a.
Computation of payback periods:
Project X |
Project Y |
|||
Year |
Cash flow |
‘CUM Cash Flow |
Cash flow |
‘CUM Cash Flow |
0 |
($10,000) |
($10,000) |
($10,000) |
($10,000) |
1 |
$6,500 |
($3,500) |
$3,000 |
($7,000) |
2 |
$3,000 |
($500) |
$3,000 |
($4,000) |
3 |
$3,000 |
$2,500 |
$3,000 |
($1,000) |
4 |
$1,000 |
$3,500 |
$3,000 |
$2,000 |
Payback Period = A +B/C
Where,
A = Last period with a negative cumulative cash flow
B = Absolute value of cumulative cash flow at the end of the period A
C = Total cash flow during the period after A
Payback Period for Project X = 2 +│$ (500) │/$ 3,000
= 2 + $ 500/$ 3,000
= 2 + 0.166666667 = 2.166666667 or 2.17 years
Payback Period for Project Y = 3 +│$ (1,000) │/$ 3,000
= 3 + $ 1,000/$ 3,000
= 3 + 0.33333333 = 3.33333333 or 3.33 years
Payback Period of Project X is 2.17 years
Payback Period of Project Y is 3.33 years
Computation of NPV:
Project X |
Project Y |
|||||
Year |
Computation of PV factor |
PV Factor @ 12 % (F) |
Cash flow CX |
PV (= CX x F) |
Cash flow CY |
PV (= CY x F) |
0 |
1/(1+0.12)^0 |
1 |
($10,000) |
($10,000) |
($10,000) |
($10,000) |
1 |
1/(1+0.12)^1 |
0.8928571428571 |
$6,500 |
$5,803.5714 |
$3,000 |
$2,678.5714 |
2 |
1/(1+0.12)^2 |
0.7971938775510 |
$3,000 |
$2,391.5816 |
$3,000 |
$2,391.5816 |
3 |
1/(1+0.12)^3 |
0.7117802478134 |
$3,000 |
$2,135.3407 |
$3,000 |
$2,135.3407 |
4 |
1/(1+0.12)^4 |
0.6355180784048 |
$1,000 |
$635.5181 |
$3,000 |
$1,906.5542 |
NPVX |
$966.0119 |
NPVY |
($887.9520) |
NPV of Project X is $ 966.0119 or $ 966.01
NPV of Project Y is - $ 887.9520 or - $ 887.95
Computation of IRRs using excel:
A |
B |
C |
|
1 |
Year |
Cash flow Project X |
Cash flow Project Y |
2 |
0 |
($10,000) |
($10,000) |
3 |
1 |
$6,500 |
$3,000 |
4 |
2 |
$3,000 |
$3,000 |
5 |
3 |
$3,000 |
$3,000 |
6 |
4 |
$1,000 |
$3,000 |
7 |
IRR |
18.03% |
7.71% |
If excel sheet looks like above table,
To compute IRR for Project X insert formula “=IRR(B2:B6) in cell B7 to get IRR as 18.03 %
To compute IRR for Project Y insert formula “=IRR(C2:C6) in cell C7 to get IRR as 7.71 %
IRR of Project X is 18.03 %
IRR of Project Y is 7.71 %
Project X is financially acceptable as it has positive NPV and IRR is higher than required rate of return.
Project Y has negative NPV and its IRR is lower than firm’s required cost of capital. Hence it is not advisable to accept Project Y.
Also payback period of Project X is less than Project Y.
Table Tools References Mailings Review View Help Design Layout Tell me Problem 3 Assume that you...
please solve and explain how to find IRR Only. and draw the time
line for this problem! thanks!
9.6 Assume that you are the chief financial officer at Porter Memorial Hospital. The CEO has asked you to analyze two proposed capital investments-project X and project Y. Each project requires a net investment outlay of $10,000, and the opportunity cost of capital for each project is 12 percent. The projects' expected net cash flows are as follows: Year Project X ($)...
draw time line for answer a
9.6 Assume that you are the chief financial officer at Porter Memorial Hospital. The CEO has asked you to analyze two proposed capital investments - project X and project Y. Each project requires a net investment outlay of $10,000, and the opportunity cost of capital for each project is 12 percent. The projects' expected net cash flows are as follows: Year Project X ($) (10,000) 6,500 3,000 3,000 1,000 Project Y ($) (10,000) 3,000...
draw time line for answer a
Assume that you are the chief financial officer at Porter Memorial Hospital. The CEO has asked you to analyze two proposed capital investments-project X and project Y. Each project requires a net investment outlay of $10,000, and the opportunity cost of capital for each project is 12 percent. The projects' expected net cash flows are as follows: 9.6 Project X (S) (10,000) Year Project Y ($) (10,000) 6,500 1 3,000 3,000 3,000 3,000 3,000...
Please show all work & calculations.
Assume that you are the chief financial officer at Porter Memorial Hospital. The CEO has asked you to analyze two proposed capital investments - Project X and Project Y. Each project requires a net investment outlay of $10,000, and the cost of capital for each project is 12 percent. The project's expected net cash flows are as follows: Year 0 1 Project X ($10,000) $6,500 $3,000 $3,000 $1,000 Project Y ($10,000) $3,000 $3,000 $3,000...
n y u MUCOLUNS I Deude controversy 5 - MICH... 5 s Question 10 4 pts Porter Memorial Hospital is considering two proposed capital investments, Project X and Project Y. Please see the data for the two projects in the attached Excel sheet and answer the following questions. Show your work in Excel. a) Calculate each project's net present value (NPV) and internal rate of return (IRR). b) Which project is financially acceptable? E TERES MILF LinkCase Report 3 Q10.xlsx...
Tools Table Window Help ne Insert Draw Design Layout References MailingsShare Comments Styles Styles Pane In reference to this video, suppose the fim's WACC exceeds the IRR for beth projects L and S if the projects are mutually exclaive, which project should the firm invest in? What if the projects are not matually exclusive, then which projects) should the firm invest in? (Hint If the WACC is greater than both projects' IRR, then both projects would delivery negative NPV.) 11-7...
You are a financial analyst for the Brittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments: Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each is 12%. The projects' expected net cash flows are shown in the table below. Expected Net Cash Flows Year Project X Project Y 0 – $10,000 – $10,000 1 6,500 3,500 2 3,000 3,500 3 3,000 3,500 4 1,000...
References Mailings Review View Help Grammarly Tell me what you want to do You-Bee Enterprises, Inc. is considering a new three-year expansion project with the relevant cash flows below. (70 points) 4. Calculate the project's NPV and IRR. Should You-Bee accept or reject this project based on your calculations? Please use the Excel template provided to answer this problem. The required return is 12 %. The tax rate is 21%. The project requires an initial fixed asset investment of $2.32...
KEY TERMS Define the following terms: a. Capital budgeting; strategic business plan b. Net present value (NPV) c. Internal rate of return (IRR) d. NPV profile; crossover rate e. Mutually exclusive projects; independent projects f. Nonnormal cash flows; normal cash flows; multiple IRRS g. Modified internal rate of return (MIRR) h. Payback period; discounted payback CAPITAL BUDGETING CRITERIA You must analyze two projects, X and Y. Each project costs $10,000, and the firm's WACC is 12%. The expected cash flows...
Flooding activity online Compatibility Mode Saved Picture Tools joykaffenber Design Layout References Mailings Review View Help Format AaBbCel AaBbC AaBbCcl AaBbCcl Aa Heading 1 Paragraph Font Styles GLY 120This Dangerous Earth Flooding Activity The Corps of Engineers Presents: H:0 Overload Assignment: Floodplain Management Details: You are the developer of a new community and must decide where to construct the following: a city park, a hospital, and a self storage business. The locations chosen for each construction site should correspond with...