Question

Assume Nortel Networks contracted to provide a customer with Internet Infrastructure for $2600,000. The project began In 2018 and was completed In 2019. Data relating to the contract are summarized below: 2018 2819 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year $ 348,90e $1,995,8ee 1, 392,8ee 465,888 1,748,888 274,808 1,818,888 Requlrec 1. Compute the amount of revenue and gross profit or loss to be recognized In 2018 and 2019 assuming Nortel recognizes revenue over time according to percentage of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming this project does not qualify for revenue recognition over time 3. Prepare a partial balance sheet to show how the Information related to this contract would be presented at the end of 2018 assuming Nortel recognizes revenue over time according to percentage of completion. 4. Prepare a partial balance sheet to show how the Information related to this contract would be presented at the end of 2018 assuming this project does not qualify for revenue recognltion over time. Complete this question by entering your answers in the tabs below Required 1Required 2Required 3 Required4 Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming Nortel recognizes revenue over time according to percentage of completion. (Loss amounts should be indicated with a minus sign. Use percentages as calculated and rounded in the table below to arrive at your final answer.) Percentages of completion Choose numerator Choose denominator | : | % complete to date Actual costs to date Estimated total costs 2018 348,0005 1,740,000 20.00% 2019 2018 To date Recognized in prior years Recognized in 2018 Construction revenue Construction expense Gross profit (loss) 520,000 s 348,000 s 172,000 s 520,000 348,000 172,000 2019 To date Recognized in prior years Recognized in 2019 Construction revenue Construction expense Gross profit (loss) 520,000 5 348,000 S 172,000 S (520,000) (348,000) (172,000)Please show all calculations!

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Answer 1.
Percentage of Completion Method
2018 2019
Cost Incurred each year (A)        348,000.00    1,995,000.00
Cost Incurred to date (B)        348,000.00    2,343,000.00
Estimated Costs ©    1,392,000.00                         -  
Total Estimated Costs (D = B + C)    1,740,000.00    2,343,000.00
% Completed (E = B / D) 20.00% 100.00%
Revenue        520,000.00    2,080,000.00
Expenses        348,000.00    1,995,000.00
Gross Profit        172,000.00          85,000.00
Revenue - 2018 = $2,600,000 X 20% = $520,000
Revenue - 2019 = ($2,600,000 X 100%) - $520,000 = $2,080,000
Answer 2.
Completed Contract Method
Year 1 Year 2
Revenue                         -      2,600,000.00
Expenses                         -      2,343,000.00
Gross Profit                         -          257,000.00
Answer 3.
Percentage of Completion Method
Balance Sheet (Partial)
2018 2019
Current Assets
Accounts Receivable    191,000.00        121,000.00
Cost & Profits > Billings      55,000.00        395,000.00
Current Liabilities
Cost & Profits < Billings                     -                           -  
Answer 4.
Completed Contract Method
Balance Sheet (Partial)
2018 2019
Current Assets
Accounts Receivable    191,000.00        121,000.00
Cost & Profits > Billings                     -          629,000.00
Current Liabilities
Cost & Profits < Billings    117,000.00                         -  
Add a comment
Know the answer?
Add Answer to:
Please show all calculations! Assume Nortel Networks contracted to provide a customer with Internet Infrastructure for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Help Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,760,000. The p...

    Help Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,760,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2018 364,000 $2,175,000 1,456,000 520,000 282,000 2019 0 1,780,000 1,830,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2018...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,600,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,600,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 348,000 $ 1,995,000 Estimated costs to complete as of 12/31 1,392,000 0 Billings during the year 465,000 1,740,000 Cash collections during the year 395,000 1,810,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

  • Requirement 3 please Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000....

    Requirement 3 please Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 356,000 $2,135,000 2019 Costs incurred during the year Estinated costs to complete as of 12/31 illings during the year Cash collections during the year 1,424,000 475, 000 1,760,000 278,000 1,820,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year $ 300,000 1,575,000 1,200,000 380,000 1,620,000 250,000 1,750,000 Required 1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,960,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,960,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $2,300,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 380,000 1,520,000 540,000 510,000 1, 820,000 1,850,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,650,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,650,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 352,000 1,408,000 470,000 405,000 2022 $2,025,000 0 1,750,000 1,815,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,720,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405.000 300,000 1.670.000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2.250,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2.250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,720,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405,000 300,000 1,670,000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began in 2016 and was completed in 2017. Data relating to the contract are summarized below: 2016 2017   Costs incurred during the year $ 360,000 $ 2,155,000   Estimated costs to complete as of 12/31 1,440,000 0   Billings during the year 500,000 1,770,000   Cash collections during the year 280,000 1,825,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405,000 300,000 2022 $1,720,000 0 1,670,000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT