Total direct cost for this project: $1,000,000. - Project overheads: $100,000. - General overheads to be distributed over all company projects: $2,000,000. - Total direct cost for all projects: $10,000,000. - Assume 10% profit. - Assume 8 work hours per day..
Hi,
Solution as follows:
STEP 1: Calculation of percentage of project overheads:
Given Data:
STEP 2: Calculation of percentage of general overheads:
Given Data:
STEP 3: Calculation of direct cost of crew for one hour:
Given Data:
Hourly cost of crew calculated in below table:
Sl. No. |
Particulars |
Unit Rate |
Unit |
Quantity |
Cost |
1 |
foreman |
$45 |
per hour |
1 |
$45 |
2 |
worker |
$40 |
per hour |
6 |
$240 |
3 |
operator |
$60 |
per hour |
1 |
$60 |
4 |
Crane |
$235 |
per hour |
1 |
$235 |
Total cost per hour |
$580 |
STEP 4: Calculation of required working hours of crew:
Given Data:
STEP 5: Estimation of unit price and total price for the activity:
Given Data:
Total price and unit price calculated in below table:
Sl. No. |
Particulars |
Unit Rate |
Unit |
Quantity |
Cost |
1 |
Material Cost of Panels |
$20 |
sq.ft |
2000 |
$40,000 |
2 |
Labor Cost of Crew C-11 |
$580 |
per hour |
50 |
$29,000 |
Total Direct Costs |
A |
$69,000 |
|||
General overheads @ 20% |
B |
= |
Ax20% |
$13,800 |
|
Project overheads @ 10% |
C |
= |
Ax10% |
$6,900 |
|
Total Costs (Direct + Indirect) |
D |
= |
A+B+C |
$89,700 |
|
Profit @ 10% of total costs |
E |
= |
Dx10% |
$8,970 |
|
Total Price for the activity |
F |
= |
D+E |
$98,670 |
|
Total Quantity (Sq.ft) |
G |
2,000 |
|||
Unit Price (Per sq.ft) |
H=F/G |
$49.34 |
Answers:
Total time = 50 hours i.e. 6 days 2 hours
Total price = $98,670
Unit price = $49.34 per sq.ft
Consider a single activity “Precast Wall Panels” of a certain project. Assume that the quantity of...
In a construction project, the unit labor cost for pouring concrete is $8.25 per cubic yard. One activity needs 125 cubic yard of concrete with the material cost of $60 per cubic yard of concrete. If a crew of 3 laborers is working normal 8-hour days and is paid $11/hr per worker, what is the activity’s approximate duration to the nearest integer
The Armstrong Manufacturing Company is considering two projects, however only one project can be chosen. Prepare an incremental analysis using the data provided. Include internal rate of return (IRR) for each alternative. Prepare a report to be presented to vice-president of manufacturing with your recommendation. The company uses a depreciation. The company’s effective income tax rate is 35%. The Armstrong Manufacturing Company is considering two projects, however only one project can be chosen. Prepare an incremental analysis using the data...
Klumper Corporation is a diversified manufacturer of industrial goods. The company’s activity-based costing system contains the following six activity cost pools and activity rates: Activity Cost Pool Activity Rates Supporting direct labor $ 8 per direct labor-hour Machine processing $ 5 per machine-hour Machine setups $ 40 per setup Production orders $ 150 per order Shipments $ 120 per shipment Product sustaining $ 800 per product Activity data have been supplied for the following two products: Total Expected Activity K425...
JAVA language CSE110 Principles of Programming Assignment 02.10 pts Assignment 02:100 pts CSE110 Principles of Programming Test #2 Given Inputs Length of road project (miles) : 3 Number of lanes Depth of asphalt (inches) 18 Days to complete project : 50 1. The trucks hauling asphalt have a maximum capacity of 5 US tons (10,000 lbs 2. The standard road lane is 12 feet wide. 3. Asphalt welghs 150 lbs per cubic foot 4. Asphalt costs $200 per ton 5....
Your company makes Product 1 and Product 2 using Activity A and Activity B. The cost driver for Activity A is direct labor hours and the cost driver for Activity B is number of setups. Activity A costs $125,000 and Activity B costs $675,000. If Product 1 had activity proportions of 10% for Activity A and 40% for Activity B, then what is the total indirect cost assigned to Product 1? what is the total indirect cost assigned to Product...
12. A slab on grade measures 120 long x 60" wide x 2' 6" thick. What is the cost to form the slab if formwork costs S1 per square foot of contact area? A. $72 B.S90 C.S162 D.S180 13. A place concrete' activity requires the placement of 2,080 cubic yards. If the individual production rate is 2 cubic yards per workhour per person, with a 10-person crew and 8-hour workday, how many days are needed to complete this activity? A....
Your company is planning to bid a contract to lay 60,000 square yards of asphalt pavement to improve the Carolinas airport runway. You have been asked to estimate the duration and direct equipment cost of the project. The contract specifications require that the pavement be 3 inches thick after compaction. The mix design is such that you estimate the asphalt to weigh 3,100 pounds per cubic yard when loose and 3,900 pounds per cubic yard after it has been compacted....
Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in Table 1. If the indirect costs for each duration is as follows, compute the direct and total cost for each duration. What is the optimum cost-time schedule? Indirect cost 27 weeks – RM 350 26 weeks – RM 270 25 weeks – RM 160 24 weeks – RM 100 12 weeks – RM 70 (12...
Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $240,000, consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Assembly setups $63,000 Setup hours Materials handling 33,000 Number of moves Assembly 120,000 Assembly hours Maintenance 24,000 Maintenance hours Total $240,000 Activity Level 1,500 300 12,000 1,200 Total direct labor hours used during the month were 8,000....
hiii please help me $200 each $5,000 $150 each $4,000 $100 each $1 each bike Let build a car / bike and dertemine its cost and selling price: 1. Cash balance $500,000 2. Purchase direct material to build the bike. 3. Two assembly workers to build the bike get paid $40 per hour. It will take 8 hours to build a 4. One Production Manager get paid $500 per day. 5. One Factory supervisor to perform quality control on the...