a)Total cost of hauling of refuse from site A to power plant = Hauling cost/yd3 -mile * total solid waste *distance between Site A annd power plant + Annual Rental fee for solid waste site = 1.50*190000*4 +1000= $11,41,000
Similarly, total cost of hauling of solid waste refuse from site B to power plant = 1.50*190000*3 +9000= $86,4000
Also total revenue from power plant for hauling of solid waste = 7.5*190000= $14,25,000 As total revenue of the city for hauling 90,000 cubic yards of solid waste from site A or site B to power plant is same.
By comparing total hauling cost of solid wastes for site A and site B, we find overhauling cost of solid waste for site B is lower than Site A. Therefore solid wastes should be located in Site B.
b) Breakeven demand is the demand at breakeven point where total revenue-total cost = 0
Here total cost for the selected firm is $86,4000. therefore total revenue at breakeven point is also = $86,4000
Also Average revenue = $7.50/per cubic yard of solid waste
Therefore breakeven demand of delivered solid waste refuse for the selected site = 864000/7.50 = 11,5200 cubic yards.
Engineering economics aste site for a city must be located at Site A or Site B....