Help solve ONLY (b) with excel. Please show step by step
Excel setup:
Solver input (the new constraint is highlighted)
Solution:
Proj-1 | Proj-2 | Proj-3 | Proj-4 | Proj-5 | Proj-6 | |||
Proportion | 100.00% | 100.00% | 100.00% | 100.00% | 3.17% | 100.00% | ||
Return | 32.40 | 35.80 | 17.75 | 14.80 | 18.20 | 12.35 | 113.68 | |
OUTLAY | Proj-1 | Proj-2 | Proj-3 | Proj-4 | Proj-5 | Proj-6 | Consumed | Available |
Year-1 | 10.5 | 8.3 | 10.2 | 7.2 | 12.3 | 9.2 | 45.79 | 60 |
Year-2 | 14.4 | 12.6 | 14.2 | 10.5 | 10.1 | 7.8 | 59.82 | 70 |
Year-3 | 2.2 | 9.5 | 5.6 | 7.5 | 8.3 | 6.9 | 31.96 | 35 |
Year-4 | 2.4 | 3.1 | 4.2 | 5.0 | 6.3 | 5.1 | 20.00 | 20 |
Help solve ONLY (b) with excel. Please show step by step 2-40. Fox Enterprises is considering...